  RH-ISAC, Page 101 of 140  Not logged in ELOG logo
  ID Date Author Categorydown Type Module Target/Number Subject Text Attachments
  2211   Wednesday, April 21, 2021, 11:18 David WangCoolingMaintenance  Refilling high active wtaer system and starting HA water pumps. High active water system is refilled. Air
are drained out of  system before pump
to be started. Following sequence are used
  
  2305   Tuesday, February 15, 2022, 11:18 Frank SongCoolingRepair  Replace 2 leak valves on high active water system The valves #V10 & V11 beside
high active water pumps were replaced in
Target Hall, pics attached.
 v10_v11.jpgv10.jpgv11.jpg 
  2306   Wednesday, February 16, 2022, 15:19 Frank SongCoolingRepair  high active cooling water valves repaired/replaced A 3/8 inch drain valve on return
cooling line was replaced in ITE. In the
meantime two 1/2 inch valves labeled FEBIAD
 RETURN_drain_valve_in_ITE.jpgFEBIAD_COIL_in_ITW.jpgENTRANCE_COLLIMATOR_RETURN_in_ITW.jpgMAIN_S_and_R_VALVES_in_ITW.jpg 
  2419   Wednesday, March 01, 2023, 09:27 David WangCoolingMaintenance  Two filters on HALCW resin circuit have been replaced. Two filters on HALCW resin circuit have
been replaced. O-ring 235# were changed on
both filter cartridge houses.  25micron 
  
  2420   Wednesday, March 01, 2023, 09:34 David WangCoolingMaintenance  Visual inspection of HALCW for possible small water leak or drip. I visually inspected HALCW system including
water station section, both target pits,
and de-ionizer system.  No small leak
  
  2424   Wednesday, March 08, 2023, 06:32 David WangCoolingMaintenance  HALCW flow sensors replacement. HALCW flow sensors replacement job is done.
All ITE/ITW(except ITE HS) return line water
flow sensors including paddle wheels and
  
  2425   Wednesday, March 08, 2023, 09:19 David WangCoolingStandard Operation  HALCW ITC:MP1/MP2 motor phase current measurement. HALCW ITC:MP1/MP2 motor phase current measurement
is done by Joel from electrician group. MP1:17.1A/17.2A/16.7A. 
MP2: 17.9A/17.9A/17.3A.   19.5A
  
  2426   Wednesday, March 08, 2023, 13:57 David WangCoolingStandard Operation  HALCW ITC:MP1/MP2 pump and motor temerature measurementsHALCW ITC:MP1/MP2 pump and motor temperature
measurements result:
MP1: pump discharging  port:
  
  2433   Monday, April 24, 2023, 10:18 David WangCoolingMaintenance  HALCW flowmeter transmotters inspetion and calibration. ITW, ITE, ITW +ITE total , and low active
cooling water return flow meter transmitters
are inspected and calibrated.  Result:
  
  2495   Friday, October 13, 2023, 11:46 David WangCoolingMaintenance  HALCW system O2 sensor service and calibration.HALCW system O2 sensor service and calibration
were done in Sep 26th. electrolyte and membrane
on rose mount sensor 499ADO were refilled
  
  2547   Friday, February 16, 2024, 11:48 David WangCoolingMaintenance  high active water transferr to holding tank100 liters of high active water from HALCW
system( mostly from s-tank and pipe lines
closing to pumps) are transferred to holding
  
  2559   Thursday, April 04, 2024, 13:10 David WangCoolingMaintenance  high active water refurbishment, reinstallation, and test operation. both high active pumps ITC:MP1 and MP2
are refurbished by RH group Maico and Peter.
Pumps have been installed back to system
  
  2560   Monday, April 08, 2024, 09:29 David WangCoolingStandard Operation  HALCW system general inspection. water are supplied to both ITE and ITW.
I did a general inspection on HALCW system.
Two small leaks on 2" shut off valves
  
  2692   Wednesday, September 25, 2024, 07:25 David WangCoolingMaintenance  HALCW O2 level sensor maintenance. HALCW O2 level sensor annual maintenance
is done. sensor membrane has been changed
and electrolyte has been refilled. gauge
  
  2763   Monday, February 03, 2025, 13:10 David WangCoolingStandard Operation  HALCW pump ITC:MP1 has been started. HALCW pump ITC:MP1 has been started. water
are supplied to both ITE and ITW system.
all water signals for individual circuits
  
  2776   Friday, February 21, 2025, 09:18 David WangCoolingStandard Operation  HALCW pump ITC:MP1 and MP2 phase current draw measurement.HALCW pump ITC:MP1 and MP2 phase current
draw measurement result: water supplied to
both station. MP1: Black 17.0A, blue 16.9A,
  
  2777   Monday, February 24, 2025, 11:15 David WangCoolingMaintenance   ITW/ITE water system manual valves water small leak inspection and repairing.  ITW/ITE water system manual valves
water small leak inspection and repairing
job is done. Small water drippings have been
  
  2781   Monday, March 03, 2025, 15:33 David WangCoolingMaintenance  HALCW resin can loop two filters have been replaced. HALCW resin can loop two filters have been
replaced. no water leak on after job check.
  
  2783   Friday, March 07, 2025, 09:16 David WangCoolingMaintenance  Service of 28 female Parker 1/4 quick connectors in ITW and ITEService of  Parker 1/4 quick connectors
in ITW and ITE have been done.  all
28 female connectors were serviced. o- rings
  
  4   Thursday, June 30, 2011, 16:04 Pierre BricaultConditioning StationRepairTM1 TM1 statusFriday June 24 2011
The target module has been moved
to the Conditioning Station (CS)
  