ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
908
|
Friday, May 01, 2015, 13:48 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 update | Target Hall Scheduled Activities
April 07 - June 26 2015 update.
2015-05-01. All TH scheduled |
|
907
|
Friday, May 01, 2015, 08:27 |
chad fisher | South Hot-Cell | Repair | TM2 | | Containment Box Removal | Containment box has been removed in preparation
for wire replacement. |
|
906
|
Thursday, April 30, 2015, 08:50 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | No target | Module move | TM#2 with no source tray has been moved
from the north east silo to the south hot
cell. |
|
905
|
Tuesday, April 28, 2015, 17:17 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | TM1 has been connected in ITW. | TM1 has been connected in ITW. Five turbo
pumps have been started. The TM1 containment
box window line is capped on the service |
|
904
|
Tuesday, April 28, 2015, 11:14 |
Travis Cave | ITW | Standard Operation | TM1 | UC#12 | Module move | TM#1 with UC#12 has been moved from the
conditioning station to the west target station. |
|
903
|
Tuesday, April 28, 2015, 11:09 |
Anders Mjos | ITW | Maintenance | | | Resistance measured of TGHT and TBHT lines to ITW | The new TBHT and TGHT power supplies were
brough up to high current; 350 A and 420
A respectively. The TGHT power supply was |
|
902
|
Tuesday, April 28, 2015, 10:26 |
David Wang | ITW | Standard Operation | TM1 | UCx12 | ITW target pit o-ring seal replacement. | Dan and I replaced ITW target pit o-ring
seal(.275DIA X42"ID). It is an annual
job before first beam to ITW. The old o-ring |
|
901
|
Tuesday, April 28, 2015, 10:21 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | CS and TM1 was vented with Argon gas | Dan and I vented CS and TM1 with Argon
gas before it is moved this morning. |
|
900
|
Monday, April 27, 2015, 17:09 |
Grant Minor | ITE | Development | TM2 | | TM2 - New Source Tray - Water Block Seal Groove Inspection Report | The water blocks soldered to the TM2 cooling
lines (see Ref. Assy. ITA6144) were inspected.
See attached inspection reports and |
|
899
|
Monday, April 27, 2015, 16:12 |
Keith C Ng | South Hot-Cell | Development | TM2 | | Ceramic Standoffs in TM2 source tray steerer assembly | On drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001". |
|
898
|
Monday, April 27, 2015, 10:28 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | TM4 has been partially disconnected at CS. | TM1 has been partially disconnected at
CS for tomorrow move. The CS TP1S is still
running and will be stopped and disconnected |
|
897
|
Thursday, April 23, 2015, 12:56 |
Anders Mjos | Conditioning Station | Maintenance | TM1 | | IG1 Good Vacuum limit changed | Changed by Dave Morris.
New value is 1E-5 T (old value was
7.09E-5 T) |
|
896
|
Thursday, April 23, 2015, 09:08 |
David Wang | Conditioning Station | Maintenance | TM1 | UCx12 | Huge Leak on TM1 contaiment box window. | There is a huge leak on TM1 containment
box window. I did a 70 psi helium pressure
test on all TM1 water circuits this morning. |
|
895
|
Wednesday, April 22, 2015, 11:05 |
David Wang | Conditioning Station | Standard Operation | TM1 | | electrical check on TM1 at CS under vacuum | I did an electrical check on TM1 at CS.
The resistance check:A-B 3.918m ohm, A-C
5.905m ohm,A-D 4.070m ohm,B-C5.462m ohm,B-D3.633m |
|
894
|
Tuesday, April 21, 2015, 17:14 |
Isaac Earle | South Hot-Cell | Standard Operation | TM1 | UC#12 | UC#12 Installed in TM1 | On Friday April 17th, UC#12 target was
installed in TM1. One of the copper
water lines was bent slightly as the target |
|
893
|
Tuesday, April 21, 2015, 13:01 |
Grant Minor | ITW | Development | TM2 | | TM2 MK4 Optics Tray - banana plug bore modification (on bench) | The MK4 optics tray prepared for TM2 (as
per ITA6082) had an undersized bore for the
banana plug, making insertion of the plug |
|
892
|
Monday, April 20, 2015, 10:22 |
David Wang | Conditioning Station | Standard Operation | TM1 | UCx12 | TM1 with UCx12 has been connected to CS and ready for conditioing. | The TH will be locked during the TM1 conditioning
time due to an interference issue between
CS HV cover and a gas analysis valve on top |
|
891
|
Monday, April 20, 2015, 10:12 |
Anders Mjos | Conditioning Station | Standard Operation | TM1 | UC#12 | Conditioning UC#12 | Monday, April 20, 2015, 09:35: Started
cooling water circulation
HV cover did not fit due to interference |
|
890
|
Monday, April 20, 2015, 07:27 |
David Wang | ITE | Standard Operation | TM4 | | Target Hall Scheduled Activities April 07 - June 26 2015 | Weekly target hall schedule update.2015-04-20
weekly target hall schedule update
2015-04-27 attachments 3,4. |
|
889
|
Friday, April 17, 2015, 14:04 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#12 | Module move | TM#1 with UCx#12 has been moved from the
south hot cell to the conditioning station. |
|