  Evaporator_2, Page 9 of 35  Not logged in ELOG logo
  ID Date Author Target Material Target Oven W.O# Source Status Subject Text Attachments
  531   Friday, February 26, 2021, 09:28 Ferran Boix PamiesEmptynone DoneParasitic target thermal tests Tests were performed with external
power supply. No target boat or container.
Small power on heating small heating
  
  530   Tuesday, February 23, 2021, 08:59 Marla Cervantes NA (Cu-tube) DoneRe coating Test 2 Tuesday, February 23, 2021, 08:49
Yesterday a heat shield was washed
and when dry it was installed in the EVAP2,
  
  529   Saturday, February 13, 2021, 08:14 Darwin Ortiz RosalesSiC41992-1TARGET BOATDone Sintering of SiC discs for SEM Saturday, February 13, 2021, 08:10
Ta boat loaded with 80 discs
 Screenshot_2021-02-14_114713.png 
  528   Thursday, February 11, 2021, 10:57 Marla Cervantes NA DoneRe coating Test 1Thursday, February 10, 2021, 12:00
Objective: Heat a Re wire to evaporate
it and deposit a layer of Re on the inner
  
  527   Tuesday, February 09, 2021, 06:48 Aaron Schmidt NA DoneTa coating testMonday, February 08, 2021, 17:00: Installed
brackets w/ Ta wire and a small piece of
Re to test voltage drop.
  
  526   Monday, February 01, 2021, 13:57 Darwin Ortiz RosalesSiC40282-4TARGET BOATDoneSintering of SiC discs for SEMMonday, February 01, 2021, 13:52  
  
  525   Tuesday, November 24, 2020, 12:56 Marla Cervantes 44139-8-SK TARGET BOATDoneGraphite casting conditioningTuesday, November 24, 2020, 09:23
A batch of 60 discs of 18 mm diameter
were loaded in a tantalum tube. The tantalum
 2020-11-24-IGP1.JPG2020-11-24IGP1-zoom_out.png2020-11-24-IGP1-stable.JPG2020-11-24-ConditioningProcess.JPG 
  524   Tuesday, November 24, 2020, 08:13 Aaron Schmidt    Flex - line HS installedMonday, November 23, 2020, 17:01: Flex-line
HS installed.

Tuesday, November 24, 2020,
  
  523   Thursday, November 05, 2020, 15:13 Ferran Boix PamiesEmpty41882-2TARGET BOATDonecleaning treatment. 2020-11-05 15:44 empty and naked
boat in for heating up system and clean up.
Turbo on.
  
  522   Wednesday, November 04, 2020, 17:31 Ferran Boix PamiesEmpty41882-2TARGET BOATDoneParasitic target graphite outgassing. 2020-11-04 17:31: target installed
with boat containing graphite container for
outgassing. Roughing pump on.
  
  521   Monday, November 02, 2020, 18:32 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDoneHEA heat treatment2020-11-02 6:32: roughing on
2020-11-02 7:21: Turbo on for a while,
IGP1:1.8e-5T . water leak check ok.
 20201104_102925.jpg20201104_144831.jpg 
  520   Tuesday, October 27, 2020, 10:25 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDoneparasitic target commissioning 2020-10-27 10:24 setup introduced
yesterday. Pumping over night IGP1: 5.7e-7T.
Water leak check ok. Performing heating elements
  
  519   Wednesday, October 21, 2020, 14:39 Aaron SchmidtNb44508-2LP-SISIn progressConditioning Nb#9 Nb#9 LP-SIS target description:
  
  518   Friday, October 16, 2020, 16:31 Luca EgoritiEmpty TARGET BOATIn progressHPOG annealingFriday, October 16, 2020, 11:30
 Target mounted in EVAP2. Pump
down started
  
  517   Thursday, October 15, 2020, 18:51 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDoneheat gun plus parasitic target thermal comissioning. 2020-10-15 18:51 : Setup installed
during the day. Pumped down to IGP1:1.5e-5T
, water leak check ok. Ramping up to 100A. 
  
  516   Tuesday, October 13, 2020, 11:15 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDonefoil heating 2020-10-13 11:13 Target was left
under vacuum over the weekend. IGP1: 1.6e-7T
water on- leak check ok. Ramping up 2A/30s
  
  515   Friday, October 09, 2020, 09:50 Ferran Boix PamiesEmpty44139-7-SKTARGET BOATDoneTests, radiation gun for parasitic target 2020-10-09 9:48 The target was installed
the day before and left pumping over night.
IGP1=4.7e-7Torr. leak check when water on,
  
  514   Wednesday, October 07, 2020, 12:25 Aaron Schmidt   In progressIEVAP2:TP1 Swap out. Wednesday, October 07, 2020
TP1 was not spinning up past 4krpm.
Stalling & tripping out. Examined with
  
  513   Tuesday, October 06, 2020, 14:23 Aaron SchmidtTa44508-1LP-SISIn progressConditioning Ta#61Ta#61 LP-SIS target description:
Total Ta foils = 470 [6x20 packs
  
  512   Monday, September 28, 2020, 11:53 John Wongnp-SiC TARGET BOATIn progressnp-SiC carbonizationMonday, September 28, 2020, 11:49
6 discs of np-SiC were loaded to
the target boat wrapped with 3 layers of
  