Tuesday, November 15, 2022, 11:24, Aaron Schmidt, UC#41 assembly, LP-SIS, ITE, TM4, 45220-8, 45235-4, In progress, Conditioning UC#41 assembly
|
LP-SIS 45220-8 is empty & for testing only.
Tuesday, November 15, 2022, 11:00: Roughing.
Tuesday, November 15, 2022, 11:21: BV1A open. |
Wednesday, October 19, 2022, 12:16, Aaron Schmidt, , , , , , , , Test Stand controls changed
|
genepicsas.triumf.ca
x11 enabled.
Then use login credentials. |
Tuesday, October 18, 2022, 13:25, Aaron Schmidt, C#5, LP-SIS, , , 45235-5, 44691-13, In progress, Conditioning C#5
|
Tuesday, October 18, 2022, 13:25: Roughing.
Tuesday, October 18, 2022, 13:28: BV1A open
Wednesday, October 19, 2022, 12:14: TP1B on. |
Thursday, September 29, 2022, 13:50, Aaron Schmidt, , , , , , , In progress, Pump down empty chamber
|
Water loop installed.
Thursday, September 29, 2022, 13:50: Roughing
Tuesday, October 18, 2022, 11:17: Venting |
Tuesday, September 27, 2022, 07:55, Aaron Schmidt, C#4, LP-SIS, ITE, TM4, 44691-3, 44378-23, In progress, Conditioning C#4 w/ thermocouples
|
Thermocouples attached on 5 X 5 multi-pin:
O - O
O - X |
Tuesday, August 30, 2022, 13:58, Aaron Schmidt, , , , , 44062-7, 44378-25, In progress, Conditioning UC#40 assembly
|
Conditioning the UC#40 LP-SIS assembly & ISAC TS main vacuum chamber. Straight / round oven in use (TGHT only).
Tuesday, August 30, 2022, 13:55: BV1B open. Roughing.
Tuesday, August 30, 2022, 14:00: BV1A open. |
Monday, July 11, 2022, 09:17, Aaron Schmidt, , , , , , , In progress, Pump down empty chamber
|
Monday, July 11, 2022, 09:15: Roughing. |
Sunday, July 10, 2022, 22:19, Aaron Schmidt, , , , , , , Problems/Solutions, TP2 Trip / TMS:RP2 issue
|
Sunday, July 10, 2022, 22:19: A trip was noted on TP2. the backing pressure is quite high. Shutting off the turbo pumps for the beamline side.
|
Thursday, July 07, 2022, 16:52, Aaron Schmidt, , LP-IG-LIS, ITW, TM2, , 42132-3, In progress, Conditioning UC#39 assembly
|
No UCx target installed. Straight / blank oven in use for out gassing.
Thursday, July 07, 2022, 16:50: Roughing.
Thursday, July 07, 2022, 16:53: BV1A Open. |
Thursday, June 30, 2022, 13:50, Aaron Schmidt, , , , , , , , Pump down empty chamber
|
Thursday, June 30, 2022, 13:46: Roughing.
Thursday, July 07, 2022, 15:00: Venting. |
Thursday, June 23, 2022, 11:00, Aaron Schmidt, SiC#44, HP-FEBIAD, ITE, TM4, 37978-1, 44378-24, In progress, Conditioning SiC#44
|
Thursday, June 23, 2022, 10:58: Roughing.
Thursday, June 23, 2022, 11:03: BV1A open.
Thursday, June 23, 2022, 11:34: TP1B on |
Monday, June 20, 2022, 11:49, Aaron Schmidt, , , , , , , , Pump down empty chamber
|
Monday, June 20, 2022, 11:49: Water line loop installed. Roughing.
Thursday, June 23, 2022, 09:25: Venting. |
Saturday, June 18, 2022, 10:04, Aaron Schmidt, SiC#43, HP-FEBIAD, ITW, TM2, 42464-1, 44378-16, In progress, Conditioning SiC#43
|
Note: SiC#42 replacement.
Saturday, June 18, 2022, 09:54: Roughing.
Saturday, June 18, 2022, 10:08: Data logger removed. Pins 4 & 5 grounded. Power on. |
Wednesday, June 08, 2022, 10:01, Aaron Schmidt, Ta#64, LP-SIS, ITE, TM4, 44691-12, 44378-13, In progress, Conditioning Ta#64 & HV Test. 7x
|
Thermocouples connected. Test HV
Wednesday, June 08, 2022, 09:33: Roughing.
Wednesday, June 08, 2022, 10:07: TP1B on. |
Tuesday, May 31, 2022, 13:35, Aaron Schmidt, UCx HS, , ITW, TM2, , 44378-19, In progress, Conditioning UC#38 assembly
|
Using a broken LP-FEBIAD source. TGHT only.
Tuesday, May 31, 2022, 13:24: Roughing.
Tuesday, May 31, 2022, 13:54: TP1B on. |
Friday, May 27, 2022, 07:19, Fernando Maldonado, , , , , , , Done, FEBIAD parameter scan web-app and brief description (with links)
|
A web-app for systematic FEBIAD parametrizations has been develop and now includes the ISAC Test Stand (ITS) :
https://beta.hla.triumf.ca/degaussing/FEBIAD-scan/
Upon landing in the web-app the ITS will be selected by default as well as the TMS:FC6:SCALECUR faraday cup, which corresponds the last cup of |
Wednesday, May 25, 2022, 15:48, Aaron Schmidt, SiC#42, HP-FEBIAD, ITW, TM2, 44692-9, 44378-5, In progress, Conditioning SiC#42
|
Wednesday, May 25, 2022, 15:46: Roughing.
Wednesday, May 25, 2022, 16:21: TP1B on.
Wednesday, May 25, 2022, 16:38: TP1A on. |
Thursday, May 12, 2022, 10:50, Aaron Schmidt, , P2N-SIS, ITE, TM4, 44812-2, 45240-1, In progress, P2N assembly conditioning - 4
|
PE shimmed & extended 1mm due to likely ion source contact.
Thursday, May 12, 2022, 10:41: Roughing.
Thursday, May 12, 2022, 11:26: TP1B on. |
Wednesday, May 11, 2022, 10:05, Aaron Schmidt, , P2N-SIS, ITE, TM4, 44812-2, 45240-1, , P2N assembly conditioning - 3
|
Target oven #45241-1 swapped out. SS bolts were in use on the legs.
Molybdenum screws in the legs on oven #44812-2. No target to ion source cup interference. 3mm gap - OK.
TGHT - R: 1.215 |
Tuesday, May 10, 2022, 10:09, Aaron Schmidt, , P2N-SIS, ITE, TM4, 45241-1, 45240-1, In progress, P2N assembly conditioning - 2
|
Ref: https://elog.triumf.ca/TIS/Test-Stand/924. During testing, it was noted one leg was glowing vs the other. P2N assembly was removed & inspected.
No contact or defects were found.
Tuesday, May 10, 2022, 10:05: Roughing. |
|