Wednesday, March 09, 2016, 17:09, Ron Kuramoto, Cyclotron, Development, EX4N new housing installation
|
The new EX4N housing assembly drawing TEC0071 (unfinished) was installed and connected to the EX4 tank side port flange over a 3 day period from Feb29
– Mar 2, 2016. This was a hands on installation spread amongst 5 people with the total accumulated dose was 2.97 mSv. See W/P C2016-02-29-5
|
Wednesday, January 28, 2015, 14:33, Travis Cave, Cyclotron, Standard Operation, Day two of in tank work
|
All copper blocker removed from the cyclotron and first radiation survey done. Shields start tomorrow. |
Thursday, January 29, 2015, 14:53, Travis Cave, Cyclotron, Standard Operation, Day three of in tank work
|
Over 50% of the shields are in some 700's left and the monitor box covers. |
Tuesday, January 27, 2015, 14:40, Travis Cave, Cyclotron, Standard Operation, Day one of in tank work
|
Day one of RH in tank work for the cyclotron (shields and blockers stuff like that) many pictures were taken. |
Friday, January 30, 2015, 15:02, Travis Cave, Cyclotron, Standard Operation, Day four of in tank work
|
All shields, ladders and pothole covers are in. One rad survey left to do. |
Monday, February 02, 2015, 14:28, Travis Cave, Cyclotron, Standard Operation, Day five of in tank work
|
Final Radiation Survey done. All in tank work completed bridge removed from the tank. |
Wednesday, February 03, 2016, 08:16, Dan McDonald, Cyclotron, Standard Operation, Cyclotron lid up
|
Lid up procedure Started at 12:00pm. Initial numbers. # 1-47,2-49,3-45,4-47,5-47,6-47,7-49,8-45,9-50,10-50,11-51,12-49. After a number of unsuccessful
attempts at jogging the system and trouble shooting it was decided to suspend operations record numbers and resume on Feb 2nd. Final numbers for
Feb 1st #1-1289,2-1297,3-1288,4-1295,5-1283,6-1298,7-1287,8-1289,9-1290,10-1296,11-1287,12-1296. |
Friday, July 04, 2014, 07:21, Dan McDonald, Elevation Jack, Standard Operation, Cyclotron lid down July-2- 2014
|
Cyclotron lid down was successfully completed on July 2 2014. Lid went partially down before jack nine had to be jogged to catch up to system. After
thirty min of continual system trips Maico Dalla Valle and I Jogged all stations to 42745. Still encountering continual system trips Gord Roy and Dan Louie
removed and reset all relays in system, lid proceeded to lower with out problem. Final jack position recording done at 19:45. |
Tuesday, January 16, 2018, 13:43, Travis Cave, Cyclotron, Standard Operation, Cyclotron in tank work
|
All cyclotron in tank work has been completed. |
Wednesday, February 05, 2020, 12:37, Adam Newsome, Cyclotron, Development, Cyclotron Vacuum Cleaning Tool - Initial Test
|
The vacuum cleaning tool (TRH1366, vacuum cleaning configuration) was tested in the cyclotron tank. The following test were performed:
1. Access to areas of interest - are we able to reach certain areas?
|
Wednesday, February 05, 2020, 12:44, Adam Newsome, Cyclotron, Development, Cyclotron Small Object Retrival Tool - Intial Test
|
The small object retrieval tool was tested in the cyclotron tank for the first time. At this time, there are no known accessible objects that were requested
to be retrieved. The tool was tested in order to gain confidence in functionality for future tasks, when needed.
|
Wednesday, May 05, 2021, 12:20, Adam Newsome, Infrastructure, Development, Cyclotron RH Control Room: Outlets Installed
|
The following outlets were installed by Electrical Services Group in order to facilitate upgrading power supplies for Cyclotron Remote Handling, as per
Work Request 5289: |
Thursday, July 16, 2020, 11:57, Adam Newsome, Cyclotron, Development, Cyclotron Mockup: Orbital Position Pendant Upgrade
|
The pendant used for controlling the orbital motion of the bridge mockup was upgraded. Features of the new pendant include:
One cable to controller (formerly two cables required)
Ergonomic and robust form factor of pendant
Easily
modifiable button/contact setup, with spare button space
Extended cable to reach anywhere in the room
Pictures attached show |
Monday, March 18, 2013, 15:12, Isaac Earle, Cyclotron, Maintenance, Cyclotron Magnet Face Gap Measurements 8x
|
Measurements of the cyclotron magnet face gap were taken on March 15, 2013 at two locations around the tank with the cyclotron lid in the fully raised
position (the lid had been raised until the upper limit switches caused the control system to stop travelling). The purpose of the measurements is
to establish an independent means of verifying correct lid height before beginning in-tank remote handling activities at the start of a shutdown period. |
Wednesday, July 02, 2014, 16:46, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Up Report for 27 June 2014
|
The cyclotron lid was raised on June 27th, 2014. Start time was 1:05pm end time was 2:17pm (good!) Dan McDonald collected and recorded numbers
from the mechanical counters for the lid up sequence, I am entering the data into the e-Log on his behalf.
Below are the mechanical counter values from the start and finish of the lid-up job: |
Thursday, January 23, 2014, 18:47, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Up Report - 22 Jan 2014 6x
|
Yesterday Grant Minor (me), Maico Dalla Valle, Dan Louie, and Arthur Leung worked with Operations to perform the Cyclotron Lid-Up task for the 2014 winter
maintenance.
Work Permit 2014-01-22-2 was issued for this job. |
Thursday, March 26, 2015, 15:48, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Up 26 March 2015
|
Lid was raised today (2nd time during 2015 shutdown) for additional inflector work.
Dan and Maico report that the lid went up smoothly and no jogs were required. The operation took about 30 minutes.
- Grant |
Monday, March 03, 2014, 15:07, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Down Report Monday 3-March-2014
|
The Cyclotron Lid Down was successfully completed today on Work Permit C2014-03-03-6.
The system only tripped twice on the way down. Both trips were at Station 9, at the following Master Syncro readings: 43194, 39198.
Oil was observed on the Jack #1 platform, but it was determined that it was coming from the crane when it's parked in the beam-on position, and |
Monday, January 08, 2018, 09:04, Maico Dalla Valle / Jason Kapalka, Cyclotron, Standard Operation, Cyclotron Lid Up
|
Remote Handing is ready for January, 8 2018 Cyclotron lid up. Elevating system service has been completed.
A Cyclotron Lid raise was attempted on Monday, January 8 at 12:00, however this attempt was aborted after lifting the lid several millimeters due the motor
|
Thursday, April 16, 2015, 15:26, Grant Minor, Elevation Jack, Maintenance, Cyclotron Elevating System Maintenance Rotation Record - Updated 16 Apr 2015
|
|
|