ID Date Authordown Category Type Subject Text Attachments
  186   Tuesday, July 23, 2024, 13:27 Riley SykesCarrierMaintenanceService/Maintenance checks 1,2, 5 Year Service and maintenance
package completed on Carrier. All reducers
repacked with Molub-Alloy 777-1 ES grease.
  
  188   Wednesday, July 24, 2024, 14:26 Riley SykesElevation JackMaintenanceService inspection and relubrication Jack 7R pulled apart and inspected
for deficiencies, all parts deemed to be
in working order, jack was rebuilt and lubricated
  
  189   Wednesday, August 07, 2024, 14:24 Riley SykesElevation JackMaintenanceService inspection and relubrication  Jack 7L pulled
apart and inspected for deficiencies, alignment
  
  142   Tuesday, May 10, 2022, 11:26 Nadia JorgensonCyclotronRepairFestooning rail rope and pulley system re-routedThe rope and pulley system that is used
to raise the festooning rail across the vault
shield door has been re-routed. It now makes
  
  143   Tuesday, May 10, 2022, 11:30 Nadia JorgensonCyclotronRepairCracked Festooning Rail Bushing Removed We removed the left bushing that
is around the air cylinder on the festooning
rail, right outside the cyclotron. It was
 Festooning_Bushing_Cracked.jpg 
  144   Tuesday, May 10, 2022, 11:31 Nadia JorgensonCyclotronStandard OperationVault Shield Door Closed The vault shield door
has been closed and seal inflated. The operation
  
  151   Tuesday, March 28, 2023, 12:02 Nadia JorgensonService BridgeRepairOutrigger 1 Failure and Repair 
During
the 2023 shutdown outrigger 1 failed. While
 Outrigger_1_Repair_2023.png 
  160   Tuesday, November 14, 2023, 12:13 Nadia JorgensonService BridgeRepairFirst Festooning Car "H" channel replacement  Damaged "H" channel removed
from the first festooning car, and spare
channel was put in place.
 Festooning_car_H_channel_deformation.pngFestooning_car_H_channel_bottom_face.png 
  161   Tuesday, November 14, 2023, 12:38 Nadia JorgensonService BridgeMaintenanceBridge Orbit Counter Work in 2023 All the bearings on both
the upper and lower wheel were replace to
  
  103   Monday, January 08, 2018, 09:04 Maico Dalla Valle / Jason KapalkaCyclotronStandard OperationCyclotron Lid UpRemote Handing is ready for January, 8 2018
Cyclotron lid up. Elevating system service
has been completed.
 Cyclotron_Elevation_Maintenance_Rotation_Record_20180223.xlsx 
  1   Monday, June 27, 2011, 10:38 John WongGeneralRoutineTesting RH elog    
  156   Thursday, September 07, 2023, 13:21 Jason ZhangService BridgeDevelopmentOutrigger #1 and #2 individual testing completeOutrigger #1 and #2 have had their controls
system overhauled as part of the O503 project.
The previous controls enclosure and the elements
  
  159   Wednesday, October 18, 2023, 12:35 Jason ZhangService BridgeDevelopmentO503 Bridge and Outrigger integration testing Service bridge, Outrigger #1, and
Outrigger #2 have had the controls system
migrated to PLC controls. The 5069-AENTR
  
  92   Monday, February 06, 2017, 20:32 Jason KapalkaElevation JackMaintenance2017 Cyclotron Elevating System Maintenance The Cyclotron Elevating System planned maintenance
work this year was performed on Jack Station
#3, #8, #9, and #10.
 Cyclotron_Elevation_Maintenance_Rotation_Record_20170829.xlsx 
  95   Tuesday, February 28, 2017, 15:45 Jason KapalkaCyclotronStandard Operation2C extraction probe removal and reinstallation2C extraction probe was removed from cyclotron
tank on 2017-02-07 by RH and Probes group
members with service 
  
  96   Friday, March 03, 2017, 13:30 Jason KapalkaCyclotronStandard OperationCP continuity testPerformed continuity test at Cyclotron center
post with RH and Operations group members
using the service bridge, 
  
  97   Tuesday, March 07, 2017, 09:31 Jason KapalkaShieldingStandard OperationBlockers/Shields/Covers/LaddersThe seven copper blockers were removed from
the Cyclotron tank by the RH group using
the service bridge, lift 
 Checklist_for_Cyclotron_Shields_and_Blocks_and_Porthole_Covers_(Rev4_As_Run_2017).pdf 
  98   Tuesday, March 14, 2017, 11:23 Jason KapalkaCyclotronStandard OperationStart/end of shutdown photo and video surveyThe start of shutdown photo and video survey
was performed in the Cyclotron tank by the
RH group using the 
 Cyclotron_Video_Inspecting_Guidelines_(RevX_20170314).xlsx 
  99   Tuesday, March 14, 2017, 12:02 Jason KapalkaCyclotronStandard OperationRadiation surveyThe unshielded radiation survey was performed
in the Cyclotron tank by the RH group using
the service bridge, 
 Procedure_for_Cyclotron_Tank_Radiation_Survey_by_Don_Jackson_(20000106_Obsolete).doctankworkssubplot.m2017_01_30_shields_out_tank_superimposed.png2017_02_02_shields_in.png 
  100   Tuesday, March 14, 2017, 17:07 Jason KapalkaProbeMaintenanceLE probe removal simulation exerciseA simulated removal of the LE2 Probe from
the Cyclotron tank was performed by the RH
and Probes group using the 
  