Sunday, April 05, 2020, 13:24, Dan McDonald, Elevation Jack, Maintenance, Elevating system station swap 2019-2020
|
Station 11-12 where swapped for station 13-14 during 2018-2019 shutdown. Once lock out and motor disconnect was complete we commenced removal of spares
and installation of original equipment. Station 13 was swapped in for station 3 and the upper bearing was serviced. In addition to regular maintenance
we built and installed a cover for the void in between station 10-11, this void in shielding measured approx 2'x4'. RH borrowed a demo Milwaukee 1' cordless |
Thursday, February 08, 2024, 08:50, Adam Newsome, Elevation Jack, Maintenance, Elevating system - station 10 motor contactor issue
|
It was observed during lid up operation on 2024-02-08, approximately halfway through raising the lid, that the motor contactor for station 10 located
within its small motor panel stopped functioning. The symptoms observed were: entire system stopped since station 10 lagged behind (approx. 150 counts
on counter), station 10 could not be jogged locally in either direction, the control signal to activate the motor was being sent to the contactor when |
Wednesday, February 07, 2024, 12:04, Adam Newsome, Elevation Jack, Repair, Elevating system - brake master relay fuse issue
|
It was observed when attempting lid up operation on 2024-02-06 that the brakes for each of the jacks were not operating correctly. It appeared that power
was not being applied so the brakes were stuck in the engaged state. This ultimately resulted in issues with the lid up operation.
The issue was traced to relay A1 (the master brake power relay) not toggling as expected, despite the relevant control signals being present to |
Monday, January 20, 2025, 13:55, Adam Newsome, Elevation Jack, Maintenance, Elevating System MRO - 2025  
|
Elevating System MRO was started Jan. 16 by R. Sykes, M. Dalla Valle, P. Hall-Patch under work permit C2025-01-16-3.
The plan for this year includes:
Remove station 5 from service and move to shop for maintenance
Remove station 7 (spare) and move to station 5
|
Friday, February 03, 2023, 08:27, Eric Lahe, Elevation Jack, Maintenance, Elevating System Jack Inspection
|
Annual Jack Inspection: The annual elevation system inspection has been completed (Jan 31,2023).
At station 1, Highfield gear Jack 13R needs a coupler seal replacement. It is ok for this shutdown, but should be replaced before next shutdown. |
Wednesday, January 31, 2024, 15:06, Eric Lahe, Elevation Jack, Maintenance, Elevating System - Annual Station Swap 2023-2024
|
The annual elevating system maintenance for the 2023-2024 shutdown following Document-220322,
Work done after electrical lockout of elevating system and motors electrically disconnected:
Work done on Station #1: |
Wednesday, March 09, 2016, 17:09, Ron Kuramoto, Cyclotron, Development, EX4N new housing installation  
|
The new EX4N housing assembly drawing TEC0071 (unfinished) was installed and connected to the EX4 tank side port flange over a 3 day period from Feb29
– Mar 2, 2016. This was a hands on installation spread amongst 5 people with the total accumulated dose was 2.97 mSv. See W/P C2016-02-29-5
|
Wednesday, January 28, 2015, 14:33, Travis Cave, Cyclotron, Standard Operation, Day two of in tank work
|
All copper blocker removed from the cyclotron and first radiation survey done. Shields start tomorrow. |
Thursday, January 29, 2015, 14:53, Travis Cave, Cyclotron, Standard Operation, Day three of in tank work
|
Over 50% of the shields are in some 700's left and the monitor box covers. |
Tuesday, January 27, 2015, 14:40, Travis Cave, Cyclotron, Standard Operation, Day one of in tank work
|
Day one of RH in tank work for the cyclotron (shields and blockers stuff like that) many pictures were taken. |
Friday, January 30, 2015, 15:02, Travis Cave, Cyclotron, Standard Operation, Day four of in tank work
|
All shields, ladders and pothole covers are in. One rad survey left to do. |
Monday, February 02, 2015, 14:28, Travis Cave, Cyclotron, Standard Operation, Day five of in tank work
|
Final Radiation Survey done. All in tank work completed bridge removed from the tank. |
Wednesday, February 03, 2016, 08:16, Dan McDonald, Cyclotron, Standard Operation, Cyclotron lid up
|
Lid up procedure Started at 12:00pm. Initial numbers. # 1-47,2-49,3-45,4-47,5-47,6-47,7-49,8-45,9-50,10-50,11-51,12-49. After a number of unsuccessful
attempts at jogging the system and trouble shooting it was decided to suspend operations record numbers and resume on Feb 2nd. Final numbers for
Feb 1st #1-1289,2-1297,3-1288,4-1295,5-1283,6-1298,7-1287,8-1289,9-1290,10-1296,11-1287,12-1296. |
Friday, July 04, 2014, 07:21, Dan McDonald, Elevation Jack, Standard Operation, Cyclotron lid down July-2- 2014
|
Cyclotron lid down was successfully completed on July 2 2014. Lid went partially down before jack nine had to be jogged to catch up to system. After
thirty min of continual system trips Maico Dalla Valle and I Jogged all stations to 42745. Still encountering continual system trips Gord Roy and Dan Louie
removed and reset all relays in system, lid proceeded to lower with out problem. Final jack position recording done at 19:45. |
Tuesday, January 16, 2018, 13:43, Travis Cave, Cyclotron, Standard Operation, Cyclotron in tank work
|
All cyclotron in tank work has been completed. |
Wednesday, February 05, 2020, 12:37, Adam Newsome, Cyclotron, Development, Cyclotron Vacuum Cleaning Tool - Initial Test
|
The vacuum cleaning tool (TRH1366, vacuum cleaning configuration) was tested in the cyclotron tank. The following test were performed:
1. Access to areas of interest - are we able to reach certain areas?
|
Wednesday, February 05, 2020, 12:44, Adam Newsome, Cyclotron, Development, Cyclotron Small Object Retrival Tool - Intial Test
|
The small object retrieval tool was tested in the cyclotron tank for the first time. At this time, there are no known accessible objects that were requested
to be retrieved. The tool was tested in order to gain confidence in functionality for future tasks, when needed.
|
Wednesday, May 05, 2021, 12:20, Adam Newsome, Infrastructure, Development, Cyclotron RH Control Room: Outlets Installed
|
The following outlets were installed by Electrical Services Group in order to facilitate upgrading power supplies for Cyclotron Remote Handling, as per
Work Request 5289: |
Thursday, July 16, 2020, 11:57, Adam Newsome, Cyclotron, Development, Cyclotron Mockup: Orbital Position Pendant Upgrade 
|
The pendant used for controlling the orbital motion of the bridge mockup was upgraded. Features of the new pendant include:
One cable to controller (formerly two cables required)
Ergonomic and robust form factor of pendant
Easily
modifiable button/contact setup, with spare button space
Extended cable to reach anywhere in the room
Pictures attached show |
Monday, March 18, 2013, 15:12, Isaac Earle, Cyclotron, Maintenance, Cyclotron Magnet Face Gap Measurements 8x
|
Measurements of the cyclotron magnet face gap were taken on March 15, 2013 at two locations around the tank with the cyclotron lid in the fully raised
position (the lid had been raised until the upper limit switches caused the control system to stop travelling). The purpose of the measurements is
to establish an independent means of verifying correct lid height before beginning in-tank remote handling activities at the start of a shutdown period. |
|