    Reply  Tuesday, April 23, 2013, 10:11, Anders Mjos, Empty, 38481-4, HP-FEBIAD, Done, CTL test 2013-04-23_Evap2_ITD0300_CTL_Thermal_Test.xlsxCTL_ITD0300_Evap2.pdfDeformed_Ionizer_Tube.jpg

 

John Wong wrote:

 

Anders Mjos wrote:

Target installed with 4 T/C

The target assembly is ITD0300 with the CTL Cu cooling block slightly modified.

Ch1 - CTL cooling block T/C feedtrough
Ch2 - Heat shield below left gripper arm - T/C feedthrough
Ch3 - Heat shield below left gripper arm - 9 pin connector
Ch4 - Target left side leg on tube - 9 pin connector

Friday, April 19, 2013, 15:23: Roughing

Friday, April 19, 2013, 15:41: Started turbo


Monday, April 22, 2013, 09:43: Opened water supply. Vacuum stable at 2.8E-7 T (IGP1)

 

Monday, April 22, 2013, 18:48

Ramping TGHT/TBHT to 850A/300A at 1A/min.


 

 

Tuesd ay, April 23, 2013, 10:07

TBHT / TGHT: 820A / 300A

TGHT:RDCUR: 816.6A
TBHT:RDCRU: 303.5A

Local P/S displays
TGHT: 821A / 11.05V
TBHT: 307A / 4.37V

Tuesday, April 23, 2013, 10:45: Ramping down TBHT to 0A @ 5A/min

Tuesday, April 23, 2013, 12:49: Ramping down TGHT to 0A @ 5A/min

Tuesday, April 23, 2013, 15:52: Swithced off TGHT and TBHT P/S. TGHT P/S showed 30A read back value, while local value was 0A


 Wednesday, April 24, 2013, 09:53: Turbo stopped

Wednesday, April 24, 2013, 12:00: Target removed 


The ionizer tube was found to have deformed as seen in the attached photo.

Entry  Thursday, January 22, 2015, 14:21, Anders Mjos, Empty, , , Problems resolved, CG1A replaced 

 See previous e-log entry for details

Entry  Saturday, August 22, 2020, 11:44, Marla Cervantes, , 44489-11, , Done, C-Cartridge test#1 

Saturday, August 22, 2020, 11:41

A Ta short tube was coated with TaC and sintered, then it was loaded with a c-cartridge

Now is currently under vacuum and it will be heated to 2000 °C during 3 days


Saturday, August 22, 2020, 11:43

Good vacuum = 3e-2 Torr

Bad vacuum = 5e-2Torr

IGP1 = 3.08e-7 Torr 

Autoram set to 10A/30 s to 200 A


 Saturday, August 22, 2020, 11:59

Good vacuum = 3e-2 Torr

Bad vacuum = 5e-2Torr

TGHT = 2.36 V, 200.1 A

IGP1 =2.46e-6 Torr

Autoramp set to to 300 A at 5A/30s 


Saturday, August 22, 2020, 13:03

TGHT = 7.32 V, 495.3 A

IGP1 = 2.7e-6 Torr

Omega = 2016 °C

AP = 1970.1 °C

Autoramp set to 550 A at 5A/30s


 Saturday, August 22, 2020, 13:11

TGHT =7.6 V, 523.2 A

IGP1 = 3.2e-6 Torr

Omega = 2077 °C


Monday, August 24, 2020, 07:59

Voltage increased ~0.2 V while current remained the same indicating an increment in resistance, temperature increment increased accordingly

TGHT = 7.815 V, 520.87 A

Omega = 2126 °C


Monday, August 24, 2020, 08:04

The current was reduced 0.1 A to 519.9

Monday, August 24, 2020, 08:55 Omega =  2112 °C


Monday, August 24, 2020, 09:12

The temperature returned to Omega = 2130 °C

The current was reduced 0.1 A to 519.8

Monday, August 24, 2020, 09:56

TGHT = 7.7 V, 518.3 A

Omega = 2132 °C 


Monday, August 24, 2020, 09:59 

The current was reduced 0.2 A to 519.6 A

TGHT = 7.7 V, 517.3 A

Monday, August 24, 2020, 10:07  Omega = 2130°C


 Monday, August 24, 2020, 10:08

The current was reduced 0.4 A to 519.2 A

TGHT = 7.7 V, 513.5 A

Monday, August 24, 2020, 10:13  Omega = 2129°C


Monday, August 24, 2020, 10:21

Voltage dropped to 7.6 V and temperature reduced to 2105 °C

Monday, August 24, 2020, 10:30

Voltage increased to 7.8 V and temperature increased to 2128 °C


Monday, August 24, 2020, 10:33

The current was reduced 0.4 A to 518.6 A

TGHT = 7.7 V, 513.06 A

Monday, August 24, 2020, 10:38  Omega = 2130 ­°C


Monday, August 24, 2020, 10:41

 The current was reduced 0.4 A to 518.2 A

Monday, August 24, 2020, 10:52 Omega = 2134 °C

Monday, August 24, 2020, 11:13 

 The current was reduced 0.4 A to 517.8 A

Monday, August 24, 2020, 11:19  Omega = 2128 °C


Monday, August 24, 2020, 11:19 

 The current was reduced 0.4 A to 517.4 A

Monday, August 24, 2020, 11:22  Omega = 2126


Monday, August 24, 2020, 11:22

 The current was reduced 0.4 A to 517.0 A

Monday, August 24, 2020, 11:25  Omega = 2123 °C


Monday, August 24, 2020, 11:26

 The current was reduced 0.4 A to 516.6 A 

Monday, August 24, 2020, 11:30  Omega = 2109 °C


Monday, August 24, 2020, 11:30 

 The current was reduced 0.4 A to 516.2 A

Monday, August 24, 2020, 11:36  Omega = 2100 °C


Monday, August 24, 2020, 11:37

  The current was reduced 0.4 A to 516.0 A

TGTH = 7.5 V, 512.9 A

Omega = 2095 °C


Monday, August 24, 2020, 14:17

Voltage dropped and later on increased 

TGHT = 7.7 V, 517.5 A

Omega = 2120 °C 


Monday, August 24, 2020, 14:18

 The current was reduced 0.4 A to 515.6 A

TGHT = 7.6 V, 509.4 A

Monday, August 24, 2020, 14:20  Omega = 2125 °C


Monday, August 24, 2020, 14:20

The current was reduced 0.4 A to 515.2 A

Monday, August 24, 2020, 14:22  Omega = 2122 °C


Monday, August 24, 2020, 14:22

 The current was reduced 0.4 A to 514.8 A

Monday, August 24, 2020, 14:29  Omega = 2116 °C


Monday, August 24, 2020, 15:27

The voltage dropped as well as the temperature

TGHT = 7.5 V, 512.5 A 

Monday, August 24, 2020, 15:28 Omega = 2095 °C


Monday, August 24, 2020, 22:06

TGHT = 7.6 V, 515.9 A 

Omega = 2105 °C


Tuesday, August 25, 2020, 09:07

TGHT = 7.6 V, 519.13 A

Omega = 2102 °C 


Tuesday, August 25, 2020, 13:02

TGHT = 7.6 V, 518.0 A

Omega = 2116 °C

IGP1 = 3e-7 Torr


Tuesday, August 25, 2020, 13:04 

Starting ramp down to 0 A at 5 A/min 

Entry  Wednesday, August 26, 2020, 10:27, Marla Cervantes, , 44489-8, , Done, C-Cartridge test #2 

 Wednesday, August 26, 2020, 10:26

A Ta short tube was loaded with a C-cartridge

Currently, the tube is under vacuum and it will be heated to 2000 °C during 3 days.

IGP1 = 3.2e-7 Torr


 Wednesday, August 26, 2020, 16:15

IGP1 = 2.5e-7 Torr

Good vacuum = 3e-2 Torr

Bad vacuum = 5e-2Torr

Autoram set to 200A at 10A/30 s


Wednesday, August 26, 2020, 17:05

TGHT = 3.9 V, 301.3 A

IGP1 = 5.4e-7 torr 

Omega = 1378 °C

AP (slope 0.9) = 1441.8 °C


Wednesday, August 26, 2020, 17:20 

Autoramp set to 550 A at 5A/30s


Wednesday, August 26, 2020, 23:43 

TGHT = 7.561 V, 504.9 A

Omega = 2124 °C

AP = 2010.5 °C


Thursday, August 27, 2020, 07:15

TGHT =  7.461 V, 510.2 A

Omega = 2103 °C


 Thursday, August 27, 2020, 13:41

TGHT = 7.5 V, 510.8 A

Omega = 2099 °C


Friday, August 28, 2020, 09:24

TGHT = 7.4 V, 513.9 A 

Omega = 2103 °C


Friday, August 28, 2020, 13:12

TGHT = 7.46 V, 505.6 A

IGP1 = 2.7e-7 Torr

Omega = 2103 °C


Saturday, August 29, 2020, 14:18

IGP1 = 2.5e-7 Torr

TGHT = 7.5 V, 510.8 A

Omega = 2109 °C 


Saturday, August 29, 2020, 17:44

IGP1 = 2.4e-7 Torr

TGHT = 7.5 V, 505.2 A

Omega = 2119 °C 


Saturday, August 29, 2020, 17:51 

Starting ramp down to 0 A at 5 A/min

Entry  Wednesday, September 08, 2021, 12:43, Darwin Ortiz Rosales, , 44139-8-SK, TARGET BOAT, Done, C Conditioning 

 Wednesday, September 08, 2021, 12:36

297 C discs were loaded onto a Ta tube wrapped in 3 Ta heatshields. (10 of which are analysis discs).  They should be the first to be pushed out as they were loaded last.

The discs were loaded upside down to facilitate transfer to final container post conditioning.

a Ta foil disc was placed at the front end and a Ta spring at the back end of the tube.

The weight of the whole system is 254.4 g

Evap 2 was left to reduce pressure overnight.

Target temperature is 2000 C for five hours @ approx 450A

Good vacuum = 3e-2 Torr

Bad vacumm= 5e-2 Torr


 Thursday, September 09, 2021, 08:46IGP1= 7.5 e-07 Torr

Will manually ramp up TGHT to 80 A 


Thursday, September 09, 2021, 09:09 

pressure began to rise at 50A so will leave at 50 A waiting for stabilization.

Current began to shoot up to rapidly, lowered current to 40A.  


Thursday, September 09, 2021, 10:34

At IGP1= 1.3e-4 Torr manually increasing current again 


Thursday, September 09, 2021, 12:52 

IGP1= 8.6e-5 and dropping

TGHT = 60A, 0.87 V

Will begin autoramp to 120A at 1A/min


Thursday, September 09, 2021, 14:06

IGP1= 3.2e-05Torr

TGH T= 120A, 1.9V

Set autoramp to 1A/10s to 200A 


Thursday, September 09, 2021, 14:57

IGP1=  1.5e-05 Torr

TGHT = 200A, 3.4V

Set Autoram to 2A/10s to 450A

OMEGA = 1249 C

 At 258A OMEGA = 1420 C

continue ramp up at 2A/10s to 450

projected 2000 C is 454 A


 

Thursday, September 09, 2021, 16:10 

Tapped up to 470 A and OMEGA 1993C.  Will leave at this current because T may rise.  

 


Thursday, September 09, 2021, 21:21

OMEGA 2011 C

IGP1 = 6.9e-06 Torr

Ramping down @ -1 A/min

 


Thursday, September 09, 2021, 17:27

Temperature kept around 2000 C by reducing current.  It was reduced to 455A and Temperature stabilized .  Time of ramp down will be  21:10 

Entry  Thursday, October 02, 2014, 11:26, John Wong, Empty, , , Maintenance, Broken insulators  

 Thursday, October 02, 2014, 11:22

It was found that after the last process, Evap#2 has broken insulators - the cylinder insulator that supports the target centre legs and the block insulator that supports the terminals.  

Informed Anders/Rick.


 

    Reply  Friday, October 03, 2014, 13:02, Anders Mjos, Empty, , , Maintenance, Broken insulators  NewInsulators.jpgBrokenInsulators.jpg

John Wong wrote:

 Thursday, October 02, 2014, 11:22

It was found that after the last process, Evap#2 has broken insulators - the cylinder insulator that supports the target centre legs and the block insulator that supports the terminals.  

Informed Anders/Rick.


 

 Friday, October 03, 2014

  • Insulators replaced. Torque 55 in lbs on all fasteners.
  • Cleaned TGHT terminals with scotch-brite and methanol.
  •  New (clean) heat shield prepared WO-39230-2.
  • Re-installed right side heat shield alignment pin (previously removed to allow line of sight to the target).
Entry  Wednesday, February 24, 2016, 17:40, John Wong, Nb, , LP-SIS, Done, Bob/Tobi Nb samples Screen_Shot_2016-02-25_at_6.04.20_PM.png

Thursday, February 25, 2016, 18:04 Wednesday, February 24, 2016, 17:29

Heat treatment of 2 bullet-shaped Nb samples in a LP-SIS container; it is just that we don't have a target boat. 

Container is wrapped with 12" in total length.  A strip of Nb foil is used as an underlayer for the samples to sit on top. 

Chamber has been pumped down and current vacuum at 1e-6 Torr. 

HS water check - good.

Target temperature 1400C

Ramping up to 250A; this should get to ~1300C.  Will let it heat for over night and step up to 1400C tomorrow. 


 Wednesday, February 24, 2016, 17:59

I'm stopping the heating process because the camera is not working.  I can't monitor the temperature.  Tried to fit the camera; don't now why it fails to connect to the server. 

Will look in to it tomorrow...


 Thursday, February 25, 2016, 08:17

Initiated auto ramping TGHT at 2A/min.


Thursday, February 25, 2016, 17:33  

Finally the camera is fixed.  

Current temperature is at 1126C, TGHT at 250A.  Will step up to reach 1400C. 


Thursday, February 25, 2016, 18:04  

TGHT stepped up to 335A to reach 1400C.  (see attachment) 

Will heat this for few hours and cool it at around 11pm tonight.


 Thursday, February 25, 2016, 22:19

Samples have been heated over 4.5 hours. 

Initiated cool down at 1A/min.


 Friday, February 26, 2016, 15:43

done! all good.


 

    Reply  Monday, November 04, 2013, 14:02, Anders Mjos, , , , Maintenance, Backing pump replaced 

 

Anders Mjos wrote:

The source of the poor vacuum in the backing line seems to be related to a dirty filter. We will try to find a replacement filter next week.

The problem seem to have started September 17th, when backing preassure CG1A went from 40 mTorr to 130 mTorr. CG1B remained around 30 mTorr.

With the help of Anthony Ip from vacuum group, the problem was diagnosed to be the roughing pump itself. The pump was replaced and pumping improved. The chamber can now be evacuated and turbo ready to start in less than 10 minutes.

The filter is not stocked by vacuum group and could not be replaced.

Last week parts of the roughing line was cleaned by Rick. The PVC roughing line has been replaced with a SST bellows. The SST bellows is KF25 and should be replaced by a KF40 bellows in the long run.

Entry  Friday, November 01, 2013, 17:20, Anders Mjos, , , , Problems, Backing pump needs new filter 

The source of the poor vacuum in the backing line seems to be related to a dirty filter. We will try to find a replacement filter next week.

The problem seem to have started September 17th, when backing preassure CG1A went from 40 mTorr to 130 mTorr. CG1B remained around 30 mTorr.

Entry  Thursday, January 14, 2016, 11:48, Laura Lambert, , , , Maintenance, Backing Pump Replaced 

 Thursday, January 14, 2016, 11:47

Backing pump was making very loud high pitched noises during last couple processes in the evaporator.

Replaced with a new one this morning.


 

Entry  Wednesday, July 17, 2019, 11:13, Marla Cervantes, Nb, 40282-4, TARGET BOAT, Done, Annealing of RRR-Nb test samples 

 Wednesday, July 17, 2019, 10:57

Annealing of five RRR Nb samples following cold-working and resistance measurements.  Used to validate computational annealing model developed for SRF studies.  For more information contact Norman Muller, x6398.

Desired temperature 1025 C.

Five Nb samples wrapped with Nb foil were set on a tantalum boat (coated with TaC)

the tantalum boat was wrapped with two tantalum sheets.

The boat was installed in the EVAP2.

The initial vacuum was IGP1 = 1.26e-6 Torr.

Ramping rate 5 A/min to final current of 200 A.


Wednesday, July 17, 2019, 11:18 

At 155 A, the ramping rate was changed to 1 A/min 


Wednesday, July 17, 2019, 11:28 

The ramping was stopped at 167 A.


 Wednesday, July 17, 2019, 11:57

Conditions:

IGP1 = 1.65e-6 Torr


TGHT = 2.54 V, 174.46 A

Temperature ~ 950 C


Wednesday, July 17, 2019, 18:07

IGP1 = 1.16 e-6

TGHT = 3.18 V, 206.7 A

Temperature ~950 C

Cooling ramp 10 A/min 

 Vented with air


Suggestion for future annealing:

  Use tantalum boat without TaC coating.

Entry  Tuesday, May 10, 2022, 14:43, Aaron Schmidt, , , , Maintenance, Active TP removed / Swap / Slow start TP 

 Tuesday, May 10, 2022, 14:42: TV551 Varian. SN: 202311 (Slightly active from BL1A - will not cross contaminate. Field only - Tagged) was removed as it was meant to be a temporary fix. Replacement (Refurbished) pump is to be installed. (Tomorrow - Use slow start function as per vacuum group) 


Thursday, May 12, 2022, 13:30: Agilent TP & hardware installed.

SN: IT21381010 

Thursday, May 12, 2022, 13:41: Roughing.

Thursday, May 12, 2022, 13:46: Halt. 


Friday, May 13, 2022, 07:05: Roughing. 

Friday, May 13, 2022, 07:18: TP1 on.

Friday, May 13, 2022, 07:23: Up to 14 KRPM. Pause/Halted startup (Whining?). Slow start w/ vacuum group.

Process to perform a TP slow start:

- Hold both top buttons on the controller for about 3 seconds

- Right Yes/No left to continue. 

- Advance to soft start - 20 min. 

- Back to remote start & go.

Friday, May 13, 2022, 08:26: TP1 on w/ slow start.

Friday, May 13, 2022, 08:39: 13 KRPM & climbing.

Friday, May 13, 2022, 09:10: TP at full speed. 38 KRPM. 0.5A 9w. This pump whines, but is operating fine. Likely will switch again when another is available. (It appears to have been dropped, Noted by Edi. Likely when shipped) 

Friday, May 13, 2022, 09:14: TP off. Slow start function off. Back to normal function. 

Entry  Thursday, April 04, 2024, 12:07, Darwin Ortiz Rosales, TiC, , LP TUBE, Done, 240404TiC sintering/conditioning 

Thursday, April 04, 2024, 12:06

Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm

conditioning tube WO = 44692-13 (4th conditioning with this tube)

End-caps on the graphite cartridge have holes for outgassing.  One spring each end in the Ta container

initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT

OMEGA slope = 0.99

Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr

Mas current~400A (1900 C)

 


Friday, April 05, 2024, 09:04  

Ramping to 85A done and pressure trending down.  Will continue ramp to 120A


Friday, April 05, 2024, 16:01

Starting rampdown at -2A/min

IGP1= 3.2e-06 Torr

 

Entry  Wednesday, April 03, 2024, 06:46, Darwin Ortiz Rosales, TiC, , LP TUBE, Done, 240402TiC 

Wednesday, April 03, 2024, 06:46

 

Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm

conditioning tube WO = 44692-13

End-caps on the graphite cartridge have holes for outgassing.  One spring each end in the Ta container

initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT

OMEGA slope = 0.99

Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr


Wednesday, April 03, 2024, 06:49

initial IGP1= 1.28e-06 Torr


Wednesday, April 03, 2024, 09:26

IGP1= 2.3e-05 Torr

TGHT = 78 A, 1.3V

Will continue ramp as planned.

 


Wednesday, April 03, 2024, 11:37

Ramping at 2A./min to 400A


Wednesday, April 03, 2024, 14:01

expected 1900C at 401A

leaving at 402A for 4 hours.  Rampdown start at 4:10 pm at -2A/min

Entry  Thursday, February 29, 2024, 07:40, Darwin Ortiz Rosales, TiC, , LP TUBE, Done, 240228TiC conditioning TiC_240228_Conditioning_Temperature_vs_Current.png

Thursday, February 29, 2024, 07:40

Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with _________ D shaped discs in a 12mm graphite cartridge with usable 11mm

conditioning tube WO = 44692-13

End-caps on the graphite cartridge have holes for outgassing.  One spring each end in the Ta container

initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT

OMEGA slope = 0.99

Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr


Thursday, February 29, 2024, 07:43

Initial IGP1=  9.31e-7 Torr


Thursday, February 29, 2024, 17:43

Temperature profile suggests 1900 C at 400A.  Now at 400A.  Will keep at this current for 4 hours.

manually ramped the last few amps.

TGHT= 400A, 7.3 V OMEGA = 1901C


Thursday, February 29, 2024, 22:20

IGP1=2.1e-6 Torr

started ramping down at -2A/min

 

Entry  Wednesday, February 21, 2024, 06:23, Darwin Ortiz Rosales, TiC, , LP TUBE, Done, 240220TiC conditioning 

Wednesday, February 21, 2024, 06:22

Ta container tube, wrapped in 4 Ta foil heat-shields, and loaded with 201 D shaped discs in a 12mm graphite cartridge with usable 11mm

conditioning tube WO = 44692-13

End-caps on the graphite cartridge have holes for outgassing.  One spring each end in the Ta container

initial heating @ 2A/min to 90 A then 1A/min to 120A TGHT

OMEGA slope = 0.99

Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr


Wednesday, February 21, 2024, 09:12

IGP1 initial = 9e-07 Torr

Starte at 3A/min to 90A


Wednesday, February 21, 2024, 09:21

increased autoramp to 4 A/min until pressure starts rising, then will slow down or pause


Wednesday, February 21, 2024, 09:32

At 74A, paused.  Will continue at 2A/min TGHT


Wednesday, February 21, 2024, 09:40

Pausing at 87A. 


Wednesday, February 21, 2024, 10:34

pressure dropping.  restarting ramp up to 120A at 2A/min


Wednesday, February 21, 2024, 10:37

From previous TiC 220206, will heat up fast until 250A and then at 1A/min until 300A to better resolve out-gassing profile


Wednesday, February 21, 2024, 12:05

Changed ramp to 1A/min to 300A


Wednesday, February 21, 2024, 13:10

Manually ramped up for a while

increased ramp speed to 2A/min

regression line started to match previous one after 1300C


Wednesday, February 21, 2024, 13:16

increased ramp rate to 4A/min to 420A


Wednesday, February 21, 2024, 13:37

Note: the temperature became unrealistic.  suspect window condensate.  Will use regression and to to 441A


Wednesday, February 21, 2024, 13:54

reached 441A, 7.6V

leaving for 3.5 hours or when pressure drops to 2-3 e-06 Torr


Wednesday, February 21, 2024, 18:56

IGP1=2.9e-06 Torr

starting rampdown at -2A/min

Entry  Wednesday, February 07, 2024, 22:49, Darwin Ortiz Rosales, TiC, 44692-11, LP TUBE, Done, 240206TiC conditioning 

Wednesday, February 07, 2024, 22:36

Ta container tube TaC coated, wrapped in 4 Ta foil heat-shields, and loaded with 320 D shaped discs in a 12mm graphite cartridge with usable 11mm

Endcaps on the graphite cartridge have holes for outgassing

initial heating @ 2A/min to 90 A then 1A/min to 120A TGHT

OMEGA slope = 0.99

Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr


Thursday, February 08, 2024, 06:18

Starting heat ramp tght

initial pressure = 8.1e-07 Torr IGP1


Thursday, February 08, 2024, 06:54

start of gasoff observed. paused ramp and will continue at 1A/min


Thursday, February 08, 2024, 07:24

lowered TGHT current to 75 A as pressure increasing too rapidly.  will leave at this current until pressure drops


Thursday, February 08, 2024, 09:11

continuing ramp to 120A on TGHT


Thursday, February 08, 2024, 09:24

Increasing ramp to 2A/min to 250A on TGHT


Thursday, February 08, 2024, 10:52

Increased ramp to 3A/min to 250A on TGHT


Thursday, February 08, 2024, 11:10

Everything looks good will continue to 300 A at 3A/min TGHT


Thursday, February 08, 2024, 11:33

Pausing heating at 285A, 4.8V TGHT

OMEGA reads 1430C

Will let pressure drop and then proceed ramping slowly @ 0.2A/min


Thursday, February 08, 2024, 13:53

IGP1= 2.4e-06 Torr

OMEGA = 1432 C

ramp at 0.2A/min towards 1550C


Thursday, February 08, 2024, 14:07

pressure very stable.  will increase to 0.4 A/min


Thursday, February 08, 2024, 15:24

increasing ramp rate to 1A/min

IGP1 = 2.5e-06 Torr


Thursday, February 08, 2024, 18:05

1900 C on OMEGA

will leave 3-4 hours depending on pressure



Thursday, February 08, 2024, 21:10

No additional pressure peaks observed and pressure on IGP1=  1.9e-06 Torr

TGHT= 460 A, 8.1V

OMEGA= 1860 C

ramp down at -2A/min

 

 

 

Entry  Thursday, December 14, 2023, 09:58, Darwin Ortiz Rosales, SiC, 41369-2, HP-SIS, Done, 231208SiC conditioning Screenshot_2023-12-14_133432.png

Thursday, December 14, 2023, 09:53

Target left pumping down in Evap2 overnight. 

Initial weight including protective jig = 1474.3 g

Total number of target foils:388 

 10 analysis discs: 5x 220727-2 labelled as A and 5x 231123-2 labelled as B on the right side (front) of container.  Order of discs ABABABABAB.

Total length packed 15.5 cm

container has 3 Ta heat shields including the inner made of three pieces as to cover the center block.

No endcaps inserted to facilitate out-gassing

Ta coated spring at  both ends

ramp to 500A @ 1A/min TGHT and to 230A on TBHT

max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)

Then temperature = 1800C

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 5.00 e -4 Torr

Bad vac at 5.00 e-2 Torr

 IGP1= 9.3e-07 Torr at start of initial ramp.


Thursday, December 14, 2023, 09:56

Started initial ramp up 1A/min on both heaters


Thursday, December 14, 2023, 11:03

Pressure dropping.  Will increase ramp speed to 2A/min on both heaters (1A/30s)


Thursday, December 14, 2023, 11:17

pressure dropping.  Increase ramp to 4A/min (2A/30s)

Will stop and ramping for temperature measurements


Thursday, December 14, 2023, 13:28

Increased ramp to 5A/min (2.5A/30s)

 Will heat to 703A on TGHT and leave for 4 hours

Entry  Wednesday, December 06, 2023, 09:57, Darwin Ortiz Rosales, SiC, 45447-4, HP-FEBIAD, Done, 231204SiC conditioning 

Wednesday, December 06, 2023, 09:47

Target number of foils:370

Analysis discs 16 A and 16B interspersed on the end further from the laser

A are discs produced using new method and B are discs produced using milling.

Total length packed 16 cm (excluding the analysis discs)

container has 3 Ta heat shields (one inner around fins and center block, new type of 1st shield made up of three pieces)

No endcaps inserted to facilitate out-gassing

Ta coated spring at  front end

ramp to 120A @ 1A/min TGHT and to 120A on TBHT hold there until pressure drop, then ramp to 500A on TGHT and 230A TBHT.

max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)

Then temperature = 1800C

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 5.00 e -4 Torr

Bad vac at 5.00 e-2 Torr

 IGP1= 1e-06 Torr at start of initial ramp.


Wednesday, December 06, 2023, 09:56

System left to drop pressure over previous night and now at 120A.  waiting for pressure drop.

 

 


Wednesday, December 06, 2023, 11:18

increased ramp rate to 2A/min


Wednesday, December 06, 2023, 14:41

increased ramp to 3A/min on TGHT and stopping to allow pressure to stabilize before taking temperature readings

Top temperature 1800C at 710 A but started dropping.  Increased current to 750A and left there for 4 hours.

Cool down at -2A/min TGHT and -1A/min TBHT


 

 