110
|
Monday, February 05, 2018, 15:40 |
Keith C Ng | Primary Beamlines | Repair | 1A Q15 repair. | 1.) Completed covering up 1A Q15.
2.) RH flask currently contains the
8 insulators removed from Q15. 3.6 mSv/h |
|
|
109
|
Thursday, February 01, 2018, 15:44 |
Keith C Ng | Primary Beamlines | Repair | q15 repair | Correction that all supply side (even numbered
insulators) ceramic insulators on Q15 have
been replaced with new old stock insulators |
|
|
108
|
Wednesday, January 31, 2018, 15:28 |
Keith C Ng | Primary Beamlines | Repair | Q15 repair | Beamlines has changed out another 2 insulators
on Q15 after discovering two additional leaks.
Insulators #2 & #4 were replaced. One |
|
|
107
|
Tuesday, January 23, 2018, 15:44 |
Keith C Ng | Primary Beamlines | Repair | 1AQ15 insulator repair | Assisted beamlines in replacing 2 insulators
on 1A Q15 magnet. #10 and #14 insulators
were found to be leaking at the ceramic, |
|
|
106
|
Thursday, July 27, 2017, 09:02 |
Keith C Ng | Primary Beamlines | Development | test | test |
|
|
105
|
Thursday, March 16, 2017, 15:50 |
Keith C Ng | Primary Beamlines | Repair | collimator b transition to t2 | On Monday found leaking joint was the ring
directly downstream of T2. Vacuum group has
been spraying Vacseal (http://www.vacseal.net/Pages/default.aspx) |
|
|
104
|
Wednesday, March 08, 2017, 16:05 |
Keith C Ng | Primary Beamlines | Repair | collimator joint repair | Started uncovering the area above the T2
to Q13 joint:
|
|
|
103
|
Monday, February 20, 2017, 15:58 |
Keith C Ng | M9 | Development | t2 m9 job wrap up | Restored shielding to T2 M9 void, blocks
seem more crooked compared to previous years. |
|
|
102
|
Friday, February 17, 2017, 13:33 |
Keith C Ng | M9 | Development | T2 M9 vacuum | Leak checked the blank off at T2 M9 exit
port with Dimo Y. and Edi D.V. (Vac Group)
and they confirm it is leak tight. Blank |
|
|
101
|
Wednesday, February 15, 2017, 15:36 |
Keith C Ng | M9 | Development | t2 m9 blank off | Installed the blank off on the T2
M9 exit port: |
|
|
100
|
Tuesday, February 14, 2017, 16:08 |
Keith C Ng | M9 | Development | T2 M9 2015 vs 2017 comparison | Attached a quick comparison of M9 exit
port flanges WRT indium remnants: looks roughly
the same. Will attempt to install blanking |
|
|
99
|
Friday, February 10, 2017, 15:53 |
Keith C Ng | M9 | Development | t2 m9 job | Installed all jigs and Alignment group
did their shoots successfully. Used individual
pins on the 15" target jig and worked |
|
|
98
|
Thursday, February 09, 2017, 16:14 |
Keith C Ng | M9 | Development | t2 m9 alignment | Prepared m9 and b1 flanges for accepting
their target jigs. The target jigs need to
be reset by alignment group, 15" was |
|
|
97
|
Tuesday, February 07, 2017, 15:36 |
Keith C Ng | M9 | Development | t2 m9 job | - Removed blank off from t2 m9 port,
had to pry off with screw driver via spring
ears. Clean removal it seems. |
|
|
96
|
Friday, February 03, 2017, 14:57 |
Keith C Ng | M9 | Development | Removing shield blocks and leak check results. | Removed temporary shielding blocks from
M9 hole and placed in temporary bunker. Capped
with 18' shielding block. Blank off ready |
|
|
95
|
Wednesday, February 01, 2017, 15:34 |
Keith C Ng | M9 | Development | T2 M9 Setup | Finished setting up work area around T2
M9 front end.
|
|
|
94
|
Monday, January 30, 2017, 12:01 |
Keith C Ng | M9 | Development | T2 leak check with vac group | Week
of Jan 23 to 27:
|
|
|
93
|
Thursday, March 31, 2016, 15:32 |
Keith C Ng | Primary Beamlines | Development | 1VM3 to 1VQ4 joint. | Re-installed indium vacuum joint for 1VQ4,
routing installation. R. Kuramoto sprayed
silicone grease on to the threads and bushings |
|
|
92
|
Wednesday, March 16, 2016, 17:57 |
Ron Kuramoto | Primary Beamlines | Development | 4VQ1&Q2 Removal | On 14March2016, 4VQ1&Q2 were
removed from BL4V and lowered into the Vault
basement B3 level where they were stored |
13x |
|
91
|
Wednesday, March 16, 2016, 17:19 |
Ron Kuramoto | Primary Beamlines | Development | 4VQ3 Removal | On 8March2016, under W/P C2016-03-08-2,
4VQ3 was lifted out of BL4V with the vault
orbit crane where it was first weighed then |
|