|
ID |
Date |
Author |
Target Material |
Target Oven W.O# |
Source |
Status |
Subject |
|
319
|
Wednesday, September 07, 2016, 15:02 |
John Wong | Empty | 39530-9 | HP-SIS | In progress | Sintering TaC coating container for SiC Target | Wednesday, September 07, 2016, 14:45
Container was previously coated with TaC solution and wrapped with 1-full length layer of Ta- heat shield around the fins.
Chamber is being pumped down. Vac at 5.6e-7 Torr before HS water valves were open; no leaks were detected.
Sintering Temperature 1900C (Omega slope @ 0.98); expected TGHT ~765A/11.90V, TGHT max at 230A.
Thursday, September 08, 2016, 18:14
At about 1600C, it was observed that the coating inside the tube seems to chip off (see attachment 1).
TGHT was ramped up to 745A/11.85V and TBHT to 230A/3.25V. Temperature measured on OMEGA/Mikron = 1914C/1881C; both instruments slopes set at 0.98.
Will remain at this TGHT current over night
Vac at 3.0e-6 Torr and coming down.
Friday, September 09, 2016, 11:01
Target has been heated at the stable temperature at 1914C (for OMEGA) and 1881C (for Mikron) with current at 745A/11.94V (see attachment 2) for almost 19 hours.
No fluctuation in p/s current or temperature was observed. The ramping up process is captured and can be view from the link below:
https://www.dropbox.com/sh/9lgtin54o17ds6j/AABn1-XjvK44mm74TjqTAmvta?dl=0
Pressure at 1.07e-6 Torr.
Cooling down TGHT at 2A/min and TBHT at 1A/min.
Continue to capture the cooling down process.
Friday, September 09, 2016, 15:17
While the target container was cooling down, the chip-like particle began obvious (see attachment 3).
Will inspect the container.. TGHT currently at 260A.
|
Attachment 1: coating_chipped_off.JPG
|
|
Attachment 2: autoTaC_sintering_20.JPEG
|
|
Attachment 3: coating_chipped_off_2.JPG
|
|
|
318
|
Tuesday, August 30, 2016, 15:25 |
John Wong | SiC | 40860-3 | LP-IG-LIS | Problems | Conditioning SiC#34. Note about the p/s voltage |
Laura Lambert wrote: |
Monday, August 08, 2016, 15:19
Previously sintered over weekend [see elog i.d 311]
Target container contains 471 discs of SiC [6 x 5 packs + 441 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 52.7172g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Conditioning temp = 1800C.
TGHT max = 450A. TBHT max = 230A.
Chamber is currently being pumped down.
Monday, August 08, 2016, 16:38
Target was not removed from evap2 after sintering, vented and cleaned windows only.
IGP1 = 5.5e-6 Torr
Stepped up manually to 80A, vacuum stable.
IGP1 = 3.2e-6 Torr
Initiating auto-ramp at 0.2A/min for the TGHT and 0.1A/min for the TBHT.
Thursday, August 11, 2016, 14:14
Tues the TGHT reached ~280A via auto-ramp
Evap2 was then tapped up manually to 480A/ ~1800C
Temperature readings on OMEGA have fluctuated up and down during conditioning process which was also observed for SiC#33
Also consistent with SiC#33, a lower current was required to reach 1800C during the conditioning process compared to the sintering process.
See attached link for data.
Tuesday, August 16, 2016, 16:25
TGHT remained at 480A, 9.2V for ~7 days.
IGP1 = 6.5e-6 Torr
OMEGA = 1470C [with window coating, so temperature reading compromised]
Initiating auto cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
Wednesday, August 17, 2016, 13:40
Vented in air and opened this morning.
Target broke
Target clearly heated to high.
See attached snapshot of striptool from conditioning process.
Will update later with photos of broken container
|
Tuesday, August 30, 2016, 15:17
A better look at the p/s voltage over the course of the constant heating at 480A. (see attachment).
The striptool shows the voltage was not giving a stable output. There were multiple occasions that the voltage dropped and then recovered; the obvious was on Aug 16. This indicates that the target was breaking up.
Finally on Aug 17, the voltage dropped and never recovered again - that indicates the target was broken. |
Attachment 1: Capture.PNG
|
|
|
317
|
Wednesday, August 24, 2016, 17:07 |
John Wong | SiC | 39814-V2-1 | LP-IG-LIS | Done | Sintering process for SiC#34 (2nd round) | Wednesday, August 24, 2016, 17:05
Target container was previously coated with TaC and sintered up to 1900C at 420A/7.01V
Container is loaded with beta-SiC 432 discs at 16cm in length.
Container is wrapped with Ta-heat shield; no end-caps are used at this time.
Chamber is being pumped down.
Thursday, August 25, 2016, 12:04
Chamber has been pumped down overnight. Pressure at 5.9e-7 Torr.
HS water valve opened; no leaks were detected.
Sintering temperature 1800C. TGHT will be set accordingly to get the desired temperature. TBHT max at 230A.
Thursday, August 25, 2016, 12:12
Tapped up TGHT/TBHT to 40A. Vac at 7e-6 and slowly going up but still below limit.
Monday, August 29, 2016, 11:04
TGHT and TBHT reached to 250A (3.65V)//230A(3.02V), respectively, and kept stable over the weekend.
Temp measured at 1372C with slope set at 1.04 (1230C at slope 0.98).
No visible coating on windows.
Setting up TGHT to reach 1800C; monitoring locally
Monday, August 29, 2016, 14:35
Stepped up TGHT to 390A/6.54V; light coating was observed on the windows. The temperature should be around 1800C which should be in line with the power (current) deposited in the container during the TaC coat sintering process (1900A at 420A); however, with the light coating the reading may be off.
Mikron was used to measured inside of the tube (away from the discs); temperature was measured at ~1800C, (see attachment) [adjusted slope at 1.00 to compensate the SiC disc and Ta]
Omega was used to measured the temperature of the discs. It is difficult to know what's the temperature inside the tube, so this measurement is only taken as a guideline. Slope changed from 1.04 to 1.15 to match Mikron's reading.
After heated at 390A for 30 mins, the windows are now coated. Temp reading is no longer reliable. The temperature could be above 1800C. Keeping a close monitor!!!
No blockage inside the tube was observed.
Will remain heating at 390A/6.44V for overnight before proceeding with the re-conditioning.
Tuesday, August 30, 2016, 10:41
Target was heated at 390A for over 10 hours and then cool down at 1A/min (see attachment#2). Windows were fully coated and Omega couldn't register any reading.
Chamber will be vented and target will be inspected before proceeding with the re-conditioning step.
Tuesday, August 30, 2016, 12:13
Target was inspected; no visible damage was observed (see attachment)
Material coated on the windows and the cu heat shields; all parts were wiped off with acetone.
No visible material build up inside the container.
Chamber is now being pumped down for re-conditiing.
Tuesday, August 30, 2016, 13:05
HS water valves open; no leaks detected.
Vac at 3.6 e-6 Torr.
Ready to set up TGHT/TBHT
Tuesday, August 30, 2016, 16:41
TGHT/TBHT stepped up to 340A (5.40V) /230A (3.1V), respectively.
Temperature was measured at 1835C at TGHT of 340A. Omega, Mikron and analogue pyrometer were all reading ~1800C inside the tube (not on the SiC surface). For that reason, I decided to stop the current at 340A, instead of 390A.
TGHT voltage is running stable.
No visible coating or blockage inside the tube was observed.
Wednesday, August 31, 2016, 11:53
A thin layer of coating is observed on both the side windows (see attachment 5). The temp reading is no longer reliable.
TGHT remains at 340A/5.45V. P/S voltage is performing steadily.
No clogging inside the tube is observed.
Setting up another Omega reader to measure temperature from the front window since this window is clear and won't get coated (see attachment #6).
Temperature measurement from the front window is ~1140C; this corresponds to the measurement from the analogue pyrometer with the correction of e=~0.2 for tantalum at 1100C.
Note: The temperature measurements should be taken as relative. Since the reading from the side windows isn't reliable any longer, the centre window will give some information how stable the temperature is holding during the reconditioning process. Continue to monitor.
Wednesday, August 31, 2016, 16:24
About two hours ago, I increased TGHT to 350A and stayed there for a few mins (see attachment 7). No change in temp was observed - that's mainly due to the coating on the windows. As for the temp measurement from the center window, a more power current input would require to see the change as heat is slowly propagating through the layers of Ta heatshields.
Local inspection on the target: no clogging inside the tube. Voltage/Current is stable at 340A/5.45V. Vac at 1.43e-7 Torr.
Wednesday, August 31, 2016, 23:00
Strange observation: Temperature readers on both omega have gone up. (see attachment 8).
I'm not sure if the temperature is reiiable. I actually saw the increase in temperature ~1850C last night around the same time; no change in TGHT current/voltage. By the next morning, it went back down to 1400C with significant coating on the windows.
Wednesday, August 31, 2016, 23:28
I had ISAC Op (Justin) to help me go into the Hotlab and take a look at the reading on Mikron. Indeed, it is reading about 2000C which is close to the Omega reading. He also looked into the tube through Mikron scope and found no clogging inside the tube.
To be safe, I am going to lower the TGHT heater down to reach ~1800C.
Wednesday, August 31, 2016, 23:41
Lower TGHT to 305A/4.81V; OMEGA reading at 1830C. Vac at 1.27e-7 Torr. Will remain at this current over night.
Thursday, September 01, 2016, 12:16
Checked on the target.
Temperature readings, right windows (omega)= 1726C, centre = 1100C (omega), left (Mikron) = 1720C.
No blockage inside the tube.
TGHT stabilizes at 305A/4.79V. Vac at 1.09e-7 Torr.
Thursday, September 01, 2016, 16:32
About an hour ago, the temp dropped to 1660C with no change in TGHT current/voltage (see attachment 9).
Vac is a 1.06e-7 Torr.
After consulting with Friedhelm, we decided to cool the target down and inspect it tomorrow.
Ramping TGHT/TBHT at 2A/min.
Wednesday, September 07, 2016, 15:13
The target was removed from the Evap and inspected.
Some spots on both ends and ionizer tube were crystalized. (see attachment 10).
No blockage inside the tube was observed.
End caps were inserted.
The target was assembled and tested - All seems fine.
|
Attachment 1: Screen_Shot_2016-08-29_at_2.35.23_PM.png
|
|
Attachment 2: SiC34_striptool.PNG
|
|
Attachment 3: Screen_Shot_2016-08-30_at_12.13.12_PM.png
|
|
Attachment 4: Screen_Shot_2016-08-30_at_4.41.00_PM.png
|
|
Attachment 5: Screen_Shot_2016-08-31_at_11.51.58_AM.png
|
|
Attachment 6: Screen_Shot_2016-08-31_at_11.52.49_AM.png
|
|
Attachment 7: Capture.PNG
|
|
Attachment 8: Aug31_11pm.PNG
|
|
Attachment 9: before_cooling.PNG
|
|
Attachment 10: Screen_Shot_2016-09-02_at_12.04.35_PM.png
|
|
|
316
|
Tuesday, August 23, 2016, 12:15 |
John Wong | Empty | 39814-V2-1 | LP-IG-LIS | Done | sintering TaC coating on SiC#34 container...round2 |
Laura Lambert wrote: |
Wednesday, August 17, 2016, 17:30
Container coated with TaC using 'flushing technique', cleaned ionizer tube with acetone, so no coating inside ionizer tube
Wrapped with 3 x Ta heat shields, incl center block
Currently pumping down in evap2
Thursday, August 18, 2016, 10:14
HS water valves opened...leak detected see attachment for photo from archives
Vented and opened up.
Anders performed leak check, nothing found.
Replaced all seals with blue seals.
Pumping down now
Thursday, August 18, 2016, 16:12
HS water valves opened...leak detected again see attachment for photo of striptool
Vented and opened up.
working with Anders on finding leak...
Monday, August 22, 2016, 10:38
leaks FIXED!
HS water valves opened, NO leaks detected!
Tapped up manually to 70A
Vacuum stable, IGP1 = 2.5e-6 Torr
Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 350A
Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A
Once max setpoints achieved, will tap up manually to final desired temperature of 1900C
Monday, August 22, 2016, 14:58
TGHT = 115A, 1.3V
TBHT = 89A, 0.97V
IGP1 = 4.1e-7 Torr.
Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.
Monday, August 22, 2016, 16:01
IGP1 = 1.25e-6 torr
TGHT = 174A, 2.2V
TBHT = 118A, 1.4V
Lowering ramping rate to 0.2A/min and 0.1A/min for the TGHT and TBHT respectively for overnight ramping.
|
Tuesday, August 23, 2016, 12:14
Initiate TGHT autoramping to 400A at 2A/min. Vac 3.5e-7 Torr.
Tuesday, August 23, 2016, 14:48
TGHt tapped up to 420A/7.01V. Local temp read at ~1900C. Will sinter at this temp for a few hours before cooling down.
Tuesday, August 23, 2016, 17:20
TGHT at been at 420A/7.01V for over 4 hours. Vac at 4.8e-7 Torr.
Cooling TGHT and TBHT at 1A/min.
Wednesday, August 24, 2016, 10:35
TGHT/TBHT at 0A.
Venting chamber.
Container looks good.
|
|
315
|
Thursday, August 18, 2016, 10:37 |
Anders Mjos | | | | Maintenance | New cooling lines for Heat Shield | Dan made a set of new cooling lines for the Source Tray Heat Shield cooling yesterday. No joints on the lines. Use same VCR fitting 3/8 -> 1/4" as for the Heat Shield. The old lines had worn threads on the male VCR nut. |
|
314
|
Wednesday, August 17, 2016, 17:31 |
Laura Lambert | Empty | 39814-V2-1 | LP-IG-LIS | In progress | sintering TaC coating on SiC#34 container...round2 | Wednesday, August 17, 2016, 17:30
Container coated with TaC using 'flushing technique', cleaned ionizer tube with acetone, so no coating inside ionizer tube
Wrapped with 3 x Ta heat shields, incl center block
Currently pumping down in evap2
Thursday, August 18, 2016, 10:14
HS water valves opened...leak detected see attachment for photo from archives
Vented and opened up.
Anders performed leak check, nothing found.
Replaced all seals with blue seals.
Pumping down now
Thursday, August 18, 2016, 16:12
HS water valves opened...leak detected again see attachment for photo of striptool
Vented and opened up.
working with Anders on finding leak...
Monday, August 22, 2016, 10:38
leaks FIXED!
HS water valves opened, NO leaks detected!
Tapped up manually to 70A
Vacuum stable, IGP1 = 2.5e-6 Torr
Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 350A
Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A
Once max setpoints achieved, will tap up manually to final desired temperature of 1900C
Monday, August 22, 2016, 14:58
TGHT = 115A, 1.3V
TBHT = 89A, 0.97V
IGP1 = 4.1e-7 Torr.
Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.
Monday, August 22, 2016, 16:01
IGP1 = 1.25e-6 torr
TGHT = 174A, 2.2V
TBHT = 118A, 1.4V
Lowering ramping rate to 0.2A/min and 0.1A/min for the TGHT and TBHT respectively for overnight ramping.
|
Attachment 1: leak.JPG
|
|
Attachment 2: water_leak.JPEG
|
|
|
313
|
Friday, August 12, 2016, 11:08 |
Laura Lambert | | | | Maintenance | NEW PUMP FOR GLOVE BOX | Wednesday, August 03, 2016, 16:16
Tues July 26th had some problems with the transfer chamber
Transfer chamber was not going below -20in pressure, when usually it will drop all the way to -30in
To by pass and put the uranium target into the glove box, the transfer chamber was flushed 10x - when opened, no change in H2O and O2 in glove box; therefore, 'bypass' worked.
Pump removed and tested by vacuum group - showed no reading on gauge when being tested, how was it even pumping?
New pump installed July 27th.
New pump = bigger/ faster/ quieter
|
|
312
|
Monday, August 08, 2016, 15:22 |
Laura Lambert | SiC | 40860-3 | LP-IG-LIS | Problems | Conditioning SiC#34 | Monday, August 08, 2016, 15:19
Previously sintered over weekend [see elog i.d 311]
Target container contains 471 discs of SiC [6 x 5 packs + 441 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 52.7172g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Conditioning temp = 1800C.
TGHT max = 450A. TBHT max = 230A.
Chamber is currently being pumped down.
Monday, August 08, 2016, 16:38
Target was not removed from evap2 after sintering, vented and cleaned windows only.
IGP1 = 5.5e-6 Torr
Stepped up manually to 80A, vacuum stable.
IGP1 = 3.2e-6 Torr
Initiating auto-ramp at 0.2A/min for the TGHT and 0.1A/min for the TBHT.
Thursday, August 11, 2016, 14:14
Tues the TGHT reached ~280A via auto-ramp
Evap2 was then tapped up manually to 480A/ ~1800C
Temperature readings on OMEGA have fluctuated up and down during conditioning process which was also observed for SiC#33
Also consistent with SiC#33, a lower current was required to reach 1800C during the conditioning process compared to the sintering process.
See attached link for data.
Tuesday, August 16, 2016, 16:25
TGHT remained at 480A, 9.2V for ~7 days.
IGP1 = 6.5e-6 Torr
OMEGA = 1470C [with window coating, so temperature reading compromised]
Initiating auto cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
Wednesday, August 17, 2016, 13:40
Vented in air and opened this morning.
Target broke
Target clearly heated to high.
See attached snapshot of striptool from conditioning process.
Will update later with photos of broken container
|
Attachment 1: conditioning_temperature_graph.xlsx
|
Attachment 2: striptool_conditioning_target_BROKEN.JPG
|
|
|
311
|
Tuesday, August 02, 2016, 13:56 |
Laura Lambert | SiC | 40860-3 | LP-IG-LIS | Done | Sintering SiC#34 | Tuesday, August 02, 2016, 13:41
Target container contains 471 discs of SiC [6 x 5 packs + 441 single discs]
Target packed length = 16cm.
Mass of SiC(green) = 52.7172g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Sintering temp = 1800C
TGHT max = 350A. TBHT max at 230A.
Chamber is currently being pumped down.
Slope on OMEGA = 1.04
Tuesday, August 02, 2016, 16:00
Tapped up manually to 30A - vacuum to high, lowered down to 20A to be able to initiate auto-ramp.
IGP1 = 2.3e-5 Torr
Initiating auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively.
Friday, August 05, 2016, 11:57
Evap2 has reached TGHT = 350A, 5.33V
TBHT = 187A, 2.31V and still climbing...
OMEGA = 1365C
IGP1 = 7.88e-7 Torr
Increased max setpoint for TGHT to 400A.
Friday, August 05, 2016, 13:33
TGHT = 380A, 5.97V
TBHT = 197A, 2.45V
OMEGA = 1396C
IGP1 = 8.75e-7 Torr
Increasing ramping rate to 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
New final setpoint for the TGHT = 450A
Friday, August 05, 2016, 14:17
TBHT = 230A, 2.97V
TGHT = 450A, 7.4V
OMEGA = 1572C
IGP1 = 3.2e-6 Torr
Increasing max setpoint for TGHT to 500A and re-initiating auto-ramp.
Friday, August 05, 2016, 15:18
At TGHT = 480A, OMEGA temperature dropped to 1400C due to coating on window.
Last reading was ~1600C
Tapped up manually to TGHT = 500A, 8.61V
Window fully coated therefore OMEGA reading is negligible at this point
Attempted to take temperature reading with other OMEGA from behind evaporator or using handheld manual temperature reader - all windows have a coating, therefore unsuccessful.
IGP1 = 1.75e-6 Torr
Reduced max voltage set for TGHT to 9.0V to minimize possibly voltage 'creep'
Will remain at these setpoints over wknd and ramp down monday morning.
Monday, August 08, 2016, 08:45
TGHT = 500A on the 'current set' and 466A on the readout, 8.74V
TBHT = 230A, 2.99V
IGP1 = 6.6e-8 Torr
OMEGA = 1460C [reading through coating on window port]
Evap2 has been at these setpoints for the wknd.
Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
Monday, August 08, 2016, 10:38
Quick observational note:
while ramping down OMEGA readings have slowly increased.
At ~350A OMEGA = ~1500C
At ~300A, OMEGA = ~1750C
Currently at 280A, OMEGA = ~2800C
Coating on window has affected the OMEGA readings in a weird way...
Monday, August 08, 2016, 15:17
Vented in air and opened up this afternoon.
Cleaned windows but left target loaded in evap2 for conditioning process.
|
Attachment 1: sintering-_coating_on_window1.jpg
|
|
Attachment 2: sintering-_coating_on_window2.jpg
|
|
Attachment 3: sintering-_coating_on_window3.jpeg
|
|
|
310
|
Tuesday, July 26, 2016, 16:53 |
Laura Lambert | Ta | 41369-6 | HP-SIS | Done | Conditioning Ta#49 | Tuesday, July 26, 2016, 16:50
loaded into evap2
pumped down, HS water valves opened, no leaks detected.
tapped up manually to 35A
vacuum stable = 3.8e-6 Torr
Initiating auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively.
Final setpoints at 230A for the TBHT and 600A for the TGHT.
Final desired temperature = 1800C
Wednesday, July 27, 2016, 09:20
IGP1 = 6.3e-7 Torr, vacuum stable.
TGHT = 232A, 2.7V
TBHT = 131A, 1.76V
Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.
Wednesday, July 27, 2016, 15:46
TGHT = 600A, 8.87V
TBHT = 230A, 3.7V
IGP1 = 1.37e-6 Torr
OMEGA = 1640C
Increased max TGHT voltage to 12V
Tapped up manually to OMEGA = 1810C
TGHT = 675A, 10.21V
IGP1 = 2.2e-6 Torr
Will remain at max setpoints for the rest of the week and cool down over weekend.
Thursday, July 28, 2016, 08:34
TGHT = 675A, 10.41V
OMEGA = 1833C
Tapped down to 660A, 10.09V
OMEGA = 1805C
Friday, July 29, 2016, 13:57
OMEGA = 1814C
TGHT = 660A, 10.16V
TBHT = 230A, 3.72V
IGP1 = 3.43e-7 Torr
evap2 has remained at max setpoints for ~42hrs
conditioning complete.
Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
Tuesday, August 02, 2016, 13:39
vented in air and removed from evap2 this morning.
target looks good!
|
|
309
|
Friday, July 15, 2016, 11:52 |
Laura Lambert | Empty | 40860-3 | LP-IG-LIS | Done | sintering TaC coating on SiC#34 container | Friday, July 15, 2016, 11:49
Container previously coated with TaC using 'flushing technique', cleaned ionizer tube with acetone, so no coating inside ionizer tube
Wrapped with 3 x Ta heat shields, incl center block - new method of each layer being one long single Ta foil covering entire container incl center block
Currently pumping down in evap2
Friday, July 15, 2016, 14:35
Turbo pump broken
Currently being replaced...
Friday, July 15, 2016, 17:04
Turns out its not the turbo pump...TP controls and pump replaced, problem still happening.
Took out heat shield and used a closed loop to rule out leak in chamber, emptied all water lines - turbo pump now on.
Took v.long time to pump down. TP will remain on over wknd.
BP turns on, PV1 turns on, RV turns on - then takes very long time for vacuum to drop ~45min? before BV and TP can be turned on.
Possibly problem with threads on heat shield and not creating proper seal?
Will continue monday with evap2 mystery problem solving...
Monday, July 18, 2016, 16:14
Replaced heat shield and copper seals.
Container re-loaded.
Turbo pump on and good vacuum achieved! YAY!
Finished pumping down, opened HS water valves - no leaks detected.
Tapped up manually to 35A
Vacuum stable, IGP1 = 3e-6 Torr
Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 400A
Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A
Once max setpoints achieved, will tap up manually to final desired temperature of 1900C
Tuesday, July 19, 2016, 09:21
TGHT = 242A, 2.76V
TBHT = 162A
IGP1 = 5.05e-6 Torr
Increasing ramping rate to 1.0A/min and 0.5A/min for the TGHT and TBHT respectively.
Tuesday, July 19, 2016, 13:04
TGHT = 400A, 4.4V
TBHT = 230A, 2.6V
OMEGA = 1120C
Reached max setpoints ~1hr ago.
Tapping up manually to 1900C...
Tuesday, July 19, 2016, 16:32
MORE problems with evap2
TGHT reads 460A, 5.1V, 1170C - a lot of power is being lost somewhere...
Comparison from elog i.d. 291 [the last IGLIS container sintering of TaC coating] the TGHT read 460A, 7.5V, 1900C
Another problem: the read out on the power supply and read out on epics of the TBHT reads 215A; however, the 'current set' says 177A - two very different numbers?!
Ramping down evap2 at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively to further inspect chamber and hopefully solve this...
Wednesday, July 20, 2016, 13:34
Chamber was vented in air and opened up for inspecting.
Fixed!
One of the steel plates used to stop reflection onto the door of the chamber was inserted improperly, resting on top of the 2 negative copper lines to the target leg, this was causing a short.
There was also a short from the right target leg touching the copper heat shield, the heat shield has been shaved down and corrected. It is no longer touching.
There were also 2 brackets that had fallen behind evap2 inside the cage, one was touching the positive lines - it wasn't quite touching the ground, but may have grounded it, causing another possible short.
The chamber was pumped back down and the HS water valves re-opened. No leaks detected.
Evap2 was tapped up manually to 35A.
Vacuum stable = 1.0e-6 Torr.
Initiating auto-ramp at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
Final setpoints are TGHT = 400A and TBHT = 230A
Wednesday, July 20, 2016, 16:25
TGHT = 315A, 4.5V
TBHT = 174A, 2.1V
IGP1 = 2e-6 Torr
OMEGA = 1518C
Lowering auto-ramp to 0.2A/min and 0.1A/min for the TGHT and TBHT overnight while unable to keep watch on the vacuum.
Thursday, July 21, 2016, 09:09
Evap 2 reached max setpoints ~7.5hrs ago.
TGHT = 400A, 6.3V
TBHT = 230A, 2.9V
IGP1 = 5.1e-7 Torr.
OMEGA = 1882C
Tapping up manually to 1900C...
Friday, July 22, 2016, 16:18
Container has remained at ~1900C for ~31hrs
TGHT reached 405A/1900C - then after ~23hrs dropped in temperature down to 1895C so was tapped up further to 410A/1910C for another ~8hrs.
TGHT = 410A, 6.57V
IGP1 = 3.1e-7 Torr
TBHT = 230A, 2.9V
Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
Will remove from evap2 after the weekend.
Tuesday, July 26, 2016, 16:49
vented in air.
container looks good, fully sintered.
will update with photos tomorrow...
|
Attachment 1: Evernote_Camera_Roll_20160524_134232.jpg
|
|
Attachment 2: Evernote_Camera_Roll_20160524_134233.jpg
|
|
Attachment 3: Evernote_Camera_Roll_20160524_1342331.jpg
|
|
Attachment 4: Evernote_Camera_Roll_20160524_1342332.jpg
|
|
Attachment 5: snapshot_of_striptool_sintering_TaC_coating.JPG
|
|
|
308
|
Monday, June 27, 2016, 11:08 |
Laura Lambert | Empty | 41790-3 | LP-SIS | Done | sintering TaC coating on UCx#17 container | Monday, June 27, 2016, 11:07
Container coated with TaC using 'flushing technique'.
Wrapped with 3 x Ta heat shields, incl center block - new method of each layer being one long single Ta foil covering entire container incl center block
Currently pumping down in evap2
Monday, June 27, 2016, 13:23
HS water valves opened
Tapped up manually to 35A
Waited ~1hr, vacuum stable
IGP1 = 1.8e-6 Torr
Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 400A
Initiating auto ramp for TBHT @ 0.1A/min to a max setpoint of 230A
Once max setpoints achieved, will tap up manually to final desired temperature of 1900C
Wednesday, June 29, 2016, 11:33
IGP1 = 1.9e-7
TGHT = 400A, 6.0V
TBHT = 223A, 3.9V
OMEGA = 1885C
Remained at these settings for ~13hrs
Increased TBHT max voltage to 4.3V to achieve 230A
TBHT = 230A, 4.1V
OMEGA = 1890C
Tapped up to TGHT = 405A, 6.17V to achieve 1900C...OMEGA reached 1915C
Lowered TGHT to = 403A, 6.12V
OMEGA = 1905C
Measured ~1870C with the mikron, same window the OMEGA measurements are taken out of.
IGP1 = 2.1e-7
Thursday, June 30, 2016, 08:44
TGHT = 403A, 6.07V
OMEGA = 1886C
Tapped back up to 1900C
TGHT = 410A, 6.22V
OMEGA = 1911C
Thursday, June 30, 2016, 16:01
OMEGA = 1911C
Container has remained at ~1900C for ~1.5 days
Initiating auto-cool at 2.0A/min and 1.0A/min for the TGHT and TBHT respectively.
Monday, July 04, 2016, 09:59
Vented in air and opened up this morning.
Container looks good.
Confirmed coating fully sintered with J.Wong.
Photos attached.
|
Attachment 1: LP-SIS_post_sintering_TaC(3).jpg
|
|
Attachment 2: LP-SIS_post_sintering_TaC(4).jpg
|
|
|
307
|
Thursday, June 16, 2016, 11:01 |
Laura Lambert | SiC | 41369-4 | HP-SIS | Done | Conditioning SiC#33 - 1st beta SiC target! | Thursday, June 16, 2016, 10:59
Previously sintered over weekend [see elog i.d 306]
Target container contains 450 discs of SiC [4 x 5 packs + 430 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 53.8758g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Conditioning temp = 1800C.
TGHT max = 710A according to sintering data. TBHT max = 230A.
Chamber is currently being pumped down.
Thursday, June 16, 2016, 15:43
Target was not removed from evap2 after sintering, vented and cleaned windows only.
HS water valves already open.
Stepped up manually to 70A, vacuum stable.
Initiated auto-ramp at 1.0A/min for the TGHT and 0.5A/min for the TBHT with max setpoints of 600A and 230A respectively.
TGHT = 118A, 0.9V
TBHT = 90A, 1.1V
IGP1 = 7.3e-7 Torr
Friday, June 17, 2016, 12:14
TGHT has been tapped up manually to reach max desired temperature of 1800C
TGHT = 690A, 10.85V
TBHT = 230A, 3.88V
IGP1 = 4.9e-7 Torr
This is a lower current than the current required to reach 1800C during the sintering process.
For sintering, the max current was determined via extrapolation of trendline from raw data due to interference of coating on window and unable to take reliable readings from OMEGA.
For this conditioning process ~1800C is reached on the OMEGA since the window is still ~un-coated.
Will remain at 690A, ~1800C for several days to maximize conditioning process.
See attachment for raw data.
Monday, June 20, 2016, 09:01
At the end of the day on friday 17th, OMEGA read ~1750C - no change in the current or voltage, vacuum was stable, this was the max setpoints used to reach 1800C.
This morning OMEGA = 2040C
TGHT = 690A, 10.95V
vacuum stable at IGP1 = 1.8e-7 Torr.
Slightly more noticeable coating on window port, looks like a thin ink layer, still relatively thin coating [ see attached image]
Also attached is archive from over wknd to show vacuum stable, current unchanged and voltage negligibly changed [only gone up by ~0.1V]
Friday, June 24, 2016, 13:52
Container has remained at max setpoints for 7 days.
Initiating auto-cool for TGHT @ 2.0A/min and for TBHT @ 1.0A/min.
Will vent chamber and remove from evap2 to pass off for assembly monday morning.
See attachment for updated excel on temperature readings for the conditioning process.
Monday, June 27, 2016, 08:28
vented in air and removed this morning.
target looks good!
all discs remained nicely alligned.
discs expanded outwards ~1cm, pushed back in to keep target length at 16cm
no visible yellow crystals like previous SiC targets
endcaps inserted and expanded.
Rh foil inserted.
Ta heat shield foils removed, fins look good.
see photos attached for pictures of target - post conditioning.
coating on window very hard to remove. looked like a light sharpy pen coating on window. ended up scratching off with acetone and screw driver. couldn't remove all of it... |
Attachment 1: current_vs_voltage_vs_temp.xlsx
|
Attachment 2: Tapping_up_from_600A_to_1800C_for_conditioning.JPG
|
|
Attachment 3: Conditioning_window_port_at_2040C_mon_20th.jpg
|
|
Attachment 4: archive_of_conditioning_over_wknd.JPG
|
|
Attachment 5: current_vs_voltage_vs_temp.xlsx
|
Attachment 6: Evernote_Camera_Roll_20160627_10.jpg
|
|
Attachment 7: Evernote_Camera_Roll_20160627_102.jpg
|
|
Attachment 8: Evernote_Camera_Roll_20160627_1023.jpg
|
|
Attachment 9: Evernote_Camera_Roll_20160627_10233.jpg
|
|
|
306
|
Thursday, June 16, 2016, 10:58 |
Laura Lambert | SiC | 41369-4 | HP-SIS | Done | Sintering SiC#33 - 1st beta-SiC target! |
John Wong wrote: |
Laura Lambert wrote: |
John Wong wrote: |
Laura Lambert wrote: |
Thursday, June 09, 2016, 15:39
First target using beta-SiC material!
Target container contains 450 discs of SiC [4 x 5 packs + 430 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 53.8758g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Sintering temp = 1800C, TGHT will be set accordingly. TBHT max at 230A.
Chamber is currently being pumped down.
Friday, June 10, 2016, 13:24
HS water valves opened, no leaks detected.
Tapping up manually to 70A...
Auto ramp will be set for TGHT = 0.2A/min to a final setpoint of 520A
Auto-ramp for TBHT = 0.1A/min to a final setpoint of 230A.
|
Friday, June 10, 2016, 16:27
TGHT stepped up to 70A/0.55V. TGHT at 50A/0.62V.
Pressure stabilized at 5.5e-5 Torr.
Initiated auto ramping. TGHT at 0.2A/min --> 520A. TBHT at 0.1A/min --> 230A.
|
Monday, June 13, 2016, 09:51
TGHT = 425A, 5.65V
TBHT = 225A, 3.7V
IGP1 = 8.7e-6 Torr.
Increasing ramping rate to 1.0A/min...
Monday, June 13, 2016, 15:56
Tapped up manually from 520A to 1800C
Extrapolated data on graph to determine correct current required to reach desired max temperature.
Will remain at 1800C for ~48hrs
See attachements for excel sheet and screenshot of striptool.
|
Wednesday, June 15, 2016, 17:54
TGHT at 710A, 11.35V. TBHT at 230A/3.86V.
Omega reading droppd to 1130C due to coating on windows.
Ionizer tube was measured (center) at around 1900C
Cooling down at 2A/min for TGHT, 1A/min for TBHT.
Samples will be collected prior to cleaning the windows.
NEXT: Conditioning.
|
Thursday, June 16, 2016, 09:29
vented in air and opened up this morning.
took some samples to be tested.
|
|
305
|
Wednesday, June 15, 2016, 17:58 |
John Wong | SiC | 41369-4 | HP-SIS | In progress | Sintering SiC#33 - 1st beta-SiC target! |
Laura Lambert wrote: |
John Wong wrote: |
Laura Lambert wrote: |
Thursday, June 09, 2016, 15:39
First target using beta-SiC material!
Target container contains 450 discs of SiC [4 x 5 packs + 430 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 53.8758g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Sintering temp = 1800C, TGHT will be set accordingly. TBHT max at 230A.
Chamber is currently being pumped down.
Friday, June 10, 2016, 13:24
HS water valves opened, no leaks detected.
Tapping up manually to 70A...
Auto ramp will be set for TGHT = 0.2A/min to a final setpoint of 520A
Auto-ramp for TBHT = 0.1A/min to a final setpoint of 230A.
|
Friday, June 10, 2016, 16:27
TGHT stepped up to 70A/0.55V. TGHT at 50A/0.62V.
Pressure stabilized at 5.5e-5 Torr.
Initiated auto ramping. TGHT at 0.2A/min --> 520A. TBHT at 0.1A/min --> 230A.
|
Monday, June 13, 2016, 09:51
TGHT = 425A, 5.65V
TBHT = 225A, 3.7V
IGP1 = 8.7e-6 Torr.
Increasing ramping rate to 1.0A/min...
Monday, June 13, 2016, 15:56
Tapped up manually from 520A to 1800C
Extrapolated data on graph to determine correct current required to reach desired max temperature.
Will remain at 1800C for ~48hrs
See attachements for excel sheet and screenshot of striptool.
|
Wednesday, June 15, 2016, 17:54
TGHT at 710A, 11.35V. TBHT at 230A/3.86V.
Omega reading droppd to 1130C due to coating on windows.
Ionizer tube was measured (center) at around 1900C
Cooling down at 2A/min for TGHT, 1A/min for TBHT.
Samples will be collected prior to cleaning the windows.
NEXT: Conditioning.
|
|
304
|
Monday, June 13, 2016, 09:53 |
Laura Lambert | SiC | 41369-4 | HP-SIS | In progress | Sintering SiC#33 - 1st beta-SiC target! |
John Wong wrote: |
Laura Lambert wrote: |
Thursday, June 09, 2016, 15:39
First target using beta-SiC material!
Target container contains 450 discs of SiC [4 x 5 packs + 430 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 53.8758g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Sintering temp = 1800C, TGHT will be set accordingly. TBHT max at 230A.
Chamber is currently being pumped down.
Friday, June 10, 2016, 13:24
HS water valves opened, no leaks detected.
Tapping up manually to 70A...
Auto ramp will be set for TGHT = 0.2A/min to a final setpoint of 520A
Auto-ramp for TBHT = 0.1A/min to a final setpoint of 230A.
|
Friday, June 10, 2016, 16:27
TGHT stepped up to 70A/0.55V. TGHT at 50A/0.62V.
Pressure stabilized at 5.5e-5 Torr.
Initiated auto ramping. TGHT at 0.2A/min --> 520A. TBHT at 0.1A/min --> 230A.
|
Monday, June 13, 2016, 09:51
TGHT = 425A, 5.65V
TBHT = 225A, 3.7V
IGP1 = 8.7e-6 Torr.
Increasing ramping rate to 1.0A/min...
Monday, June 13, 2016, 15:56
Tapped up manually from 520A to 1800C
Extrapolated data on graph to determine correct current required to reach desired max temperature.
Will remain at 1800C for ~48hrs
See attachements for excel sheet and screenshot of striptool.
|
Attachment 1: current_vs_voltage_vs_temp.xlsx
|
Attachment 2: Tapping_up_from_520A_to_1800C.JPG
|
|
|
303
|
Friday, June 10, 2016, 16:30 |
John Wong | SiC | 41369-4 | HP-SIS | In progress | Sintering SiC#33 - 1st beta-SiC target! |
Laura Lambert wrote: |
Thursday, June 09, 2016, 15:39
First target using beta-SiC material!
Target container contains 450 discs of SiC [4 x 5 packs + 430 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 53.8758g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Sintering temp = 1800C, TGHT will be set accordingly. TBHT max at 230A.
Chamber is currently being pumped down.
Friday, June 10, 2016, 13:24
HS water valves opened, no leaks detected.
Tapping up manually to 70A...
Auto ramp will be set for TGHT = 0.2A/min to a final setpoint of 520A
Auto-ramp for TBHT = 0.1A/min to a final setpoint of 230A.
|
Friday, June 10, 2016, 16:27
TGHT stepped up to 70A/0.55V. TGHT at 50A/0.62V.
Pressure stabilized at 5.5e-5 Torr.
Initiated auto ramping. TGHT at 0.2A/min --> 520A. TBHT at 0.1A/min --> 230A.
|
|
302
|
Thursday, June 09, 2016, 15:48 |
Laura Lambert | SiC | 41369-4 | HP-SIS | In progress | Sintering SiC#33 - 1st beta-SiC target! | Thursday, June 09, 2016, 15:39
First target using beta-SiC material!
Target container contains 450 discs of SiC [4 x 5 packs + 430 single discs]
Target packed length = 16cm.
Mass of 533 discs SiC(green) = 53.8758g
Container is wrapped with 3 heatshields; no end caps are inserted yet - coated spring inserted both sides to hold discs in place.
Sintering temp = 1800C, TGHT will be set accordingly. TBHT max at 230A.
Chamber is currently being pumped down.
Friday, June 10, 2016, 13:24
HS water valves opened, no leaks detected.
Tapping up manually to 70A...
Auto ramp will be set for TGHT = 0.2A/min to a final setpoint of 520A
Auto-ramp for TBHT = 0.1A/min to a final setpoint of 230A.
|
Attachment 1: target_with_end-coils.jpg
|
|
|
301
|
Tuesday, May 31, 2016, 11:10 |
John Wong | Empty | 41369-4 | HP-SIS | Done | sintering TaC coating on SiC#33 container |
Laura Lambert wrote: |
Wednesday, May 25, 2016, 11:37
Container coated with TaC using 'flushing technique' [cleaned ionizer tube with acetone, so no coating inside ionizer tube]
Wrapped with 2 x Ta heat shields - one full height of Ta foil wrapped around cooling fins twice
Currently pumping down in evap2
Thursday, May 26, 2016, 09:28
Tapped up manually to 40A
IGP1 = 6.6e-7 Torr
Initiating auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively.
Final setpoints for TGHT = 650A and TBHT = 230A
Once max setpoints reached will continue to tap up manually while monitoring temperature to 1900C
|
Tuesday, May 31, 2016, 11:09
TGHT at 615A/9.08V, temp = 1610C. Vacuum at 1.8e-7 Torr.
Tapping up TGHT to reach 1900C
Tuesday, May 31, 2016, 12:04
TGHT at 765A/11.90V. Temp at 1900C. Pressure is coming down from 8.7e-7Torr.
Will keep at this temperature for a day.
Wednesday, June 01, 2016, 15:22
Temperature has been stable at 1900C. Pressure is coming down from 3.4e-7 Torr.
Cooling down TGHT and TBHT at 2A/min and 1A/min, respectively.
Friday, June 03, 2016, 12:10
TGHT/TBHT at 0A. Target can be remained under vacuum until Monday.
Monday, June 06, 2016, 16:54
Target container was inspected; it looks good
|
|
300
|
Wednesday, May 25, 2016, 11:40 |
Laura Lambert | Empty | 41369-4 | HP-SIS | In progress | sintering TaC coating on SiC#33 container | Wednesday, May 25, 2016, 11:37
Container coated with TaC using 'flushing technique' [cleaned ionizer tube with acetone, so no coating inside ionizer tube]
Wrapped with 2 x Ta heat shields - one full height of Ta foil wrapped around cooling fins twice
Currently pumping down in evap2
Thursday, May 26, 2016, 09:28
Tapped up manually to 40A
IGP1 = 6.6e-7 Torr
Initiating auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively.
Final setpoints for TGHT = 650A and TBHT = 230A
Once max setpoints reached will continue to tap up manually while monitoring temperature to 1900C
|
|