  463   Tuesday, October 08, 2019, 14:16 Aaron SchmidtSiC HP-FEBIADIn progressTemp measurements.

Tuesday, October 08, 2019, 14:14: Remove Flex line HS. 

HS: 42752-1

Waterlines not open yet.

Tuesday, October 08, 2019, 14:15: roughing.

Tuesday, October 08, 2019, 14:24: Turbo pump on. 

Tuesday, October 08, 2019, 14:32: TP @ speed. 


Wednesday, October 09, 2019, 13:24 

The initial pressure was 3.25e-7 Torr

The current was manually increased to 25 A on both TBHT and TGHT  at a rate of 1 A each 30 s for both heaters.


Wednesday, October 09, 2019, 13:33

At 1 pm an additional ram was made to TGHT 350 A and TBHT 200 at same rate.

  466   Friday, November 15, 2019, 13:26 Aaron SchmidtSiC HP-FEBIADProblems resolvedTemp map testing - 1. (Leak issue)

 HS 42752-5 - Setup for Temperature mapping.

Friday, November 15, 2019, 13:26: Roughing. 

Friday, November 15, 2019, 13:36: Turbo pump on. 


Monday, November 18, 2019, 07:46: Waterlines opened. Vacuum ok @ 3.56e-07T.

Monday, November 18, 2019, 07:48: PS on.

Monday, November 18, 2019, 09:21: PS off. Vacuum slowly spiked to 1.23e-06T. Indicative of a small water leak. 

Monday, November 18, 2019, 09:24: HS waterlines purged. vacuum dropped to 5.54e-07T. 

Monday, November 18, 2019, 09:27: Valves closed. TP off. BP off.

Monday, November 18, 2019, 10:27: Venting.

Monday, November 18, 2019, 11:06: Gaskets checked / replaced. Roughing. 

Monday, November 18, 2019, 11:14: turbo pump on. 

Monday, November 18, 2019, 14:19: Waterlines opened. 

Monday, November 18, 2019, 14:23: Response on vacuum. Leak is still present & a higher rate (Has an immediate response). Turbos off. 

Monday, November 18, 2019, 14:28: Venting. 

Monday, November 18, 2019, 14:49: turbo pump on. 


Tuesday, November 19, 2019, 07:07: Waterlines opened. Leak is present.  Turbo pump off. 

Tuesday, November 19, 2019, 11:24: After venting, changed 1 gasket. Setup LD & completed a leak check with the lines pressurized to 75 PSI of He. 

Tuesday, November 19, 2019, 11:25: Roughing. 

Tuesday, November 19, 2019, 11:33: Turbo pump on. 


Wednesday, November 20, 2019, 08:59: Waterlines opened. Leak is present.  Turbo pump off.  

Wednesday, November 20, 2019, 11:26: FEBIAD Removed. U-Line installed to check Evap 2 Connection. FEBIAD examined outside. 

Wednesday, November 20, 2019, 11:34: Turbo pump on. 

Wednesday, November 20, 2019, 13:05: HPA off (Was running through HS line still. Vac @ 5.54e-06T).  

Wednesday, November 20, 2019, 13:07: Open waterline. Vacuum @ 3.88e-06T & dropping steadily.  

Wednesday, November 20, 2019, 13:12: Vacuum @ 3.69e-06T & dropping. No leak detected via Vac. 

Wednesday, November 20, 2019, 13:14: Waterline Closed / purged. Turbo pumps off. 

Wednesday, November 20, 2019, 13:58: Turbo pump on. 

Wednesday, November 20, 2019, 13:50: Cleaned seal / FEBIAD re-installed. Roughing.


Thursday, November 21, 2019, 08:06: Waterlines opened. Vacuum ok @ 4.10e-07T. 

Notes:

1) The FEBIAD left cooling line was the culprit for the leaks. A fine copper build up was noted on the gasket /  sealing face. Images included. 

2) Evap 2 was leak checked separately as well & is OK.

Attachment 1: Test_FEBIAD_2019_-_Nov_-_Leak.docx
Attachment 2: Evap_2_cooling_-_1.jpg
Evap_2_cooling_-_1.jpg
Attachment 3: Test_FEBIAD_Left_HS_cooling_line_-_1.jpg
Test_FEBIAD_Left_HS_cooling_line_-_1.jpg
Attachment 4: Test_FEBIAD_Left_HS_cooling_line_-_2.jpg
Test_FEBIAD_Left_HS_cooling_line_-_2.jpg
  467   Thursday, November 21, 2019, 08:10 Aaron SchmidtSiC HP-FEBIADIn progressTemperature mapping.

 Thursday, November 21, 2019, 08:09: PS on. Leak issue resolved (Evap 2 Elog 466). Vacuum @ 4.10e-07T.

Thursday, November 21, 2019, 08:15: Auto-ramping TGHT / TBHT @ 2 A per min to 300 / 150 A. 

  468   Friday, November 22, 2019, 18:32 Fernando Maldonado & Marla Cervantes TaC HP-FEBIADIn progressTaC coating/sintering

 Friday, November 22, 2019, 18:18:

 

 

Friday, November 22, 2019, 18:18: Roughing

Friday, November 22, 2019, 18:23: Turbo on .

Friday, November 22, 2019, 18:32: Turbo at speed 

 

  469   Saturday, November 23, 2019, 14:03 Darwin Ortiz RosalesTaC42464-3HP-FEBIADDoneTaC coating/sintering

12.3

Saturday, November 23, 2019, 14:00

Container coated with TaC and wrapped with 3 Ta heat shields.

Desired temperature= 1900 C, Omega Slope set = 0.990, Auto TGHT at 0.2A/min to reach 400A, TGHT will be tapped up accordingly to reach desired Temp.

TBHT will be set fixed at 230 A (max). 

Good vac at 3.00e -5 Torr

Bad vac at 5.00e-5 Torr

Chamber pump down was started on Friday November 22; however.

No leaks were observed when turning water lines on.

IGP1= 4.6e-07 Torr


 Saturday, November 23, 2019, 15:30

autoramp at 0.5A /min up to 50A for both TGHT and TBHT and maintained for 1 hour.


Saturday, November 23, 2019, 16:15

IGP1= 1.1e-06 Torr

Auto Ramp to 450 A on THGT and 230A on TBHT at 0.5A/min


Saturday, November 23, 2019, 23:44

IGP1= 5.2e-06 Torr

TGHT = 248A, 2.9V  TBHT= 233A 2.9V

Increased ramp step to 1A/min to 620 A


Sunday, November 24, 2019, 00:14

IGP1=1.9e-06 Torr

TGHT = 274.3, 3.3V   TBHT= 233A, 2.9V

 


Sunday, November 24, 2019, 07:33

IGP1=3.2e-06 Torr

OMEGA= 1490C

TGHT = 619 A, 9.1V   TBHT=233A, 2.9V

Continue ramping THGT at 1A/min to 700 A


Sunday, November 24, 2019, 10:05

IGP1= 2.1 e-05 Torr

OMEGA= 1676 C

TGHT= 700A, 10.6V   TBHT= 233A, 2.0V

Start autoramp to 780A as per regression in attachment


Sunday, November 24, 2019, 13:22

Autoramp to 795A  for TGHT


Sunday, November 24, 2019, 21:16

OMEGA= 1854 C

TGHT= 789.6A, 12.27V  TBHT= 233.A, 2.9V

IGP1= 2.0e-05

Will allow pressure to stabilize lower.


Sunday, November 24, 2019, 22:16

TGHTT= 789.6A, 12.3V TBHT=233.3A, 2.9V

OMEGA=1855C

IGP1 = 6.9e-06Torr

Start cooling TGHT at 2A/min and TBHT at 1A/min

Attachment 1: HPFIBIAD20191124.PNG
HPFIBIAD20191124.PNG
  471   Tuesday, November 26, 2019, 15:21 Darwin Ortiz RosalesSiC42464-3HP-FEBIADDoneConditioning of SiC discs (sintering) (RUSH)

Tuesday, November 26, 2019, 14:53

Total number of foils: 504

Total length packed 17.4 cm

container has 3 Ta heat shields.

No endcaps inserted to facilitate out-gassing

Two TaC coated Ta wire springs inserted at either end.

Initially to ramp TGHT and TBHT to 50A at 1A/min

Then heat manually to OMEGA ~1400 C , ramping TGHT manually and automatically  to reach 530A A (Omega slope set = 0.990)

Then temperature= (Correected to 1800C) 1900 C, Omega Slope set = 0.990, manually and automatically ramp to 700A, TGHT will be tapped up accordingly to reach desired Temp.

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 3.00 e -5 Torr

Bad vac at 5.00 e-5 Torr

System experienced some vacuum issues due to cooling water leak in a heatshield line. 

Evaluation discs not included because no space.

Total Green disc mass measured = 58.250 g

 


Tuesday, November 26, 2019, 15:00

IGP1= 7.4e-06 Torr.  No leak issues found after last fix (Anders will add details).


Tuesday, November 26, 2019, 15:33

TGHT= 52.7A, .22V   TBHT= 49.3A, .52V

IGP1= 7.202 e-06 Torr (trending up so will allow to stabilize).


Wednesday, November 27, 2019, 06:09

left with autoramp waiting for vac to drop but no advance overnight.

Pressure did not seem to drop back below 3e-5 Torr magnitude, therefore not much advance in current ramp.


Thursday, November 28, 2019, 11:15

Continued ramping manually 

OMEGA = 1429 C  (0.99 slope), TGHT = 542A, 7.8V

With slope = 1.08 OMEGA = 1724 C, therefore staying at 0.99 slope

TaC coating sintering  plot suggests 753A to reach 1800C (See attachment 1)

Windows a little bit coated but not enough to disturb laser. 


Thursday, November 28, 2019, 12:17

TGHT =753A, 11.8V since 12:00 noon. 

TBHT= 233.4A, 3.3V

OMEGA= 1735 C (0.99 slope)


 Thursday, November 28, 2019, 13:01

OMEGA = 1860C (1.08 slope)


 Thursday, November 28, 2019, 14:38

OMEGA temperature began to creep up to ~1880.  Tapped TGHT current down to 733.5A, 11.4V


Thursday, November 28, 2019, 15:12

Checked windows and no significant additional buildup of obstructive material.

Temperature creeping up again.  Tap down TGHT current to 729 A, 11.2 V

OMEGA = 1870C at slope 1.08


 Thursday, November 28, 2019, 16:03

Temperature increase to 1880C

Tap down TGHT current to 715A, 10.9V

OMEGA= 1870 C (slope = 1.08)


Thursday, November 28, 2019, 16:22

Temperature creep to 1880 C

Tap down TGHT to 700A, 10.8V

OMEGA= 1845C

IGP1=2.2e-06 Torr


Thursday, November 28, 2019, 16:37

IGP1= 1.9e-06 Torr

OMEGA = 1850C (1.08 slope)

TGHT = 692A, 10.5V  TBHT= 233A, 3.2V

 

Initiating pressure ramp at -2A/min on TGHT and -1A/min on TBHT


Thursday, November 28, 2019, 16:45

IGP1= 1.28e-06 Torr

OMEGA= 1770 C (1.08 slope)

TGHT = 650A, 9.8V

ramp TGHT at -3.5A/min maintain TBHT at -1A/m in


 Thursday, November 28, 2019, 17:11

IGP1= 1.14e-06 Torr

OMEGA = 1730 C (1.08 slope)

ramp TGHT at -5A/min maintain TBHT at -1A/m


Thursday, November 28, 2019, 17:20

IGP1- 8.9e-07 Torr

OMEGA=1636C

ramp TGHT at -6A/min maintain TBHT at -1A/min


 Thursday, November 28, 2019, 17:34

IGP1= 7e-07 Torr

OMEGA= 1500 C (1.08 slope)

ramp TGHT at -8A/min maintain TBHT at -1A/min

TBHT = 183A


 OMEGA 1180C

TGHT =300 A

TBHT = 155A

Initiated -15A/min TGHT and -4A/min TBHT

IGP1= 5.2e-07 Torr


OMEGA below 1000C

begin manual tapdown


Thursday, November 28, 2019, 19:42

Target was dismounted after cooling.  Two graphite discs and end caps inserted.

 

Attachment 1: HPFIBIAD20191124-SinteringTaC.PNG
HPFIBIAD20191124-SinteringTaC.PNG
  472   Tuesday, November 26, 2019, 15:43 Anders MjosSiC42464-3HP-FEBIADProblems resolvedWater to vacuum leak on heat shield line

This morning, the vacuum responded to shutting of the water of the heat shield circuit (leak rate without pumping leveling out). The vacuum chamber was vented and the heat shield with flexible lines was replaced with another heat shield with fixed lines. The chamber was again pumped down and water opened at ~150 mTorr to test the leak up rate without pumping. No leaks apparent, so continued pumping down with turbo pump. At a vacuum of about 1E-6 Torr the water was again supplied to the heat shield circuit and an increase in vacuum could be observed. Stopped the turbo pump and prepared to vent. Two new heat shield lines were brazed in the machine shop and fitted by Maico after lunch. During this time one of the old lines (from heat shield to feedthrough in box) was leak tested and a leak found at a location just above the VCR. The line had been twisted and due to the twist developed a leak. With the two lines replaced, the vacuum was pumped down again and water could be supplied without any increase in vacuum pressure at 1E-6 Torr. To facilitate the new copper tubing, the restraining bracket for the heat shield VCRs was not mounted. It will have to be fitted later. Until then, please contact Anders for help in removing the heat shield to prevent any damage to the new lines.

  473   Wednesday, November 27, 2019, 17:45 John WongSiC42464-3HP-FEBIADDoneConditioning of SiC discs (sintering) (RUSH)

Darwin Ortiz Rosales wrote:

Tuesday, November 26, 2019, 14:53

Total number of foils: 504

Total length packed 17.4 cm

container has 3 Ta heat shields.

No endcaps inserted to facilitate out-gassing

Two TaC coated Ta wire springs inserted at either end.

Initially to ramp TGHT and TBHT to 50A at 1A/min

Then heat manually to OMEGA ~1400 C , ramping TGHT manually and automatically  to reach 530A A (Omega slope set = 0.990)

Then temperature= 1900 C (Correction = 1800 C, NOT 1900 - JW), Omega Slope set = 0.990 (use 1.08, check temp, JW), manually and automatically ramp to 700A (check temp to see if it's matching with the 1.08 slope), TGHT will be tapped up accordingly to reach desired Temp.

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 3.00 e -5 Torr

Bad vac at 5.00 e-5 Torr

System experienced some vacuum issues due to cooling water leak in a heatshield line. 

Evaluation discs not included because no space.

Total Green disc mass measured = 58.250 g

 


Tuesday, November 26, 2019, 15:00

IGP1= 7.4e-06 Torr.  No leak issues found after last fix (Anders will add details).


Tuesday, November 26, 2019, 15:33

TGHT= 52.7A, .22V   TBHT= 49.3A, .52V

IGP1= 7.202 e-06 Torr (trending up so will allow to stabilize).

 

 Wednesday, November 27, 2019, 17:44

I'll take over from here to step up the target heater, and I'll coordinate it with Darwin. 


 Wednesday, November 27, 2019, 20:36

Note: Sintering temp should be at 1800 C, NOT 1900.  Use Omega slope 1.08 and check temperature.  Correction made on elog #471.

Continue to step up TGHT and TBHT, keeping vacuum below 1.5 e-5 Torr. 


 Thursday, November 28, 2019, 03:06

TGHT reached to 400A/5.29V, TBHT at 230A/3.13V. 

Vacuum coming down from 1.3 e-5 Torr.

OMEGA = 1105 C (slope at 0.99).

Instructions for Darwin:

1.  Confirm temperature - check the temp plot from the TaC coating step. 

2.  Change OMEGA slop to 1.08 - check to see if this matches the temp plot.  If not, bring it back to 0.99.

3.  Continue to step up TGHT, check temp at 1400C (change slop 1.08 and check), 1500 C, 1600 C (check windows for coating - if any coating, then OMEGA is no longer useful hereon)

4.  Use the temp plot and continue to tap up TGHT to reach 1800 C and hold it for at least 4 hours or until the vacuum goes below 1 e-6 Torr then proceed with cooling down.

5.  Use the auto cooling program for TGHT (-2A/min) and TBHT (-1A/min)

Note:  For ramping up TGHT, keep vacuum below 1.5 e-4 Torr and keep tapping up to reach 1800 C.  Above 1100 C, this should be a quick step to get to 1800 C; should take < 2 hrs to get there.  

See the striptool or the attachment below to see how I did it. 

Once the chamber is cool down, take out a few samples for SEM analysis. 

Good luck!


 

Attachment 1: SiC_42464-3_RUSH_400A.JPG
SiC_42464-3_RUSH_400A.JPG
  535   Tuesday, March 09, 2021, 11:54 Darwin Ortiz RosalesTaC42464-1HP-FEBIADDoneTaC coating/sintering

Tuesday, March 09, 2021, 11:54 

 Container coated with TaC and wrapped with 3 Ta heat shields.

Desired temperature= 1900 C, Omega Slope set = 0.990, Auto TGHT at 0.2A/min to reach 400A, TGHT will be increased  accordingly to reach desired Temp.

TBHT will be set fixed at 230 A max).

Good vac at 3.00e -5 Torr

Bad vac at 5.00e-5 Torr

Chamber pump down


Wednesday, March 10, 2021, 08:32

IGP1 = 2.6 e -07 Torr

Start autoramp @ 1A/min to 40 A on both TGHT and TBHT

***Autoramp aborted due to work on EF12 affecting EVAP2***

Will have to resume Thursday or Friday

 


Saturday, March 13, 2021, 7:54

  IGP1= 3.8e-07 Torr

Initiate heating @ 0.5A/min TBHT and TGHT to 60 A


Saturday, March 13, 2021, 23:01

IGP1 = 2.7e-07Torr

TGHT = 60.5A, 0.7V

TBHT= 60.0A, 0.7V

Initiate ramp @ 1 a/min to 400 A on TGHT and 230A on TBHT


Sunday, March 14, 2021, 08:45

IGP1= 8.2e-07 Torr

TGHT = 400A, 5.6V

TBHT = 232.9A, 3.0V 

OMEGA = 1142 C

Continue ramping to 460 A on TGHT at 1a/min


 Sunday, March 14, 2021, 10:11

IGP1 = 1.0 e-06 Torr

TGHT= 460.4 A, 6.5 V

TBHT = 232.9 A, 3.0 V

OMEGA = 1239 C

Will ramp up to 500 A at 1a/min on TGHT


Sunday, March 14, 2021, 10:53

 IGP1 = 1.3 e-06 Torr

TGHT= 495 A, 7.2 V

TBHT = 232.9 A, 3.0 V

OMEGA = 1316 C

Will ramp up to 600 A at 1a/min on TGHT

 


Sunday, March 14, 2021, 12:45

IGP1 = 3.0 e-06 Torr

TGHT= 604 A, 9.1 V

TBHT = 232.9 A, 3.1 V

OMEGA = 1610 C

Will ramp up to 660 A at 1a/min on TGHT 

 


Sunday, March 14, 2021, 17:01

IGP1= 2.4e-06 Torr

TGHT =  664 A, 10V

TBHT = 232.9 A, 3.1V

OMEGA = 1733 C

tapping TGHT to 740 A

OMEGA = 1883 C


 Sunday, March 14, 2021, 21:45

IGP1= 3.1e-06 Torr

TGHT =  744A, 11.5V

TBHT = 232.9 A, 3.2V

OMEGA = 1875 C

Start cooling TGHT @-3A/min and TBHT @-1A/min

 

  567   Thursday, February 10, 2022, 08:58 Darwin Ortiz RosalesSiC HP-FEBIADDone 

Thursday, February 10, 2022, 08:52 

Total number of foils: 528 ( including 10 analysis discs)

Weight without springs = 1521.9 g (includes heatshields and T bar)

Total length packed 18.1 cm (including 10 analysis discs that will be removed)

container has 3 Ta heat shields.

No endcaps inserted to facilitate out-gassing

Ta coated spring at  ends

Initially to ramp TGHT and TBHT to 50A at0.5 A/min

Then heat automatically heat to OMEGA ~1400 C , then continue to max 530A on TGHT and 230A on TBHT (Omega slope set = 0.990)

Then temperature = 1800C

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 3.00 e -4 Torr

Bad vac at 5.00 e-2 Torr

 IGP1= 1.0 e-06 Torr at start of initial ramp


IGP1 = 5.7 e-06 Torr

TGHT = 50.0 A, 0.6 V

TBHT = 50.0A, 0.5 V

continue to ramp up at 0.5A/min to 200A


Friday, February 11, 2022, 07:59 

IGP1=3.0e-07 Torr and stable

TGHT= 201A, 2.8V

TBHT = 201A, 2.6V

continue autoramp at 1A/min to 230A on TBHT and 450A on TGHT


Friday, February 11, 2022, 12:41

IGP1= 6.6e-05 Torr

TGHT= 450A, 6.5V

TBHT= 232A, 3.1V

OMEGA = 1258C

Allowing pressure to drop.  Will continue ramp up when [pressure around 9-e-6 Torr


Friday, February 11, 2022, 13:59

IGP1= 2.4e-05 Torr

Will ramp up at 1A/min to 550A on TGHT


Friday, February 11, 2022, 15:54  

IGP1= 2.4e-05 Torr

TGHT= 551.0A, 8.3V

TBHT=232A, 3.2V

OMEGA= 1426 C

ramp to 600 A @ 2A/min


Friday, February 11, 2022, 16:23

TGHT= 600.1A, 9.3V

TBHT= 232A, 3.2V

OMEGA = 1612C

ramp to 689 @2A/min to 1800 C as projected in regression plot attached 


Friday, February 11, 2022, 21:20 

Evap has been at 1800 +/- 20 C for 4 hours and 10 minutes

OMEGA 1802 C

TGHT = 689 A, 11.0V

TBHT=232.8 A, 3.26V

IGP1= 1.3e-05 Torr and stabilizing.  

will start cool down at -2A/min TGHT and -1A/min TBHT

 

 

  569   Wednesday, March 09, 2022, 06:27 Darwin Ortiz RosalesTaC42464-2HP-FEBIADDoneTaC coating/sintering

 Wednesday, March 09, 2022, 06:25

Ta HP-FEBIAD was coated with TaC and wrapped with Ta heat-shields (3 layers)

Desired temperature = 1800 C , TBHT will be set fixed at 230A (max).

Evap 2 will be pumped down over previous night

Good vacuum = 3.00 e-4 Torr

Bad vacuum = 5.00 e-2 Torr

IGP1= 1.2 e-06 Torr

Start autoramp @1A/min to 60 A


Wednesday, March 09, 2022, 09:29

 TGHT= 60 A 0.67 V

TBHT = 60A 0.59V

IGP1= 1.77e-6 Torr

autoramp @ 2A/min to 120 A and monitor (both TGHT and TBHT)


Wednesday, March 09, 2022, 10:19

IGP1 was increasing to fast.  Manually lowered current to 105A on both TGHT and TBHT.

Will allow pressure to stabilize

Plant group requested maintenance work for EF12/13

Therefore, keeping system as is until further instructions from plant group.


Thursday, March 10, 2022, 15:18

Will resume ramp up to 120 A for both TGHT and TBHT @ 1A/min

 IGP1= 6.4 e-07 Torr

 


Thursday, March 10, 2022, 15:30

Increase ramp rate to 2A/min 


Thursday, March 10, 2022, 17:41

@ 245 A TGHT and 230A TBHT ramp back down to 100 A for both as OMEGA not displaying Temperature.  Will need to go in tomorrow to fix OMEGA 


Friday, March 11, 2022, 14:25

Ramping at 2A/min to 230A for both TGHT and TBHT


Friday, March 11, 2022, 15:17

IGP1= 1.23e-6 Torr

Continue Ramping TGHT @ 3A/min to 400 A keep TBHT at 230A


Friday, March 11, 2022, 22:22

@ TGHT 725 A 1800 C was reached on OMEGA

Kept there since 7:20 pm.  Start rampdown at 11:20 pm.

 


Friday, March 11, 2022, 23:19  

 IGP1= 6.9e-6 Torr

OMEGA= 1805C

TGHT= 725 A, 10.9V

TBHT= 232A, 3.1V

Start rampdown at -2A/min on TGHT and -1A/min for TBHT

 

  570   Wednesday, March 23, 2022, 10:52 Darwin Ortiz RosalesTaC44692-9HP-FEBIADDoneTaC coating

Wednesday, March 23, 2022, 10:49

Ta HP-FEBIAD was coated with TaC and wrapped with Ta heat-shields (3.5 layers) (two pieces around the fins only and 3 layers around the whole )

Desired temperature = 1800 C , TBHT will be set fixed at 230A (max).  TGHT expected to reach desired Temperature @~700A

Evap 2 was pumped down over previous night

Good vacuum = 3.00 e-4 Torr

Bad vacuum = 5.00 e-2 Torr

IGP1= 1.2 e-06 Torr

Start autoramp @0.5 A/min to 60 A


 Wednesday, March 23, 2022, 11:37

Increase autoramp to 1A/min to 60A for both TGHT and TBHT


Wednesday, March 23, 2022, 12:24

Pressure increasing at 60A so will leave at this current until pressure drops


Wednesday, March 23, 2022, 13:32

IGP1 = 2.9e-06 Torr

Will autoramp at 0.5A/min to 90A both TGHT and TBHT


Thursday, March 24, 2022, 16:35

1800C reached at 724A TGHT .  TBHT @ 230A.  Will keep at this temperature for 4 hours. 


Thursday, March 24, 2022, 20:20

 IGP1 = 6.9 e-06 Torr

OMEGA= 1828 C

TGHT = 724 A, 11.6 V

TBHT = 232.8 A, 3.1 V

Will start ramp-down at 2035 @ -2A/min TGHT and -1A/min TBHT

 

Attachment 1: image_2022-03-24_201954.png
image_2022-03-24_201954.png
  576   Wednesday, May 18, 2022, 09:59 Darwin Ortiz RosalesSiC44692-9HP-FEBIADDoneT-220516 Sintering SiC

 Wednesday, May 18, 2022, 09:46

Total number of foils: 415 ( including 10 analysis discs on the right side of the container)

Total weight = 1580 g (includes heatshields and T bar)

Total length packed 17 cm (including 10 analysis discs that will be removed)

container has 3 Ta heat shields.

No endcaps inserted to facilitate out-gassing

Ta coated spring at  front (right) side

Initially to ramp TGHT and TBHT to 30A at 3 A/min

then continue to and slow down ramp when pressure begins to increase

max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)

Then temperature = 1800C

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 3.00 e -4 Torr

Bad vac at 5.00 e-2 Torr

 IGP1= 7.1 e-07 Torr at start of initial ramp.  Note, first real operation with new noisy Turbo Pump.


Wednesday, May 18, 2022, 10:18

Pressure increase observed starting around 60A.  Ramped to 70 A and will leave until pressure stabilizes

After about 30 minutes pressure dropped so ramped up to 90 A @1A/min on both TGHT and TBHT


Wednesday, May 18, 2022, 11:37

pressure spike around 90A.  will leave until pressure stabilizes 


Wednesday, May 18, 2022, 12:54  

start autoramp to 100A at 1A/min.  IGP1= 1.4e-4 Torr


Wednesday, May 18, 2022, 13:15

autoramp to 150A @1A/min 


Wednesday, May 18, 2022, 13:41

 At 110A another spike in pressure.  System waiting for good vacuum


Wednesday, May 18, 2022, 15:24

ramped to 150A on both TGHT and TBHT.  Ramping to 200 A at @A/min for both TGHT and TBHT

currently IGP1=  2.0e-4 Torr


Wednesday, May 18, 2022, 15:33  

Pressure still trending down; therefore will start ramp at 4A/min to 400 amp on TGHT and 230A to TBHT


Wednesday, May 18, 2022, 16:22 

Increasing ramp to 4A/min on TGHT


Wednesday, May 18, 2022, 17:26 

switched to 6A/min in 1A/10s increments on TGHT


Wednesday, May 18, 2022, 17:43 

Set final current to 730 A as per regression attached.

 

 

 

 

 

 

 


Wednesday, May 18, 2022, 17:54

Final current on TGHT = 740A, 11.9 V

OMEGA = 1775 C

TBHT = 230A, 

Will leave for 4 hours

 


Wednesday, May 18, 2022, 19:56

Temperature dropped so increased current to 755A for the remaining of the time.


Friday, May 20, 2022, 08:58

Final notes:  The difference between initial and final mass was 6 g as expected.  Slight coating on window of evaporator may explain apparent temperature drop.  Next time will keep current at projected setting.  The material looks good with slight overheating on the outer discs of left side.

 

 

  578   Tuesday, June 07, 2022, 07:31 Darwin Ortiz RosalesSiC42464-2HP-FEBIADDoneT-220524 Sintering SiC

Tuesday, June 07, 2022, 07:19

Total number of foils: 403 ( including 5 analysis discs on the right side of the container)

Total weight = 1535.3 g (includes heatshields, spring and T bar)

Total length packed 16.4 cm (excluding 5 analysis discs that will be removed)

container has 3 Ta heat shields.

No endcaps inserted to facilitate out-gassing

Ta coated spring at  front (right) side

Initially to ramp TGHT and TBHT to 50A at 3 A/min

then continue to 80A and slow down ramp when pressure begins to increase

max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)

Then temperature = 1800C

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 3.00 e -4 Torr

Bad vac at 5.00 e-2 Torr

 IGP1= 7.6 e-07 Torr at start of initial ramp.


 Tuesday, June 07, 2022, 11:14

Ramping to 150A on TGHT and TBHT at 1A/min


Ramped TGHT and TBHT to 230A at 2A/min

Tuesday, June 07, 2022, 13:12

Ramping TGHT to 600A at 4A/min

TBHT at 230A, 3.0V


Tuesday, June 07, 2022, 16:41

TGHT= 740 A, 12.1V

TBHT= 232A, 3.0 V

OMEGA reading 1616C but questionable.  Will leave for 4 hours at 740A top TGHT.


Wednesday, June 08, 2022, 22:15

Early Wednesday morning the left TGHT bolt was found damaged.  The target leg was coated with bolt material rendering the Target inoperable.   

The Heatshield assembly was swapped and surfaces cleaned.  A "dummy" FEBIAD was installed to test if the system can withstand high current. 

The system was pumped down and ramped to 740A on TGHT at 4A/min.  It was then left at that current for 4 to 5 hours.

Currently starting rampdown at -2A/min to 0A. 

Photos of the incident attached in *eLog 580*.  IGP1= 5.7e-06 Torr

TGHT= 742A, 11.4V

  580   Thursday, June 09, 2022, 09:09 Darwin Ortiz RosalesTa HP-FEBIADDoneTroubleshooting

Thursday, June 09, 2022, 09:07

Yesterday, Wednesday June 08, 2022 @ ~3.00 pm a "dummy" target container was installed in EVAP 2 after the heatshield assembly had been swapped.

The purpose is to test correct functioning of the system.  Melting and evaporation on one of the bolts of the previous target container (eLog578) prompted the change in heatshield assembly and current testing.

TGHT was ramped up to 740A @ 4A/min, left to run at the final current for ~4.5 hours and then ramped down @-2A/min to 0A.

Will dismount dummy container this morning.

IGP1=2.5e-07 Torr


Thursday, June 09, 2022, 11:16

The target appears in good shape.  No abnormal behaviour. 

Picture attached are of the previous failed target eLog 578

 

Attachment 1: MicrosoftTeams-image_(3).png
MicrosoftTeams-image_(3).png
Attachment 2: MicrosoftTeams-image_(4).png
MicrosoftTeams-image_(4).png
Attachment 3: MicrosoftTeams-image_(5).png
MicrosoftTeams-image_(5).png
  582   Tuesday, June 14, 2022, 09:04 Darwin Ortiz RosalesTa37978-1HP-FEBIADDoneTaC coating sintering

Tuesday, June 14, 2022, 08:47

Ta HP-FEBIAD was coated with TaC and wrapped with Ta heat-shields (3 layers)

Desired temperature = 1800 C , TBHT will be set fixed at 230A (max).

Evap 2 will be pumped down over previous night

OMEGA slope= 0.990

Good vacuum = 3.00 e-4 Torr

Bad vacuum = 5.00 e-2 Torr

IGP1= 1.2 e-06 Torr

Start autoramp @2A/min to 80 A then autoramp heat @1A/min to 150 A.  Then autoramp TGHT to 675A and TBHT to 230A.


Tuesday, June 14, 2022, 08:49

IGP1= 0.13 Torr

*had timed out and it was off.  I RST and turned back on.*

Will wait for the pressure to drop to start heating


 Tuesday, June 14, 2022, 09:36

IGP1= 9.4e-06 Torr

Start autoramp @2A/min to 80A


Tuesday, June 14, 2022, 11:27

IGP1= 8.7 e-06 Torr Trending down. 

TGHT= 146A, 1.6V

TBHT= 146A, 1.7V

Has been ramping at 1A/min

Change ramp rate to 2A/min to 700A on TGHT and 230A on TBHT


Tuesday, June 14, 2022, 14:48

Change final current on TGHT to 675A, according to plot.  May change again. 

Currently TGHT=  537A, 7.7V 

IGP1= 4.4e-06 Torr


Tuesday, June 14, 2022, 18:46

Top temperature was 1825 Celsius at TGHT = 675A

Will start rampdown at 8:00 pm

 


 Tuesday, June 14, 2022, 20:01

TGHT= 675A, 10.3 V

TBHT= 230A, 3V

OMEGA= 1815C

IGP1= 3.9e-06 Torr

ramping down @-2A/min TGHT and -1A/min TBHT

  584   Tuesday, June 21, 2022, 09:48 Darwin Ortiz RosalesSiC37978-1HP-FEBIADDoneT-220617 sintering

Tuesday, June 21, 2022, 09:43

Total number of foils: 377 ( including 6 analysis discs on the right side of the container)

Total weight = 1454 g (includes heatshields, spring and T bar)

Total length packed 15.5 cm (excluding 6 analysis discs that will be removed)

container has 3 Ta heat shields and is coated

No endcaps inserted to facilitate out-gassing

Ta coated spring at  front (right) side

Initially to ramp TGHT and TBHT to 80A at 2 A/min

then to 120A and slow down ramp when pressure begins to increase

max approx 675A on TGHT and 230A on TBHT (Omega slope set = 0.990)

Then temperature = 1800C

TBHT will be set fixed at 230 A (max).  TBHT heated manually and automatically to max.

Good vac at 3.00 e -4 Torr

Bad vac at 5.00 e-2 Torr

 IGP1=3.6 e-07 Torr at start of initial ramp.

 


Tuesday, June 21, 2022, 13:54

IGP1= 7.1 e-05 and dropping.  Start ramp to 150A for both TGHT and TBHT @1A/min


Tuesday, June 21, 2022, 21:27

Increased ramp rate to 3A/min for TGHT to 675A


Tuesday, June 21, 2022, 22:38

Ramp up to 685 A on TGHT and leave for 4 hours. 

OMEGA = 1645 C but suspect reading not on Ta surface.


Wednesday, June 22, 2022, 02:28

IGP1=7.7e-6 Torr

OMEGA =1610C

TGHT = 685A, 10.5V

TBHT = 230A, 3V

initiate rampdown at -2A/min and -1Amin TGHT and TBHT

  586   Wednesday, June 29, 2022, 10:12 Darwin Ortiz RosalesTaC44692-10HP-FEBIADDoneTaC coating sintering

Wednesday, June 29, 2022, 10:07

Ta HP-FEBIAD was coated with TaC and wrapped with Ta heat-shields (3 layers)

Desired temperature = 1800 C , TBHT will be set fixed at 230A (max).

Evap 2 will be pumped down over previous night

OMEGA slope= 0.990

Good vacuum = 3.00 e-4 Torr

Bad vacuum = 5.00 e-2 Torr

IGP1= 1.2 e-06 Torr

Start autoramp @2A/min to 80 A then autoramp heat @1A/min to 150 A.  Then autoramp TGHT to 675A and TBHT to 230A.1


Wednesday, June 29, 2022, 10:13

Chamber isolation performed and no change of pressure observed.

Water leak test performed and no pressure change detected.

Starting ramp up


Wednesday, June 29, 2022, 13:23

Ramping to 675A on TGHT and 230A on TBHT @ 2A/min

Ramped TGHT to 680A, 10.6V  and held for 4 hours


Wednesday, June 29, 2022, 21:52

Started rampdown @-2A/min TGHT and -1A/min TBHT

  589   Thursday, August 25, 2022, 10:16 Darwin Ortiz RosalesTiC44692-10HP-FEBIADDoneTiC 220818 Sintering (TiC #6)

Thursday, August 25, 2022, 10:06

 

Target container is loaded with 379 Discs of TiC for Target and 5 extra discs for analysis on left end

Target length = 12.5

3 Ta foil heatshields and on TaC coated Ta spring on right side

Total weight including heatshields and spring = 1551.4 g   Final total weight = 1545.5 g

Final power should be ~10988 Watt

TGHT ramp up to 820A, and TGHT to 300A at 0.1A/min.

IGP1= 7.7e-7 Torr

Good vacuum =3.0e-05 Torr

Bad vacuum = 5e-04 Torr

Initial TGHT and TBHT autoramped @1A/min to 50A

TBHT mas 230A

TGHT max depends on final power

 


Thursday, August 25, 2022, 11:17 

Start autoramp at 1A/min to 80A on both TGHT and TBHT


Thursday, August 25, 2022, 11:54 

leaving at 80A until pressure stops rising

 


Thursday, August 25, 2022, 22:29

left to autoramp to 230A TBHT and 750 A TGHT since approximately 2:00 pm

Will leave ramping @1A/min to 750 A on TGHT

TBHT currently at 230A


 Friday, August 26, 2022, 07:27

TGHT = 850A, 9.3V

Started autoramp to 850A at 1A/min for TGHT

TBHT held at 230A

OMEGA = 1584C

 


Friday, August 26, 2022, 09:34

Target running at ~820A, 13.1 V since 9

Cooling to start between 1:15 to 1:30 pm

OMEGA reads 1668 C at top current

current reading oscillates between 812A and 828A and 13.1V  to 13.2V.

 


Monday, August 29, 2022, 12:21

Cooling at -2A/min for TGHT and -1A/min TBHT started on time on Friday August 26th.

Target remained under vacuum after cooling, over the weekend.

Target removed this morning and looks good. 5 discs removed for analysis

 

  609   Thursday, February 23, 2023, 18:24 Darwin Ortiz RosalesTaC45441-2HP-FEBIADDoneTaC coating sintering

Thursday, February 23, 2023, 18:20

Ta HP-FEBIAD was coated with TaC and wrapped with Ta heat-shields (3 layers) and 1 under layer that doesn't cover the middle section.

Desired temperature = 1800 C , TBHT will be set fixed at 230A (max).

Evap 2 will be pumped down to 5e-06 Torr range

OMEGA slope= 0.990

Good vacuum = 5.00 e-4 Torr

Bad vacuum = 5.00 e-2 Torr

IGP1=2.5 e-06 Torr

Start autoramp @1A/min to 80 A then autoramp heat @1A/min to 150 A.  Then autoramp TGHT to approx 675A and TBHT to 230A.1

 


Friday, February 24, 2023, 09:10

heated overnight @0.5 A/min to 400 A.  Then started heating at 1A/min to 600 A while taking readings for current/Temp regression.

regression so far points to 682A to get to 1800C.  Will continue taking readings and possible heat to 1850 C. 


Friday, February 24, 2023, 09:43

autoramping to 690A at 1A/min


Friday, February 24, 2023, 11:24

ramping manually to 690A from 650A


Friday, February 24, 2023, 11:32

4 hours at 330pm

TGHT 492A, 10.6V

TBHT = 230A, 3.2V

IGP1=5.11e-06 Torr

OMEGA =1840 C


Friday, February 24, 2023, 15:36

TGHT = 692A, 10.6V

TBHT = 230 A, 3.2V

OMEGA = 1835 C

IGP1= 2.4e-06 Torr

Starting rampdown at -2A/min TGHT and -1A/min TBHT