  Test-Stand, Page 7 of 53  Not logged in ELOG logo
  ID Date Author Target/No.#down Source Station Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  337   Friday, September 27, 2013, 11:41 Anders MjosTa#41HP-SISITWTM439069-538817-10DoneTa#41 ConditioningFriday, September 27, 2013, 11:41: Roughing
Friday, September 27, 2013, 12:08:
Turbos started
 Ta#41_EE_After_Test_Stand.pdf 
  292   Wednesday, April 10, 2013, 12:14 Anders MjosTa#40HP-SISITETM438295-4 DoneConditioning Ta#40 Wednesday, April 10, 2013, 12:13:
Stopped turbos in preparation for venting
the chamber.
  
  295   Thursday, April 18, 2013, 13:50 Anders MjosTa#40HP-SISITETM438295-4 DoneTa#40 stored under vacuumTarget installed at the Test Stand after
an inspection in the lab. EE was cleand.
All bolts torqued to 130 in lbs
  
  287   Monday, March 25, 2013, 11:39 Anders MjosTa#39LP-SISITWTM1  DoneTa#39 commissioningTarget installed with 130 in lbs torque
on all bolts.
Monday, March 25, 2013, 11:36: Roughing
  
  101   Thursday, May 31, 2012, 15:43 Anders MjosTa#38LP-SISITWTM1  In progressTarget ready to be heatedThursday, May 31, 2012, 15:42: Roughing
Thursday, May 31, 2012, 16:01 : Starting
turbos
  
  102   Friday, June 01, 2012, 12:23 Aurelia LaxdalTa#38LP-SISITWTM1  In progressHV & Heaters conditioning.Did the HV conditioning.
Heaters conditioning in progress.
The Hall probe is not working: couldn't
  
  103   Monday, June 04, 2012, 10:51 Anders MjosTa#38LP-SISITWTM1  DoneVenting chamber

    

       
            
  
  1022   Friday, September 20, 2024, 14:22 Aaron SchmidtTa#LP-SISITETM245447-1845235-13 Conditioning Ta# https://elog.triumf.ca/TIS/Target+Production/146
Has not run through EVAP2.
Friday, September 20, 2024, 14:04:
  
  559   Wednesday, January 18, 2017, 09:23 Aaron SchmidtTa TestLP-FEBIAD  39530-3 In progressTri-Coil FEBIAD for testingWednesday, January 18, 2017, 09:22: Roughing
Wednesday, January 18, 2017, 09:41:
Turbo pumps started.
 12x 
  600   Wednesday, July 19, 2017, 09:13 Aaron SchmidtTa Targets     DoneIon PeaksAttached is a recent list of Ta targets
with their extracted ions peaks.
 Magnet_peaks.xlsx 
  658   Wednesday, April 25, 2018, 09:50 Aaron SchmidtTa (test)LP-SIS  41177-3 In progressTa test and window changeWindow changed on view port. Ta target
prepared for Aurelia's tests.
***Note*** No Ta window foils
 TS-2018-04-25-14-55.rgaTa_target_heating_test_-_Test_stand.docx 
  433   Thursday, April 02, 2015, 15:42 Anders MjosTM2 Test TargetLP-FEBIAD TM2 39230-1DoneTM2 Test Target ConditioningThursday, April 02, 2015, 15:42: Roughing
Thursday, April 02, 2015, 16:12:
Turbos started
 TM2_FEBIAD_Test_Target.docxER_Scans.zip 
  207   Thursday, September 20, 2012, 15:52 Anders MjosTEST SiCHP-FEBIAD    In progressInstallilng SiC-HP-FEBIAD target for operator trainingThursday, September 20, 2012, 15:50: Roughing
Thursday, September 20, 2012, 15:54:
Aborting. VCR for gas line not connected.
  
  208   Friday, September 21, 2012, 08:20 Anders MjosTEST SiCHP-FEBIAD    In progressInstallilng SiC-HP-FEBIAD target for operator training

    

       
            
  
  85   Tuesday, May 15, 2012, 07:39 Rick MaharajSic #27HP-SISITETM4  In progressWater on at test standThe vacuum on TSGIG1 reads 2.85e-07. Turing
on water on teststand and observing any changes
in vacuum pressure.
  
  969   Wednesday, May 31, 2023, 15:19 Aaron SchmidtSiC#46HP-SIS  44692-245235-6In progressConditioning SiC#2023A (Spare, renamed SiC-23B) - No salts(Spare HP-SIS SiC SiC-23B)
Wednesday, May 31, 2023, 15:18: Roughing.

Thursday, June 01, 2023,
 SiC#2023A_-_No_Salts.docx 
  966   Tuesday, May 09, 2023, 10:40 Aaron SchmidtSiC#45HP-SISITETM444692-345235-8In progressConditioning SiC#45Tuesday, May 09, 2023, 10:28: Roughing.
Tuesday, May 09, 2023, 11:25: TP1B
on. 
 SiC#45_Conditioning..docx 
  934   Thursday, June 23, 2022, 11:00 Aaron SchmidtSiC#44HP-FEBIADITETM437978-144378-24In progressConditioning SiC#44Thursday, June 23, 2022, 10:58: Roughing.
Thursday, June 23, 2022, 11:03: BV1A
open.
 SiC#44_-_R.docxER-580-290-30kV-m28.txtSiC#44.docx 
  932   Saturday, June 18, 2022, 10:04 Aaron SchmidtSiC#43HP-FEBIADITWTM242464-144378-16In progressConditioning SiC#43Note: SiC#42 replacement.
Saturday, June 18, 2022, 09:54: Roughing.
Saturday, June 18, 2022, 10:08: Data
 SiC#43_Conditioning_-_R.docxER-580-290-30kV-m27.txtSiC#43.docx 
  928   Wednesday, May 25, 2022, 15:48 Aaron SchmidtSiC#42HP-FEBIADITWTM244692-944378-5In progressConditioning SiC#42Wednesday, May 25, 2022, 15:46: Roughing.
Wednesday, May 25, 2022, 16:21: TP1B
on.
 ER-580-290-30kV-m28.txtSiC#42.docxSiC#42_Conditioning_-_R.docx 