Entry  Wednesday, October 20, 2021, 15:01, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Wednesday, October 20, 2021, 15:01: Roughing.
Entry  Thursday, October 14, 2021, 10:13, Aaron Schmidt, , LP-SIS, ITW, TM2, , 44378-22, In progress, Conditioning UC#36 HS UC#36.docx
Tube / TGHT only.
Thursday, October 14, 2021, 10:11: Roughing.
Thursday, October 14, 2021, 12:05: TP1B on. 
Entry  Wednesday, October 06, 2021, 11:56, Aaron Schmidt, , , , , , , , Pump down empty chamber 
Wednesday, October 06, 2021, 11:56: Roughing.

Thursday, October 14, 2021, 09:07: Venting.
Entry  Monday, October 04, 2021, 15:38, Aaron Schmidt, , LP-IG-LIS, ITE, TM4, , 42132-7, In progress, Conditioning UC#35 IG-LIS HS UC#35.docx
Monday, October 04, 2021, 15:38: Roughing.
Monday, October 04, 2021, 16:08: TP1B on. 
Monday, October 04, 2021, 16:15: TP1 A on. 
Entry  Thursday, September 23, 2021, 07:16, Aaron Schmidt, , , , , , , , Pump down empty chamber & reboot 
Thursday, September 23, 2021, 07:15: Roughing. Waterline loop installed.

Monday, September 27, 2021, 10:35: MB1 off. Turbo pumps, IG, RP, all off/closed. DI water closed/purged.
TS shutdown for planned power outage.
Entry  Tuesday, September 14, 2021, 17:12, Aaron Schmidt, C#3, LP-SIS, ITW, TM2, 44691-7, 44378-11, In progress, C#3 Conditioning 6x
Tuesday, September 14, 2021, 17:00: Roughing
Tuesday, September 14, 2021, 17:37: TP1B on.
Tuesday, September 14, 2021, 17:47: TP1A on.
Entry  Tuesday, September 07, 2021, 16:04, Alexander Shkuratoff, , , , , , , Done, Replaced flange on F/T R with blank flange 
Feedthrough R had a flange installed with a HV feedthrough on it for TM3 service tray prototype HV tests. It was replaced today with the original blank
flange.
Entry  Tuesday, August 31, 2021, 13:55, Aaron Schmidt, , , , , , , , Pump down chamber 
Pump down chamber w/ empty HS
Entry  Wednesday, August 25, 2021, 15:30, Ferran Boix Pamies, , , , , , , , Thermocouple high voltage test 
Wednesday, August 25, 2021, 15:29: Roughing.

Thursday, August 26, 2021, 04:11: IG1 switched on. Vacuum @ 8.35e-06T - AS 
Thursday, August 26, 2021, 14:04 Water on, no spike in vacuum. IG1:2.6e-6T
Entry  Monday, August 23, 2021, 10:49, Aaron Schmidt - Fernando Maldonado, , , , , , , Problems/Solutions, RGA replaced with a blind flange 
Monday, August 23, 2021, 10:49: Aaron removed the Extorr RGA and install a blind instead.
When the new RGA arrives it will be changed.
Entry  Monday, August 23, 2021, 09:55, Fernando Maldonado, , , , , , , Problems/Solutions, RP1 changed back 
 Monday, August 23, 2021, 09:53: RP1 was swapped back to our original pump. (see e-log
889)
Derek informed that they test it overnight and performed well, and it's a bit slow but it goes down to 20 mT.
Entry  Saturday, August 07, 2021, 18:07, Fernando Maldonado, , , , , , , Problems/Solutions, FC0 lasrge oscillation and RMPs offset. Both started today. [Got solved by itself] 
Saturday, August 07, 2021, 18:02: As mentions in previous entries, the FC0 current oscillates with no change on ion source parameters.
Hence, I came on-site to see if there was an issue with the hardware. Nothing obvious.
Last night there were some sparks that might have cause some issue.
Entry  Thursday, August 05, 2021, 08:49, Fernando Maldonado, , , , , , , Problems/Solutions, CANBUS snooper set up to investigate random optics turnining off Annotation_2021-08-06_144737.png20210806_150334.jpg
Problem: Some devices turn off unexpectedly and sometimes without any obvious trigger. In the past, the only time this was an issue
was during mass scans. Now with the automation of measurements, this is a major problem as it prevents longer parameter scans.
Thursday, August 05, 2021, 08:00: Kevin setup the CANBUS snooper by hooking it up on the magnet card loop port.
Entry  Tuesday, August 03, 2021, 11:55, Fernando Maldonado, , , , , , , Problems/Solutions, Swapped emmittance meter voltage cables. 
After not being able to get beam through the emittance meter. I diagnosed that the plates was not biased (reason yet unknow).
I swapped the cables from the plates such that it looks like the picture below. With this, I was able to take an emittance scan with the previous
parameters.
Entry  Friday, July 30, 2021, 16:28, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Done, FEBIAD parameter scan - efficiency measurements  
Restarting everything after swapping RP1 (see elog 889).


Friday, July 30, 2021, 16:14: IG1 @ 7.02e-7 T.
Entry  Friday, July 30, 2021, 15:34, Carla Babcock, , , , , , , Failed, TSG:RP1 failure 
TP1A tripped off on Fernando, seems the backing pressure got too high. Even with PV1 closed the RP1 pump could not get below 200mTorr. Derek from vacuum
group came and had a look, and is swapping RP1 out for one of the vacuum group pumps, then will see if they can repair ours.
Entry  Wednesday, July 28, 2021, 08:48, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD parameter scan - efficiency measurements 
Modified spiral tube from VCR to counteract torque towards the HS. Now points towards TBHT.

Electric checks before closing shows no short between TIS and HS.
Entry  Tuesday, July 27, 2021, 12:57, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD parameter scan - efficiency measurements 
Assembly has new gas tube to the target for better fit and clearance to the HS.
Electric checks before closing shows no short between TIS and HS.

Tuesday, July 27, 2021, 12:57: Venting
Entry  Monday, July 26, 2021, 17:35, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD efficiency measurements. 
 Monday, July 26, 2021, 17:23: Roughing
Monday, July 26, 2021, 17:55: Turbos on.
Monday, July 26, 2021, 18:03 : TP1A timed out ...again
Entry  Thursday, July 22, 2021, 17:43, Fernando Maldonado, , LP-FEBIAD, , , 41790-10, 44378-5, Failed, FEBIAD efficiency measurements 
 Thursday, July 22, 2021, 17:43: Roughing
New argon gas bottle installed.
Thursday, July 22, 2021, 18:16: Turbos on.