  ID Date Author Category Type Subject
  90   Friday, March 04, 2016, 16:05 Keith C NgPrimary BeamlinesDevelopmentvault beamline 4 disassembly

 

Attempted to remove RH parts between Q1, 2 and monitor vacuum box. Removed Q1 to monitor box parts, could not remove monitor to Q2 parts, pin drive and indium ring are stuck in place. Indium joint is severed however. Collar was removed.

 

East leg of pin drive was bent trying to remove the stuck indium ring, it is stuck to the monitor box.

 

Recommend to proceed with removal of magnet regarless of the current state of the indium ring.

 

Pails with RH parts marked 1384, 1385, 1386 and stored in north end of vault tunnel on grey shelf. RPG storage book updated to reflect this.

  89   Monday, February 22, 2016, 16:09 Keith C NgPrimary BeamlinesDevelopment4V CM1 blanking

 

Rolled indium into new blanking plate turned down to 5.550". Dry fit with no indium ok. Assembled hook eyes from the previous blank off plate (removed from the slits box?). Used the same 20.5 mm spring compression (1.5 turns of the nut from finger tight). Hooks did not move 100% completely freely, but seemed ok.

 

20160222_beamline4v_P1030502.JPG

 

Blanked off CM1: Reused CM1 pin drive (was written on the pin drive) Pin drive was 500 uSv/h on contact. Working at beam plane level seemed to have lower dose rate. Drove down to 1/8" just before shoulder on taper. Intended to use WD-40 but can was empty. Vacuum leak check will have to wait until a later date.

 

20160222_beamline4v_P1030505.JPG 20160222_beamline4v_P1030511.JPG

 

2016 02 23: Attached scanned inspection report of as installed blanking plate.

Attachment 4: 20160223_4VCM1_blank_off_inspection_report.pdf
20160223_4VCM1_blank_off_inspection_report.pdf
  88   Friday, February 19, 2016, 14:03 Keith C NgPrimary BeamlinesDevelopment4V CM1 blanking

Continued with work blanking off CM1 flange.

- Placed lead shot on left and right side of the CM1 flange to lower fields. No significant change, went from 2.8 mSv to 1.9-2 mSv.

- Inspected indium flange, some residue on 3 and 9 (left and right) clock sides of knife flange. No significant indium stuck on, some small cleanup done.

20160219_beamline4v_P1030494.JPG

- Spare blank off test fitted, did not fit: rocking felt from side to side. CM1 flange seems to be ovalized. Test fitted an aluminum carrier ring (B-3471), fit. Difference in OD sizes is 5.560 vs 5.550 (indium carrier ring is smaller). Will skim blanking plate to 5.550" and reassemble blank off.

 20160219_beamline4v_P1030499.JPG

Work to continue next week.

  87   Thursday, February 18, 2016, 16:34 Keith C NgPrimary BeamlinesDevelopmentVault beam line 4V disassembly

Disconnected all 4V beamline joints. Parts for indium joints removed except for the Q1 to downstream monitor box and monitor upstream to Q2 due to access issues (no space for ingress). Removed pin drive and collars currently piled on top of the beam line stands near the concrete shielding block on the north side of the vault. These need to be sorted for storage as waste or spares. Indium ring carriers were all bagged and left in the area waiting for a storage location.

  86   Friday, February 05, 2016, 08:48 Keith C NgPrimary BeamlinesMaintenance4VVR1 Removal

Returned work permit C2016-01-27-2 due to tank lid being raised and elevated fields make the work area un-favourable to work in. Work will resume to blank off the combination magnet flange when the tank lid is closed in March.

Tasks remaining:

- Inspect combination magnet flange, document valve stand

- Clean indium off of flange (if necessary)

- Install indium blank off and helium leak check

  85   Friday, January 29, 2016, 17:08 Keith C NgPrimary BeamlinesMaintenance4VVR1 Removal

Today:

Disconnected and removed 4VVR1 gate valve and removed from beamline.

- Pin drives removed and stored in bags near by

- Hook collar removed and stored in separate bags. The hook collar used at CM1 was marked with an "X".

- Indium rings also removed and stored in separate bags. Indium appeared to not stick on to the flange during removal on the tank side flange. A closer inspection will be needed at a more convenient date.

- Craning out the valve proved difficult as the shiv block was interfering with the motor lift. Lifting the valve on to the combination magnet, adjusting the sling length shorter and then final craning was the procedure used.

Cyclotron tank flange entrance at combination magnet has been covered with plastic bag and taped off. Valve was then transported to the north tunnel alcove for intermediate storage as per instructions from RPG.

Note that during cart transport, the valve tipped and fell off the cart. No visible damage could be seen on initial inspection.

 

  84   Friday, April 17, 2015, 15:11 Keith C NgM9Developmentm9 t2 alignment job

Today: Restored filler shielding in T2 M9 Q1Q2 hole.

- Blocks marked with beam direction on this installation. Active faces point toward target monument.

20150417_m9t2_P1030353.JPG20150417_m9t2_P1030354.JPG20150417_m9t2_P1030355.JPG

 

- Checked spring eye spacing after installation under vacuum overnight, appears to be equal on both sides. 1/16" spacing.

20150417_m9t2_P1030366.JPG20150417_m9t2_P1030365.JPG20150417_m9t2_P1030364.JPG

 

- Remote handling equipment has been removed from work area and restoration of shelding around T2 has begun as of 15:00.

  83   Thursday, April 16, 2015, 09:17 Keith C NgM9Developmentm9 t2 alignment job

Yesterday (Apr 15):

1) Installed TB22265 on to M9 exit port at 18:48 with no vacuum and left over night. Done per 2013 installation procedure (1.5 turns of the preload nut, after pins are engaged and springs are at free length)

 - On this installation, the nuts (TB22264) and tool block (TB22263) were reused from the 2013 blanking plate. The blanking plate (TB22267), spring eyes, springs and washers were new parts. Reused parts were 900 uSv/h on contact and 50 uSv/h @ 1/2m.

 - Spring eye, spring eye washers and nuts had fitment issues due to manufacturing errors. No dry fitting of parts was performed before hand. Spring eye used was a new style single piece machined type.

 - Selected springs were used in this installation: East spring rate: 4762 lbs/in, West spring rate 4972 lbs/in. See attached spreadsheet for spring rate test details.

20150415_m9t2_P1030320.JPG20150415_m9t2_P1030314.JPG20150415_m9t2_P1030322.JPG

 

2) 2013 TB22265 (previous) blanking plate was discovered to have a stuck spring eye on the East side.

 - Spring eye would not rotate or slide freely when moved by hand. Upon removing the spring eye with a mallet, evidence of aluminum galling could be seen.

 - Pin diameters measured were .499, diameters on drawing were .497 -.002/+.0. Specified hole diameter on blanking plate is .500 +.001/-.0. These spring eyes were of the 2pc welded type.

 - Despite larger than drawing size, west spring eye could still slide freely. On east spring eye near the welded area filing marks could be seen near the galling. This area measured .4995 at one point.

20150415_m9t2_P1030300.JPG

- Suspect this manufacturing defect (a lump) caused the spring eye to bind and cause the indium knife to stop advancing.

 

Today (Apr 16):

1) Leak checked blank off after leaving clamped over night. Vacuum pumping started at 9:00, leak check began at 11:00. Appears to be leak tight. (leak check results attached)

- Spring eye gaps appear to be the same as the previous day.

vlcsnap-00008.jpgvlcsnap-00009.jpg

 

2) Began tear down of bridge and shielding setup.

- Surveyed the following radioactive items for storage in RH lead flask:

- M9 B1 pin drive hold down bolt; 800 uSv/h on contact,  50uSv/h @ 0.5 m. no removable contamination.

20150416_m9t2_P1030324.JPG

- TB22265 2013 blank off; 3900 uSv/h on contact, 200 uSv/h @ 0.5 m. 3000 cpm, on gamma detector (44-2) and 1600 cpm contamination on RM-14.

Attachment 1: 2015apr15_springratetest.xlsx
Attachment 6: img-416130259-0001.pdf
img-416130259-0001.pdf
  82   Tuesday, April 14, 2015, 08:31 Keith C NgM9Developmentm9 t2 alignment job

Yesterday:

1) Addressed mounting issue with the 15" alignment jig: removed material from the spring eye to make the hole from 1" to 0.75" when bottomed out. This would cause the spring eye and mounting eyelets on B1 to have 0.226" of starting overlap, vs the original 0.024" negative overlap previously seen.

2) M9B1 15" pin drive was removed along with the securing bolt. The bearing block on the pin drive had seized up and could not be rotated. It was decided to remove the screw drive from the pins and drive down the pin assembly in a manner similar to installing the 8" target. Installation of the 15" jig will continue today.

 

Today:

1) installed 15" and 8" sighting jigs, Beamlines group completed multiple passes for measurements. 15" pin drive was installed without the drive mechanism which was seized, pins were slipped into place (same procedure as 8" rubber seal blanking plate).

2) Reinstalled dust cover on to B1 flange, wiped off vacuum pump (?) oil from inner side of cover with acetone. Also wiped B1 flange with acetone + lint free cloth. The inner surface of the B1 flange and knife edge will need to be cleaned with specialized tooling.

20150414_m9t2_P1030289.JPG20150414_m9t2_P1030290.JPG

 

3) 15" pin drive was replaced as follows: Seized screw drive was partially re-threaded into the taper pins, pins were lowered into place into receiving holes and the hook block that locates the pin drive was re-engaged. The pin drive securing bolt was left out. Not that this particular pin drive is not to be used in the future, high field parts were replaced for storage purposes.

20150414_m9t2_P1030295.JPG20150414_m9t2_P1030297.JPG

  81   Friday, April 10, 2015, 16:25 Keith C NgM9Developmentm9 t2 alignment job

Continued with installation of target jigs:

1) Craned in equipment for alignment group.

2) Attempted to install target jig over B1 flange;

- Not enough horizontal distance south of B1 flange to install the target flange vertically and into place, jig must be maneuvered in side ways from the east of B1 into position.

- Spring eyes were designed such that after driving the taper pins into place the spring eyes were not being loaded due to a lack of allowing for spring compression. Design is being studied to fix this problem.

- B1 sighting flange was subsequently removed and one spring eye removed from the assembly (taper pins were left partially engaged in the top ear of the T2 M9 @70 Turns up (20 turns down)). Total amount of turns to drive down pins is 90 turns.

3) T2 M9 Q1 8" sighting jig was installed into place successfully

- Threaded pole used to install the 8" jig could not be unscrewed due to the pole tool securing nuts interfering with the pole used to install the pin drive (no clearance for tools). Poles are to be left in situ, screwed into their respective equipment until job is completed.

3) Alignment group sighted the T2Q1 target flange and the mushroom pad jig. They will continue on Monday with the B1 flange should the spring eye problem be addressed by then.

 

  80   Thursday, April 09, 2015, 17:20 Keith C NgM9Developmentm9 t2 alignment job

1) Vented T2 and removed rubber seal blanking plate, vacuum level appeared to be at normal operating ranges prior to the indium seal developing a small leak.

2) Removed B1 dust cover, cover was stuck to B1 flange due to oil residue. Oil residue is believed to be from a vacuum pump being turned on in the disconnected section of M9B line. Residue was seen on the bottom half of the B1 to Q2 flange, it was cleaned off using a cotton glove and acetone attached to a 20ft pole. Attempting to clean with wipealls left lint behind.

20150409_m9t2_P1030246.JPG

3) Mushroom pad jig installed in place, shielding reconfigured and platform plates in place. Target flanges to be installed tomorrow.

20150409_m9t2_P1030248.JPG20150409_m9t2_P1030251.JPG20150409_m9t2_P1030256.JPG

  79   Wednesday, April 08, 2015, 14:18 Keith C NgM9Developmentm9 t2 alignment job

1) Visual inspection of T2 M9 flange: no obvious indium deposits on T2 flange knife edge seen, left over indium from before 2013 is still present on counter bore. See screen captures. Screen captures show state of flange after removing blanking plate, no cleaning was performed after removal.

vlcsnap-00011.jpgvlcsnap-00010.jpgvlcsnap-00002.jpgvlcsnap-00013.jpg

vlcsnap-00006.jpgvlcsnap-00005.jpgvlcsnap-00007.jpgvlcsnap-00004.jpg

2) Rlanking plate with rubber seal installed on T2M9 exit port at noon. T2 volume pumping started around 13:00.

2)  Plot of pressure over a week period of 1ACG3, units in Torr:

2015apr8_xtpage1acg3.jpg

Attachment 6: vlcsnap-00003.jpg
vlcsnap-00003.jpg
Attachment 7: vlcsnap-00006.jpg
vlcsnap-00006.jpg
Attachment 8: vlcsnap-00005.jpg
vlcsnap-00005.jpg
  78   Tuesday, April 07, 2015, 16:09 Keith C NgM9Developmentm9 t2 alignment job

work to prepare for installation of alignment jigs on T2M9 and M9B1 continues:

1) Vented T2 volume and removed M9 blanking plate. Volume was not fully vented so plate was stuck and had to be pried off slightly. Around 2 turns of the nuts were required to undo the spring eyes, this is likely less than the total number of turns that were used to tighten the assembly since the indium knife embeds itself in the indium. Blank off is currently bagged in the hot block bunker.

2) Visual inspection of indium impression: 3 knife steps seen all around, east and west sides have indium that look like they have made contact with the bottom of the counter bore. Top and bottom have show distinct "oozing out", but not flattened.

3) Blank off plate fields: 3.9mSv/h on contact, 200µSv/h @ 1/2m. contamination on indium area: 5500 cpm on 44-2, 22000 cpm on rm14; contamination on central aluminum only area: 1300 cpm on 44-2, 1000 cpm on rm14.

  77   Tuesday, April 07, 2015, 08:27 Keith C NgM9Developmentm9 t2 alignment job

Work completed for Thursday:

1) Shielding filler blocks removed from M9Q1Q2 hole. Highest field was 5mSv/h coming from TSH0081 on the end facing the monolith. Blocks and frame had 1000-1200 CPM of contamination.

2) Filler blocks were placed in bunker formed by 18' shielding blocks. An additional 18' block was placed over the bunker to shield the south mezzanine from the field coming from the filler blocks. Bridge setup around M9T2 hole reconfigured slightly for fall protection purposes.

3) Blanking plate nuts on T2M9 exit port were tightened by 1/2 turn at 16:00 (first West side then east, by 1/4 increments. eg 1/4 + 1/4 West, 1/4 + 1/4 East). No immediate effect on vacuum observed.

 

Attached is survey of steel filler shielding blocks. Contamination on the support frame is unknown, either 0 contamination or not recorded.

20150407_m9t2_P1030233.JPG

  76   Wednesday, April 01, 2015, 16:07 Keith C NgM9MaintenanceT2 M9 area work

1) Block and bridge setup is mostly complete for T2 M9 sighting job. Waiting on approving drawing TB22322 in order to continue with installing sighting equipment.

2) He leak checked upstream of T2 and surrounding area. Appears to be a small leak at the M9T2 exit port through the blanking plate seal. Mode of failure undetermined at this time. Leak does not impact operation of beam line 1A according to vacuum group.

  75   Monday, March 30, 2015, 16:10 Keith C NgM9RepairT2 area uncovering

Started to uncover and create work space around T2 M9 area, setup is mostly complete. Some misc items to be craned into position. RH set up is mostly to do He leak checking of 1A beamline due to vacuum leak somewhere in the area around T2, bridge on B1 side of M9 has not been set yet.

  74   Thursday, March 05, 2015, 08:42 Keith C NgPrimary BeamlinesRepair1AT1 area water leak fixes

1) Quick connect fittings on the rotary collimator were leaking (the two red collared fittings in photo below).

20150303_wintershut_IMG_1375.JPG

Replaced quick disconnect connectors on rotary collimator with compression fitting unions and bypassed the bulk head on the collimator, water hoses are hanging loose.

  1. (top) supply line has an additional union + spliced line 90deg section
  2. (bottom) is return line

20150304_wintershut_IMG_1384.JPG20150304_wintershut_IMG_1390.JPG20150304_wintershut_IMG_1389.JPG

The hoses should be shut off at their supply and then disconnected by undoing the fittings, if the collimator is to be removed. 

 

2) Replaced leaking fitting on 1AQ9 water cooled indium joint. Copper refrigerator tubing that runs down the shielding block cable chase that feeds T1 from the water package. Replaced both return and supply section as they were corroded (joined) together. Unsure which is supply or which is return line, or if it matters.

20150304_wintershut_IMG_1382.JPG20150304_wintershut_IMG_1383.JPG20150304_wintershut_IMG_1385.JPG20150304_wintershut_IMG_1388.JPG

 

Final state of top of collimator area in picture below, inlet and outlet tagged (2015 mar 5).

20150305_ucnbuild_IMG_1398.JPG

2015 mar 6: the replaced supply joint was leaking a small amount of water through one of the union joints, decided to remove both the suspect union joints and connect the metal hose to the copper line. Appears to be okay/dry.

20150306_rotarycollimator_P1030153_2.jpg

Attachment 1: 20150303_wintershut_IMG_1375.JPG
20150303_wintershut_IMG_1375.JPG
  73   Thursday, February 26, 2015, 16:22 Keith C NgPrimary BeamlinesDevelopmentM13Q1Q2 blank off (part of UCN work)

He leak checked T1M13Q1 joint, is leak tight.

 - Detected a small leak in nearby M15 slits box. 4.3x10E-9 atm cc/sec was highest leak rate recorded (Vac group says is small leak, okay to run).

 - Will be tearing down bridge setup and cover up area.

  72   Wednesday, February 25, 2015, 14:57 Keith C NgPrimary BeamlinesDevelopmentT1 M13Q1Q2 blank off work

Blanking plate with indium between T1 and M13Q1 flange has been installed, joint will be He leak checked tomorrow. Vac group informs that pumping of T1 volume will start this afternoon going over night.

- The spring eyes on Q2 vacuum box are ~0.2" above the pin supports, the gap changes by 0.05" between open and closed positions.

- Pin drives were driven down to 34 turns (left a 1/8" gap between the bar and the top of the T1 flange)

20150225_vlcsnap00010.jpg

- A thermocouple wire was attached to the blanking plate, leads are not yet connected however.

  71   Monday, February 23, 2015, 15:57 Keith C NgPrimary BeamlinesDevelopmentM13Q1Q2 blank off (part of UCN work)

"Hector" shield block installed into place, Q1Q2 Vacuum box still actuates normally. It does not appear that the position of the pin drive has shifted. Some additional shielding steel is to be placed on top of the shield block once RH setup is removed.

Remote handling equipment installed around T1 ready to install indium blanking plate between T1 and M13Q1.