Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_2  Not logged in ELOG logo
Entry  Thursday, October 02, 2014, 11:26, John Wong, Empty, , , Maintenance, Broken insulators  
    Reply  Friday, October 03, 2014, 13:02, Anders Mjos, Empty, , , Maintenance, Broken insulators  NewInsulators.jpgBrokenInsulators.jpg
Message ID: 159     Entry time: Thursday, October 02, 2014, 11:26     Reply to this: 161
Author: John Wong 
Target Material: Empty 
Target Oven W.O#:  
Source:  
Status: Maintenance 
Subject: Broken insulators  

 Thursday, October 02, 2014, 11:22

It was found that after the last process, Evap#2 has broken insulators - the cylinder insulator that supports the target centre legs and the block insulator that supports the terminals.  

Informed Anders/Rick.


 