  9   Friday, October 12, 2012, 15:12 Keith C NgM9RepairM9 T2 Joint Repair cont.Joint repair continues.
 
Leak Check:
 20121012_RH2_01_0002.JPG20121012_RH2_01_0004.JPG 
  10   Monday, October 15, 2012, 17:03 Keith C NgM9RepairM9 T2 joint repair cont.Today:
- Removed pins and removed indium
through ring. Joint fully open at 14.5 to
  
  11   Tuesday, October 16, 2012, 19:47 Grant MinorM9RepairInspection of failed double-indium thru-ring TB22148See inspection notes attached for failed
M9T2 double-indium thru-ring TB22148, inspected
on Oct 15th 2012.
 TB22148_thru_ring_inspT2_15oct2012.pdfTB22148_thru_ring_inspQ1_15oct2012.pdf 
  12   Tuesday, October 16, 2012, 19:50 Grant MinorM9RepairM9T2 Joint Repair - Status Update 16 Oct 2012See attached.  M9T2_Joint_Repair_-_Status_Update_16_Oct_2012.pdf 
  13   Thursday, October 18, 2012, 08:26 Keith C NgM9RepairM9 T2 joint repair cont.Yesterday:
Installed indium blank off at M9
T2 joint and pumped down at 15:20 to 15:45
  
  14   Thursday, October 18, 2012, 16:28 Keith C NgM9RepairM9 T2 joint repair cont.Today:
Completed leak check of M9 T2 area:
joint(s) are He leak tight. Remote He lines
 T2_Remote_Leak_Check.PDF20121018_m9q2_waterleak.jpg 
  15   Friday, October 19, 2012, 16:48 Keith C NgM9RepairM9 T2 Joint Repair cont.Today:
Cleaned up work site and removed
extraneous poles and tooling. Radioactive
 20121019_RH1_01_0081.JPG20121019_RH1_01_0082.JPG20121019_RH2_02_0004.JPG 
  16   Friday, October 19, 2012, 18:21 Grant MinorM9Development8" double-ring test samples of EPDM and BUNA-N (Nitrile)Today I picked up two 2FT x 4Ft x 0.125"
thick strips of stock EPDM and BUNA-N (Nitrile)
material from BC Rubber Supply.  A copy
 BC_RUBBER_SUPPLY_PS_VA-B18799.pdf20121019_RH2_02_0025.JPG20121019_RH2_02_0027.JPG20121019_RH2_02_0029.JPG20121019_RH2_02_0031.JPG 
  17   Monday, October 22, 2012, 15:48 Keith C NgM9RepairM9 T2 clean up and shield restorationToday;
Restoring shielding at M9 T2 area
and cleaning up RH setup.
 20121022_RH1_02_0092.JPG20121022_RH1_02_0081.JPG20121022_RH1_02_0082.JPG 
  18   Wednesday, October 24, 2012, 11:53 Keith C NgM9RepairM9 T2 blank off completeShielding around m9 t2 restored as of 11:45,
vacuum levels still the same since 19 October.
- Work permit returned.
 201211_m9t2repair.xlsx 
  35   Thursday, February 07, 2013, 16:02 Keith C NgM9RepairM9 Q1 Q2 removal, site preprationStarted work on removing M9 Q1 Q2 magnets;
area clean up and preparation, removing shielding
above Q1 and Q2 and remote handling setup
 20130207_m9q1q2remove_IMG_0155.JPG20130207_m9q1q2remove_IMG_0162.JPG20130207_m9q1q2remove_IMG_0165.JPG20130207_m9q1q2remove_IMG_0154.JPG20130207_m9q1q2remove_IMG_0157.JPG 
  36   Friday, February 08, 2013, 15:31 Keith C NgM9RepairM9 Q1 Q2 removal, site preprationCompleted remote handling/shielding setup
over T2 M9, see photos for setup.
- Rad levels at 16' above Q2 were
 20130208_m9q1q2remove_IMG_0172.JPG20130208_m9q1q2remove_IMG_0174.JPG20130208_m9q1q2remove_IMG_0175.JPG 
  37   Wednesday, February 13, 2013, 15:49 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationLocal and remote leak checks on M9 T2 area
were done today to confirm leak; Leak was
still present at T2 M9 joint. M9 Q1 and Q2
  
  38   Thursday, February 14, 2013, 15:43 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationRemoved 8" rubber test rings from
M9 T2 joint. Rings moved to RH warm cell.
Radiation levels were 70 µSv on contact
 20130214_m9q1q2remove_IMG_0179.JPG20130214_m9q1q2remove_IMG_0177.JPG20130214_m9q1q2remove_IMG_0187.JPG20130214_m9q1q2remove_IMG_0181.JPG20130214_m9q1q2remove_IMG_0185.JPG 
  39   Friday, February 15, 2013, 14:29 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationBeam lines group purged M9 Q1 Q2 magnets
and water lines in preparation of disconnecting
water services to those magnets, done in
 20130215_m9q1q2remove_P1020780.JPG20130215_m9q1q2remove_P1020778.JPG20130215_m9q1q2remove_P1020781.JPG 
  40   Monday, February 18, 2013, 16:24 Keith C NgM9RepairM9 Q1 Q2 removal, electrical and water disconnectedToday, re-arranged electrical wiring on
Q1 Q2 magnet away from Q2 indium joint. Cable
bundles were bundled as neatly as possible.
 20130218_m9q1q2remove_P1020787.JPG20130218_m9q1q2remove_P1020786.JPG20130218_m9q1q2remove_P1020788.JPG 
  41   Tuesday, February 19, 2013, 16:46 Keith C NgM9MaintenanceM9 Q1 Q2 removal, preparationDetermined M9 Q2 service stand supply connector
was slowly leaking.
- Ball valve to the supply was leaking
 20130219_m9q1q2remove_IMG_0206.JPG 
  42   Thursday, February 21, 2013, 17:02 Keith C NgM9MaintenanceM9 Q1 Q2 removal, joint dissassemblyCUALCW system water loss was not from 1A
triplet. Q15 Q16 held static  pressure at
90 psi since 9 am until 17:00. Holding with
  
  43   Friday, February 22, 2013, 17:27 Keith C NgM9RepairM9 Q1 Q2 removal, Q2 joint dissassemblyM9 Q2 15" pin drive was removed and
disconnected.
- Pin drive retention screw had to
 20130222_m9q1q2remove_P1020840.JPG20130222_m9q1q2remove_P1020832.JPG20130222_m9q1q2remove_P1020831.JPG 
  44   Monday, February 25, 2013, 16:37 Keith C NgM9MaintenanceM9 Q1 Q2 removal, Q2 seal disassemblyRemoved Q2 15" indium seal ring, discovered
seal contained rubber on both sides instead
of indium.
 7x 