Entry  Friday, November 01, 2013, 17:20, Anders Mjos, , , , Problems, Backing pump needs new filter 
    Reply  Monday, November 04, 2013, 14:02, Anders Mjos, , , , Maintenance, Backing pump replaced 
Message ID: 93     Entry time: Friday, November 01, 2013, 17:20     Reply to this: 94
Author: Anders Mjos 
Target Material:  
Target Oven W.O#:  
Source:  
Status: Problems 
Subject: Backing pump needs new filter 

The source of the poor vacuum in the backing line seems to be related to a dirty filter. We will try to find a replacement filter next week.

The problem seem to have started September 17th, when backing preassure CG1A went from 40 mTorr to 130 mTorr. CG1B remained around 30 mTorr.