Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Evaporator_2, Page 17 of 35  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Target Materialdown Target Oven W.O# Source Status Subject
  684   Wednesday, March 12, 2025, 07:10 Darwin Ortiz RosalesEndcaps TARGET BOATDoneTaC coating sintering

Tuesday, March 11, 2025, 15:44

The coated container was wrapped in 3 Ta foil heatshields.

16 caps and 4 springs

Target temperature on OMEGA= 1750-1800C

OMEGA slope:= 0.990

Target time at max temperature = 4 hours

Final Current TBHT= N/A

Final TGHT current= ~400A (adjustable)


Wednesday, March 12, 2025, 07:07

Heating autoramp started at 1A/min on  TGHT 90A

Then at 4A/min  to 400 A.

Good vacuum = 5.0 e-04 Torr

Bad vacuum = 5.0E-02 Torr

 IGP1 initial =4.8e-07 Torr


Wednesday, March 12, 2025, 09:52

starting ramp at 2A/min to 400A 


Wednesday, March 12, 2025, 10:21

increasing ramp to 4A/min (2A/30s)


Wednesday, March 12, 2025, 11:57

TGHT=441A, 7.2V

Will keep for 4 hours

1750C


Wednesday, March 12, 2025, 15:57

starting rampdown at -2A/min

  4   Tuesday, February 28, 2012, 11:00 John WongEmptyTest oven LP-SISDoneMeasuring temperatures, currents & voltages

 Tuesday, February 28, 2012, 10:36

Two thermocouples were inserted through the left side of the copper heat shield, see attachment #1.  One thermocouple is attached to the target tube with a Ta-wire, and the other is attached to the back block.

Data gathering: 

1.  Target heater (IEVAP2:TGHT) setpoint current/voltage  

2.  Target heater (IEVAP2:TGHT) readback current/voltage

4.  Tube heater (IEVAP2:TBHT) setpoint current/voltage

3.  Thermocouples voltages & controls' readback (IEVAP2:TCM) 


 

 

Attachment 1: Evap_2_thermocouple.jpg
Evap_2_thermocouple.jpg
  15   Tuesday, April 03, 2012, 09:00 John WongEmptyTa-target boat #2  Sintering Ta-target boat with TaC coating

Tuesday, April 03, 2012, 08:54

Yesterday, a new target boat was sprayed with TaC coating and let dried.

The boat was then installed in the Evap#2 chamber and pumped down to 10-6 Torr before the target heater was turned on.  NOTE: Target boat is not wrapped with Ta-heat shield. 

TGHT auto ramping was initiated at 2.0A/min and max setpoint to 700A.  The voltage was set at 3V; therefore, the current only ramped up to 250A over night.

--> Increased the TGHT voltage to 15A, and continue ramping the TGHT to 700A.  Currently vac at low 2.3e-7 Torr. 


 Tuesday, April 03, 2012, 09:12

The vac is at low 10e-7 as the TGHT is ramping up.  Changing ramping rate from 2A/min to 5A/min. 


Tuesday, April 03, 2012, 12:00  

TGHT reached to 700A. Measured temp @ 1280C. 

Tapped up TGHT to:

800A.  Measured temp @ 1400C. 

850A (local 843A/15.60V). Measured temp @ 1450C.  

900A (local 893A/16.88V).  Measured temp @ 1500C


 Tuesday, April 03, 2012, 14:35:

Try autoramping TGHT to 1000A but voltage has gone up close to the max limit (20V).  TGHT could only go up to ~970A (see attachment 1: TGHT_maxcurrent.jpg).  The heater remained at that current for ~1hr but auto cooling was initiated - at 10A/min.


 

Attachment 1: TGHT_maxcurrent.jpg
TGHT_maxcurrent.jpg
  36   Thursday, July 19, 2012, 17:05 John WongEmpty37918-3LP-FEBIADDoneCoating target oven /w TaC & sintering for UCx#5

Thursday, July 19, 2012, 16:58

The target container was coated with TaC. 

It's wrapped with 3 layers of Ta as the heat-shield, including the backblock.

TGHT will be ramped up to 580A at 0.2A/min.

TBHT will be ramped up to 230A at 0.2A/min.

Currently, IGP1 = 1.5e-6 Torr.  BP = 15mTorr


 Friday, July 20, 2012, 13:56

TGHT and TBHT reached to 580A & 230A, respectively, and stayed for ~ 2hrs. 

Measured temperature at the ionizer tube to be 1630C.

Cooling down in process at 2A/min...


 Sunday, July 22, 2012, 20:53

The chamber was vented earlier around 14:00hr.  

The target container looks good! 


 

  45   Wednesday, August 22, 2012, 17:36 John WongEmpty39165-5LP-SISDoneCoating target oven /w TaC & sintering for UCx#5

Wednesday, August 22, 2012, 17:25

Note:  LP-FEBIAD target container ( W.O#37918-3) was coated with TaC and sintered on July 19 for UCx#5 target.  Then, a last minute request from the Sci Dev. to run the UCx#5 in LP-SIS. 

The target container was coated with TaC  (Using IR heat lamp to speed the drying time)

It's wrapped with 3 layers of Ta as the heat-shield, including the backblock.

TGHT will be ramped up to 580A at 0.5A/min.

TBHT will be ramped up to 230A at 0.5A/min.

Chamber is currently being pumped down.


 Wednesday, August 22, 2012, 18:27

Chamber was pumped down to 5.4e-6 Torr; the HS cooling water valve was opened and no leaks were detected.

Stepped up TGHT/TBHT to 20A.

Initiated auto-ramping...


 Friday, August 24, 2012, 00:21

TGHT/TBHT have reached to 580A/230A, respectively, and have remained at the currents for ~10hrs.

Current, IG1 is at 9.3e-7 torr.  The sintering process is done.

Initiating auto-cool down at 2A/min.


 Friday, August 24, 2012, 13:31

TGHT & TBHT power supplies are off.

The chamber is vented.


 

  51   Wednesday, October 10, 2012, 16:37 John WongEmpty39165-4LP-SISDoneCoating target oven /w TaC & sintering for TiC#3

Wednesday, October 10, 2012, 16:35

Target container is coated with TaC.  No Ta-heat shields are used.

TGHT will be ramped up to 580A at 0.2A/min.

TBHT will be ramped up to 230A at 0.2A/min.

Chamber is currently being pumped down


 Wednesday, October 10, 2012, 17:31

Chamber was pumped down to mid 10-6 Torr.  HS water valve was opened and no leak in vacuum was observed.

TGHT and TBHT were stepped up to 30A.  Everything seems fine...

Initiated auto-ramping:  Good vac = 2.0e-5 torr, Bad Vac = 3.0e-5 Torr. 


 Thursday, October 11, 2012, 10:35

TBHT has reached to 230A, 3.52V. 

TGHT has reached to 232A.  Vacuum is stabilizing at 8.0e-7 Torr, BP at 19 mTorr. 

Increased TGHT ramping rate to 2.0A/min. 


 Thursday, October 11, 2012, 14:55

TGHT reached to 580A/9.95V, local 575A/10.03V. 

TGHT at 230A/3.62V

Local target container temperature measured at ~1430C, central block at ~1220C

IGP1 currently at 1.68e-6 Torr. 

Heaters will be remained on for another 2 hours or so before auto-cooling is initiated.


 Thursday, October 11, 2012, 17:49

Target container has been heated for over 4 hrs.

IGP1 @ 1.10e-6 Torr, BP @ 18mTorr

Auto-cooling initiated, rate @ 2A/min.


 Friday, October 12, 2012, 10:02

TBHT/TGHT have reached to zero current. 

P/S off.

Venting chamber..

see attachment#1: striptool archiver


 Tuesday, October 16, 2012, 10:35

Container looks good.  It will be used for TiC#3


 

Attachment 1: striptool_archiver_container_TaC_coating.PNG
striptool_archiver_container_TaC_coating.PNG
  54   Friday, January 11, 2013, 14:00 John WongEmptyTa-Target boat DoneTesting QMS & thermocouples

 Friday, January 11, 2013, 13:52

TEST#1

A new target boat is coated with TaC and will go through the sintering process at 580A (max).  Ramping rate 5A/20min.

For this test, two thermocouples are installed to measure the temperature of the container.  The QMS is also operating to analyze the gases. 

See attachment#1 for the thermocouple setup.  Note:  No Ta heat shield is used to wrap around the target container.  

See attachment#2 for an example of the QMS and temperature measurements.  

More details about the results later...  


Tuesday, January 22, 2013, 12:19  

The test was successfully complete. 

Short summary of the results: 

1.  A significant difference in the temperature dependence on the heater current could be found when ramping up/down (see attachment #3). 

2.  A difference of 200 C at the highest temperature was between the two thermocouples were measured. 

3.  The measured temperatures are lower than previous measurements with a pyrometer on an empty LP target container (see attachment#3).

4.  RGA spectra show most of the higher mass organic molecules are gone after initial heating at low temperature.  

5.  Above 560A, CO2 shows up again and decreases up to about 680A heating current. (see attachment #4).

6.  After running at high temperature for some time, only H2O & CO and their constituents are left.  (see attachment #5).

Data can be found on my dropbox, folder "RFQ-test\Test#1-ver1.0"


Next:  Re-heating the target


Tuesday, February 12, 2013, 17:10 

TEST#2: Re-heating the target again.  See if it fit the curves. Measuring concentrations of 14N, 16O, 18H2O, 28CO, 32 CH3OH, 40Ar, 44C02. 

Ramping rate 1A/min

Wednesday, March 06, 2013, 18:14 

Test#2 complete.  Data can be found on my dropbox, folder "RFQ-test\Test#2-ver1.0"


Wednesday, March 06, 2013, 18:14 

Test#3:  RFQ target container_version 2.0, thermal test.

Measuring back block temperature & analyze gases.  

Data can be found on my dropbox, folder "RFQ-test\Test#3-ver2.0"



 

 

 

 

 

 

 

Attachment 1: evap2_thermocouple_setup.PNG
evap2_thermocouple_setup.PNG
Attachment 2: QMS_temperature_setup.PNG
QMS_temperature_setup.PNG
Attachment 3: 008_all_temp.png
008_all_temp.png
Attachment 4: 018.png
018.png
Attachment 5: 022.png
022.png
  57   Monday, February 18, 2013, 16:43 John WongEmpty LP-SISDoneSintering TaC coating on the RFQ target container

 Monday, February 18, 2013, 16:28

The RFQ target container is coated with TaC and ready to be sintered.  No Ta-heat shields are used.  This container will be used for the SiC#28-LPSIS-RFQ. 

Two thermocouples are welded on the container:  One on the end cap and the other on the back block (see attachment#1)

The target will be heated to at least  TGHT at 580A and TBHT at 300A; the vacuum and gasses will be monitored.  

The chamber is currently being pumped down...  


 Friday, February 22, 2013, 14:24

The gasses were analyzed with the RGA:

TGHT @ 520A, TBHT @ 300A:  Mass 28 (CO) reached to max current of ~5pA before the current started to decrease, (see attachment #2).  This could be the indication of the material(s) in the target container was "sort of" fully reduced. 

TGHT was further ramped up  to 600A and heated for a few hours.  The temperature on the end was measured at 1252C and the center block was at 1580C.  (see attachment #3).

The container was successfully sintered with TaC. 


 

 

Attachment 1: SiC#28_-_LPSIS-RFQ.png
SiC#28_-_LPSIS-RFQ.png
Attachment 2: Sintering_of_TaC.PNG
Sintering_of_TaC.PNG
Attachment 3: autorampingdown_10.PNG
autorampingdown_10.PNG
  59   Monday, March 04, 2013, 17:41 John WongEmptyLP-SIS RFQ ver 2.0  Testing LPSIS RFQ ver 2.0

 Monday, March 04, 2013, 17:39

This is the 2nd modified target container for RFQ LPSIS.  The container will be heated up to 650A TGHT and 150A on TBHT.  No Ta-heat shield is being used.  

Heating rate at 1A/min for both TGHT & TBHT.  Once the target is at the currents, TBHT will be further ramped up to 300A.  

Temperatures are being measured by two thermocouples (one on RFQ component and the other on the Cu heat-shield).  

Gases are being analyzed using the RGA. 


 

  60   Wednesday, March 06, 2013, 10:41 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal test

Wednesday, March 06, 2013

The Cool Transfer Line (CTL) test target is installed for thermal tests. Drawing number is ITD0431 REV A.

Thermocouple channels are as follows:

T1: Cu block on CTL
T2: Heat Shield above CTL
T3: Heat Shield cooling water Supply
T4: Heat Shield cooling water Return

Cooling water is in Evap2 supplied to the cooling line that goes directly to the area on the Heat Shield above the CTL.

Test results attached.
 

Attachment 1: CTL_1st_Assebmly_Thermal_Test_Evap2.pdf
CTL_1st_Assebmly_Thermal_Test_Evap2.pdf
Attachment 2: 2013-03-08_Evap2_First_Thermal_Test.pdf
2013-03-08_Evap2_First_Thermal_Test.pdf
  61   Wednesday, March 06, 2013, 17:53 John WongEmpty38481-4HP-FEBIADDoneCTL thermal test

Anders Mjos wrote:

Wednesday, March 06, 2013

The Cool Transfer Line (CTL) test target is installed for thermal tests. Drawing number is ITD0431 REV A.

Thermocouple channels are as follows:

T1: Cu block on CTL
T2: Heat Shield above CTL
T3: Heat Shield cooling water Supply
T4: Heat Shield cooling water Return

Cooling water is in Evap2 supplied to the cooling line that goes directly to the area on the Heat Shield above the CTL.
 

 Wednesday, March 06, 2013, 17:23

The target has been pumping down to 5.3 e-7 Torr.  On the RGA mass scan, mainly H2O (mass 18 + constituents) was detected at ~2.7pA (see attachment #1).

The target will be heated up: TGHT = 850A (rate @ 1A/min); TBHT = 300A (rate @ 1A/min).


 Thursday, March 07, 2013, 11:51

TGHT and TBHT reached to 850A (local, 845A\13.80V) and 300A, respectively.  The out gassing of CO (mass 28) reached to ~5pA at the max currents.  (see attachment #2) 

 TBHT will be ramped down to 0A to compare the temperatures.  


 Thursday, March 07, 2013, 15:55

TBHT at 0A.  See attachment#3 for the temperatures and RGA data before further ramping down the TGHT.


 

Attachment 1: rampingup_1.PNG
rampingup_1.PNG
Attachment 2: rampingup_2.PNG
rampingup_2.PNG
Attachment 3: autorampingdown_23.PNG
autorampingdown_23.PNG
  62   Monday, March 11, 2013, 12:23 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal test 2

 

Anders Mjos wrote:

Wednesday, March 06, 2013

The Cool Transfer Line (CTL) test target is installed for thermal tests. Drawing number is ITD0431 REV A.

Thermocouple channels are as follows:

T1: Cu block on CTL
T2: Heat Shield above CTL
T3: Heat Shield cooling water Supply
T4: Heat Shield cooling water Return

Cooling water is in Evap2 supplied to the cooling line that goes directly to the area on the Heat Shield above the CTL.
 

 

Monday, March 11, 2013

The CTL test target was installed again for a second thermal test. CTL block fastened to HS with 1 in lbs. A small piece of Ta-foil of 0.001" thickness was used between the CTL Cu-block and the Ta transfer line to reduce the heat transfer..

Thermocouples were re-attached to CTL and Heat Shield (see above for channels #s).

See attached graph (PDF) for details.

Attachment 1: 2013-03-11_Evap2_Second_Thermal_Test.pdf
2013-03-11_Evap2_Second_Thermal_Test.pdf
  63   Monday, March 11, 2013, 15:59 John WongEmpty38481-4HP-FEBIADDoneCTL thermal test 2

Anders Mjos wrote:

Anders Mjos wrote:

Wednesday, March 06, 2013

The Cool Transfer Line (CTL) test target is installed for thermal tests. Drawing number is ITD0431 REV A.

Thermocouple channels are as follows:

T1: Cu block on CTL
T2: Heat Shield above CTL
T3: Heat Shield cooling water Supply
T4: Heat Shield cooling water Return

Cooling water is in Evap2 supplied to the cooling line that goes directly to the area on the Heat Shield above the CTL.
 

Monday, March 11, 2013

The CTL test target was installed again for a second thermal test. CTL block fastened to HS with 1 in lbs. A small piece of Ta-foil of 0.001" thickness was used between the CTL Cu-block and the Ta transfer line to reduce the heat transfer..

Thermocouples were re-attached to CTL and Heat Shield (see above for channels #s).

 Monday, March 11, 2013, 15:55

Chamber was pumped down to 2 e-7 Torr.  HS water valve opened and no leaks were detected.  

TGHT and TBHT are ramping up to 850A and 300A at 2A/min, respectively.  

RGA is running... 


Tuesday, March 12, 2013, 10:44  

TGHT/TBHT reached to max currents. 

See attachment #1 for temperature and RGA measurements. 

Cooling down in process... 5A/min. 


 

Attachment 1: autorampingup_110.PNG
autorampingup_110.PNG
  64   Wednesday, March 13, 2013, 16:08 Anders MjosEmpty38481-4HP-FEBIADDoneThermal test

Wednesday, March 13, 2013 

Thermocouple channels (see attached PDF for photos)
T1 - Left target leg at tube
T2 - Between cooling fins close to tube, left side
T3 - Supply water HS
T4 - Return water HS


Friday, March 22, 2013

Test not conducted. Target removed.

Attachment 1: HP-FEBIAD-A_TC_at_fins.pdf
HP-FEBIAD-A_TC_at_fins.pdf
  65   Thursday, March 14, 2013, 12:27 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal test 3 (w/o CTL block)

Thursday, March 12, 2013 

The CTL was removed and target heated to 580A / 300A

T1: Left target leg close to tube
T2: Heat Shield above CTL
T3: Heat Shield cooling water Supply
T4: Heat Shield cooling water Return


Thursday, March 13, 2013  

The target was cooled down 


Results attached as PDF and Excel

Attachment 1: 2013-03-13_-_FEBIAD-HP-A_TargetLeg_and_HeatShield_TC.pdf
2013-03-13_-_FEBIAD-HP-A_TargetLeg_and_HeatShield_TC.pdf
Attachment 2: 2013-03-13_-_FEBIAD-HP-A_TargetLeg_and_HeatShield_TC.xlsx
  66   Thursday, April 11, 2013, 14:20 John WongEmpty39165-6LP-SISDoneCoating target oven /w TaC & sintering for UCx#6

Monday, April 08, 2013, 17:39

Target container is coated with TaC; the container will be used for the UCx#6 target. 

No Ta-heat shields are used.

For the sintering process:

TGHT will be ramped up to 580A at 0.2A/min

TBHT will be ramped up to 230A at 0.2A/min

Chamber has been pumped down.  HS cooling H2O valve opened; no leaks have detected.


Thursday, April 11, 2013, 14:35 

Target and tube heaters have reached to optimum.

Auto-cooling initiated...


 Friday, April 12, 2013, 11:17

P/S off.  Chamber vented. 

Done!


 

  67   Friday, April 19, 2013, 09:39 Rick MaharajEmpty  Donethermocouple Feedthru

 A thermocouple feedthru was installed via 9 pin sub-D connector. It runs from the the conflat cross on the top of the evaporator to the upper 9 pin connector of the target mounting plate.

  68   Friday, April 19, 2013, 15:27 Anders MjosEmpty38481-4HP-FEBIADDoneCTL test

Target installed with 4 T/C

The target assembly is ITD0300 with the CTL Cu cooling block slightly modified.

Ch1 - CTL cooling block T/C feedtrough
Ch2 - Heat shield below left gripper arm - T/C feedthrough
Ch3 - Heat shield below left gripper arm - 9 pin connector
Ch4 - Target left side leg on tube - 9 pin connector

Friday, April 19, 2013, 15:23: Roughing

Friday, April 19, 2013, 15:41: Started turbo


Monday, April 22, 2013, 09:43: Opened water supply. Vacuum stable at 2.8E-7 T (IGP1)

  69   Monday, April 22, 2013, 18:49 John WongEmpty38481-4HP-FEBIADDoneCTL test

Anders Mjos wrote:

Target installed with 4 T/C

The target assembly is ITD0300 with the CTL Cu cooling block slightly modified.

Ch1 - CTL cooling block T/C feedtrough
Ch2 - Heat shield below left gripper arm - T/C feedthrough
Ch3 - Heat shield below left gripper arm - 9 pin connector
Ch4 - Target left side leg on tube - 9 pin connector

Friday, April 19, 2013, 15:23: Roughing

Friday, April 19, 2013, 15:41: Started turbo


Monday, April 22, 2013, 09:43: Opened water supply. Vacuum stable at 2.8E-7 T (IGP1)

Monday, April 22, 2013, 18:48

Ramping TGHT/TBHT to 850A/300A at 1A/min.


 

  70   Tuesday, April 23, 2013, 10:11 Anders MjosEmpty38481-4HP-FEBIADDoneCTL test

 

John Wong wrote:

 

Anders Mjos wrote:

Target installed with 4 T/C

The target assembly is ITD0300 with the CTL Cu cooling block slightly modified.

Ch1 - CTL cooling block T/C feedtrough
Ch2 - Heat shield below left gripper arm - T/C feedthrough
Ch3 - Heat shield below left gripper arm - 9 pin connector
Ch4 - Target left side leg on tube - 9 pin connector

Friday, April 19, 2013, 15:23: Roughing

Friday, April 19, 2013, 15:41: Started turbo


Monday, April 22, 2013, 09:43: Opened water supply. Vacuum stable at 2.8E-7 T (IGP1)

 

Monday, April 22, 2013, 18:48

Ramping TGHT/TBHT to 850A/300A at 1A/min.


 

 

Tuesd ay, April 23, 2013, 10:07

TBHT / TGHT: 820A / 300A

TGHT:RDCUR: 816.6A
TBHT:RDCRU: 303.5A

Local P/S displays
TGHT: 821A / 11.05V
TBHT: 307A / 4.37V

Tuesday, April 23, 2013, 10:45: Ramping down TBHT to 0A @ 5A/min

Tuesday, April 23, 2013, 12:49: Ramping down TGHT to 0A @ 5A/min

Tuesday, April 23, 2013, 15:52: Swithced off TGHT and TBHT P/S. TGHT P/S showed 30A read back value, while local value was 0A


 Wednesday, April 24, 2013, 09:53: Turbo stopped

Wednesday, April 24, 2013, 12:00: Target removed 


The ionizer tube was found to have deformed as seen in the attached photo.

Attachment 1: 2013-04-23_Evap2_ITD0300_CTL_Thermal_Test.xlsx
Attachment 2: CTL_ITD0300_Evap2.pdf
CTL_ITD0300_Evap2.pdf
Attachment 3: Deformed_Ionizer_Tube.jpg
Deformed_Ionizer_Tube.jpg
ELOG V2.9.2-2455