847
|
Tuesday, February 09, 2021, 14:02 |
Aaron Schmidt | | | | | | | Problems/Solutions | DI water loss | Tuesday, February 09, 2021, 13:43: DI water flow completely stopped.
Control room contacted. DI water loss confirmed.
Tuesday, February 09, 2021, 13:52: DI water flow returned.
Control room contacted. DI water loss due to a "seamless" pump change over for the DI water supply & mechanical services. The supply was transferred over to a new pump which overloaded and failed. They had to switch back over to the (old) pump. Mechanical services will still try to do the switch over again. Either tomorrow or the day after. Running the TS up to 580A until then is not recommended. Control room to update tomorrow morning.
Fault# 13773: Cu-LCW south SA3-03 tripped on motor overload. |
849
|
Friday, February 12, 2021, 12:16 |
Fernando Maldonado | | | | | | | Problems/Solutions | Grounding collimator cable from outside | Friday, February 12, 2021, 12:13: Since the collimator is not used, Carla and I installed a BNC short outside the cage. See picture. |
Attachment 1: 20210212_121227.jpg
|
|
850
|
Friday, February 12, 2021, 16:38 |
Fernando Maldonado | | | | | | | Failed | FEBIAD parameter scan - efficiency measurements - energy spread. | Friday, February 12, 2021, 16:37: FEBIAD installed with mechanical calibrated leak
Friday, February 12, 2021, 16:38: Roughing.
Gas lines opened all the way to the sour. SV4 and SV5.
Friday, February 12, 2021, 18:47: Turbos on.
Friday, February 12, 2021, 18:55: IG1 on.
Friday, February 12, 2021, 23:22: IG1 @ 1.5E-4 T. I think the line inside the vacuum chamber is leaking
Friday, February 12, 2021, 23:23: SV5 closed.
Friday, February 12, 2021, 23:24: Vacuum dropping slightly.
Friday, February 12, 2021, 23:24: SV5 opened. IG1 responds to the opening of SV5. The lines from the feedthrough to the calibrated leak need to be re-done.
Tuesday, February 16, 2021, 10:21: IG1 off. Turbos off.
Tuesday, February 16, 2021, 11:21: Venting.
Aaron closed SV4 and the vacuum drop normally. Leak through SV5 as well. |
851
|
Tuesday, February 16, 2021, 14:52 |
Fernando Maldonado | | | | | | | Problems/Solutions | Leak checking gas lines. | Vacuum side
Tuesday, February 16, 2021, 13:42: The gas lines inside have been check. The inlet of the calibrated leak was not tighten properly and hence the large leak observed. FIXED.
Tuesday, February 16, 2021, 13:42: The only leak remaining INSIDE the vacuum is the one on the FT side which for 200kPa is around 7e-6 atm cc /s. At this pressure, the undesired leak is leak rate is around 1 % of the one getting into the source.
Atmosphere side
Tuesday, February 16, 2021, 14:49: Some minor leaks in connection points around 1e-6 atm cc/s. Not much I can do without changing all connection to glands with metal gaskets.
Tuesday, February 16, 2021, 14:50: SV5 was leak check on its own, the gas goes through quite noticeable, no need to sniff with leak detector. SV1 leak checked and it works.
Tuesday, February 16, 2021, 14:52: Valves swapped, labels changed.
Tuesday, February 16, 2021, 15:17: Roughing.
Tuesday, February 16, 2021, 15:53: Turbos on.
Tuesday, February 16, 2021, 15:59: IG1 on
Tuesday, February 16, 2021, 16:29: IG1 @ 5.3e-5 and dropping. Already better than Friday/Saturday.
Tuesday, February 16, 2021, 16:53: IG1 @ 2.9e-5 T.
Wednesday, February 17, 2021, 16:53: IG1 @ 1.5e-6 T.
Wednesday, February 17, 2021, 16:53: The Neon bottle seems to be empty. The leak on the lines were not as bad to have this happened. I suspect when squeezing the bottle I rotated the gauge enough to cause a leak there.
Wednesday, February 17, 2021, 17:00: Using a full nitrogen bottle, I confirmed that rotating the two-stage regulator causes a leak.
Wednesday, February 17, 2021, 18:00: Things look OK now. Water open. No response on vacuum. Will put power.
Wednesday, February 17, 2021, 20:00: Some items were timed out. Tried to recycle the PLC now all the items are red. Check tomorrow |
852
|
Thursday, February 18, 2021, 10:47 |
Aaron Schmidt | | | | | | | | Optics loss / CANBUS failure. | Thursday, February 18, 2021, 10:45: TPS:Q3 & the TSB CBC CANBUS controllers had failed yesterday, as well as a cable was incorrectly seated. This was fixed this morning.
Before
After.
|
853
|
Thursday, February 18, 2021, 11:03 |
Aaron Schmidt | | | | | | | Problems/Solutions | DI water pump configuration | https://elog.triumf.ca/TIS/Test-Stand/847
There was a previous DI CU-LCW pump trip as per the above elog. The CU-LCW pump was configured this morning. The water pressure is set to 80 PSI as per the MCR. Any further can overload & trip the pump.
Thursday, February 18, 2021, 10:55: Current flow rates & pressure read at the TS
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
22.30 |
3.8 |
TBHT |
22.14 |
6.27
|
COIL + EE |
22.08 |
1.74 |
TGHT |
22.16 |
5.04 |
DI water pressure as per the gauge on the supply side of the FS#2-5 manifold @ 85 PSI.
Noticeable flow rate reduction based on previous target conditioning logs. Previous pressure was around 100 PSI. |
854
|
Thursday, February 18, 2021, 15:15 |
Fernando Maldonado | | | | | | | Done | HLA tests | Thursday, February 18, 2021, 15:01: With the help of Spencer Kiy, we tested the proper communication from python to epics.
Getting TSP:Q1 PV: successful both from the web application and jupyter notebook.
Setting TSP:Q1 PV: successful from the web application, failed jupyter notebook.
Issue fixed on the HLA server side
Setting TSP:Q1 PV: successful both from the web application and jupyter notebook.
Testing other potentially useful apps for ramping routines and a customized "striptool".
HLA developments only available from the ISAC test stand's PC and Fernando's PC.
|
855
|
Thursday, February 18, 2021, 16:48 |
Fernando Maldonado | | | | | | | Failed | FEBIAD parameter scans | Thursday, February 18, 2021, 15:19: Gas lines roughed and refilled. Gauge reads -50 kPa. Absolute pressure is 50 kPa.
IG1 @ 9.7 e-7 T.
Thursday, February 18, 2021, 15:27: BIAS/EZL/EE @ 30/13/1.5 kV. No sign of instabilities as before. Bias current=0.08 mA.
This also means the leak, in this clean environment is fine.
Thursday, February 18, 2021, 15:28
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
22.25 |
3.71 |
TBHT |
22.11 |
6.16
|
COIL + EE |
21.94 |
1.71 |
TGHT |
22.06 |
5.02 |
Slightly drop in flow. Will check later as well.
Thursday, February 18, 2021, 15:37: BIAS/EZL/EE @ 35/13/1.5 kV.
Thursday, February 18, 2021, 15:39. Spark inside. Recover with no problem
Thursday, February 18, 2021, 16:27 : BIAS/EZL/EE @ 40/13/1.5 kV.
Thursday, February 18, 2021, 16:28: Spark
Thursday, February 18, 2021, 16:42:
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
22.16 |
3.66 |
TBHT |
21.91 |
2.42
|
COIL + EE |
21.91 |
1.66 |
TGHT |
21.8 |
4.91 |
Thursday, February 18, 2021, 17:1: Logging water temperature and flow in the PC.
Thursday, February 18, 2021, 17:19: BIAS/EZL/EE @ 0.000 kV.
Thursday, February 18, 2021, 17:20: Auto-ramping TGHT/TBHT to
Thursday, February 18, 2021, 17:26: Anode is shorted. It seems that the Ta capillary is touching the HS. I have to open.
Thursday, February 18, 2021, 17:35: IG1 and turbos off.
Thursday, February 18, 2021, 18:2: Venting
Thursday, February 18, 2021, 18:42: Gauge reader at the service cap is now at -40 kPa. A 10 kPa incursion over 4 hours.
Friday, February 19, 2021, 11:04: The anode still has a short, returning all previous jumpers. Short present.
Unhooked anode cable can sustain voltage, hence the electric circuit has a short,
Friday, February 19, 2021, 11:48: Target removed. No short on anode-target. However there is no short in the service tray either, the voltage from the anode supply is held with no problem.
Friday, February 19, 2021, 12:41: Only when the tbht is bolted the power supply goes current limited.
Friday, February 19, 2021, 12:44: Source tray can hold anode voltage without drawing any current, as expected.
Friday, February 19, 2021, 12:52: Target legs to HS presents a short. When HS is removed the short is gone. Will try to find the contact point.
Friday, February 19, 2021, 12:56: Suspecting that is the gas line that goes to the back of the TGHT; is too high and touches the HS. Putting and insulator and installing the HS cover. No short.
Removing the insulator there is a short.
Will bend the gas line.
Friday, February 19, 2021, 13:08: Installed the open assembly, and the anode voltage is held in the system without drawing current, as expected.
Friday, February 19, 2021, 13:21: TIS assy re-installed, short is fixed. |
856
|
Friday, February 19, 2021, 13:44 |
Fernando Maldonado | | | | | | | Failed | FEBIAD parameter scans | Friday, February 19, 2021, 13:28: Roughing
Friday, February 19, 2021, 13:43: Power on
Friday, February 19, 2021, 13:59: Turbos on
Friday, February 19, 2021, 14:07: IG1 on.
Friday, February 19, 2021, 15:06: Water open. No vacuum response.
Friday, February 19, 2021, 15:06: IG1 @ 3.13e-5 T.
Friday, February 19, 2021, 15:47 :
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
23.26 |
3.92 |
TBHT |
23.09 |
6.15
|
COIL + EE |
23.09 |
1.80 |
TGHT |
23.02 |
5.06 |
Friday, February 19, 2021, 15:48: IG1 @ 1.65 e-5 T
Saturday, February 20, 2021, 09:19. IG1 @ 1e-6 T
Saturday, February 20, 2021, 09:20: Auto-ramping TGHT/TBHT to 300,150 A @ 2A/min
Saturday, February 20, 2021, 13:26: IG1 @ 1.78e-6 T
Saturday, February 20, 2021, 13:29: Anode @ 50 V. Coil @ 20 A.
Saturday, February 20, 2021, 13:52: Bias voltage only reaches 6 kV, the bias current seems a bit unstable, not sure now what the problem is.
Saturday, February 20, 2021, 14:58: Auto-cooling TGHT/TBHT to 0 A @ 2 A/min
Sunday, February 21, 2021, 11:24: Auto-ramping TGHT/TBHT to 580/290A @ 2A/min
Sunday, February 21, 2021, 16:39: Ramp up complete. IG1 @ 2.15e-6 T.
Will wait until vacuum is stable to try to put high voltage.
Sunday, February 21, 2021, 21:51: IG1 @ 2.06e-6 T. Unable to go above 5 kV.
Sunday, February 21, 2021, 22:00: Auto-cooling TGHT/TBHT to 0 A @ 2 A/min
Monday, February 22, 2021, 09:12: IG1@1.01e-7 T. Bias gets current limited as of 11 kV. The system does not spark so the current is leaking through somewhere.
Monday, February 22, 2021, 09:29: Grounding the TM2 F/T. No effects, same bias issues.
Monday, February 22, 2021, 11:3: the only way for this instabilities to occur is with a short between ground and HV. No such touch is occurring inside.
Monday, February 22, 2021, 11:37: Instability reacts with punching the cage, that is, shaking up the cage causes the instability to decrease.
Will re-accommodate the cage as it seemed slightly crooked, hence the motivation to punch it.
Monday, February 22, 2021, 14:00: Cage re-accommodated with the help of Aaron. Move a insulating cable that was touching a FT.
Monday, February 22, 2021, 14:30: Now sparks are visible between the coil/HS waterlines and ground waterlines (see pictures attached). I have to open the vacuum chamber.
Monday, February 22, 2021, 14:54: IG1 off. Turbos off.
Monday, February 22, 2021, 15:49: Venting
Monday, February 22, 2021, 16:43: Made clearance between HS/COIL to GND.
|
Attachment 1: GND-COIL_spark.jpg
|
|
Attachment 2: GND-HS_spark.jpg
|
|
859
|
Monday, March 01, 2021, 16:13 |
Fernando Maldonado | | | | | | | Done | Temporary RGA installation | Monday, March 01, 2021, 16:03: An ExTorr RGA has been installed in the ISAC test stand.
The original SRS 100 is still broken ( e-log 778)
The SRS 100 from the conditioning station will not be available this week. |
Attachment 1: EXTorr.PNG
|
|
860
|
Tuesday, March 02, 2021, 11:42 |
Aaron Schmidt | | | | | | | | TS Tripped. |
Tuesday, March 02, 2021, 11:40: Fully reset
TGHT / TBHT set to 20 A ok. Anode w/ 30 V. ok.
Tuesday, March 02, 2021, 11:42: 10 A on coil. Increment was at 75 A. Set back to 1 A.
Tuesday, March 02, 2021, 11:44: BIAS / EE / EZL @ 1 / 0.5 / 1 kV.
|
861
|
Wednesday, March 10, 2021, 11:10 |
Carla Babcock | | | | | | | | Venting for installation of emittance meters | Wednesday, March 10, 2021, 10:48 : Venting beamline section only for installation of emittance meters. |
862
|
Wednesday, March 10, 2021, 14:28 |
Aaron Schmidt | | | | | | | In progress | RP2 swap. | Swapped RP2 out from a Varian SH-110 to a Varian PTS06001.
Wednesday, March 10, 2021, 14:20: RP2 on.
Wednesday, March 10, 2021, 14:27: Turbo pumps on |
864
|
Monday, March 15, 2021, 16:10 |
Carla Babcock | | | | | | | | TISA emittance meter testing with new FEBIAD source | Monday, March 15, 2021, 16:09 Target and ion source ramped to 400A/330A this afternoon
Monday, March 15, 2021, 18:53 : Tune through to final RPMs but not optimized. 5e-8 on FC0. Will turn down target and ion source values to TGHT/TBHT 350/250 until tomorrow. BIAS/EZL/COIL/ANODE all off.
Tuesday, March 16, 2021, 15:04 Mike is finished with emittance meter controls so ramping everything back up and trying to get beam through.
Thursday, March 18, 2021, 18:06 : Vacuum has been rising slowly over the past 20hrs from 9.3e-7 to 9.9e-7. Everything has been up since Tuesday. No beam through emittance meter, though beam can be found on the regular test stand emittance meter. Just discovered that both voltage plates are plugged into positive power supplies so waiting for a controls fix on that then will retry.
Friday, March 19, 2021, 17:08 : Finally success. New emittance meter shows same results as the standard test stand emittance rig. Will continue testing new controls next week |
Attachment 1: Carla_tune_tracking.docx
|
865
|
Thursday, March 25, 2021, 08:11 |
Aaron Schmidt | | | | | | | | Test Stand Tripped. (Water leak) |
Lot's of water visually present in the chamber.
Wednesday, March 24, 2021, 13:17: Water lines purged.
Vent & wipe out the water inside the chamber. Setup a fan to aid in drying. Manually purge the water from the RP1 Scroll pump through the exhaust.
Thursday, March 25, 2021, 08:06: Gradually open each line to check the water blocks & fittings for a visual leak. Open the ballast plug on RP1, as well as manually purge the water from the RP1 Scroll pump through the exhaust again.
Thursday, March 25, 2021, 08:34: Leak found on FS#3 - Left Coil return (G) water block.
Thursday, March 25, 2021, 09:15: FEBIAD assembly & L-Coil line removed.
Thursday, March 25, 2021, 11:38: Re-connect RP1 to the exhaust port & re-insert the ballast plug.
Thursday, March 25, 2021, 11:40: RP1 Ok. CG1A & CG1 B around 0.048T & dropping. Chamber still open.
Indium gasket installed on G, C-Seal on E.
Friday, March 26, 2021, 08:21: Roughing.
Friday, March 26, 2021, 09:08: Vacuum @ 2.001 T. Opened FS#3 waterline. Quick test.
Friday, March 26, 2021, 09:11: Vacuum @ 1.901 T. No observable spike on CG1.
Friday, March 26, 2021, 09:12: Close FS#3 & purge
Friday, March 26, 2021, 09:27: Quickly open ballast plug.
Friday, March 26, 2021, 09:30: Re-insert plug.
Friday, March 26, 2021, 09:38: CG1 @ 2.253 T.
Friday, March 26, 2021, 09:41: Close BV1A & B.
Friday, March 26, 2021, 09:45: Manually purge water from the RP1 Scroll pump through the exhaust.
Friday, March 26, 2021, 09:51: Re-open BV1A & B.
Friday, March 26, 2021, 10:17: Close BV1A & B. Manually purge water from the RP1 Scroll pump through the exhaust.
Friday, March 26, 2021, 10:26: Close the exhaust & give the pump time to recover.
Friday, March 26, 2021, 10:36: Briefly vent the chamber to 30 T. Re-open BV1A & B.
Friday, March 26, 2021, 11:20: Vacuum @ 1.706T. Open FS#3. Allow to fill with water, then close off. No observable spike on CG1.
Friday, March 26, 2021, 11:25: Opened ballast cap. Close BV1A & B.
Friday, March 26, 2021, 11:26: Close ballast.
Friday, March 26, 2021, 11:29: Briefly vent the chamber to 30 T. Re-open BV1A & B.
Friday, March 26, 2021, 12:11: Vacuum @ 2.75T. Close BV1A & B. Vent chamber to setup a fan.
Monday, March 29, 2021, 09:00: LD & He attached. LD#2 as supplied via Vacuum group.
Monday, March 29, 2021, 09:01: Sniffer set. Leak Rate @ 2.0E-07 to 2.3E-07 atm-cc/sec
Monday, March 29, 2021, 09:03: Pressurize (E)(G) to 75 PSI.
Monday, March 29, 2021, 09:05: No major spike seen on LD.
Monday, March 29, 2021, 09:06: Pressurize (E)(G) to 100 PSI.
Monday, March 29, 2021, 09:09: No major spike seen on LD. Purge He from the lines.
Monday, March 29, 2021, 09:12: Roughing.
Monday, March 29, 2021, 09:22: Opened ballast cap to release water vapour while roughing.
Monday, March 29, 2021, 09:42: Closed the ballast cap. Purge cycle RP1 on & off for the next hour or so.
To purge cycle RP1 for water vapour. Close BV1A & B. Disconnect exhaust line from RP1 & open the upper ballast. Close PV1, Vent with TSG:VV1A till the line reaches atmosphere with dry nitrogen.
Close VV1 & open PV1. Water should spew out of the exhaust. Rough the backing lines down. Open BV1A & B to rough then chamber. Repeat leaving the upper ballast open.
Monday, March 29, 2021, 14:00: Purge RP1. Close upper ballast, re-connect exhaust.
Monday, March 29, 2021, 14:36: TP1B on.
Monday, March 29, 2021, 19:47: TP1A on.
Monday, March 29, 2021, 19:55: IG1 on.
Tuesday, March 30, 2021, 08:52: Vacuum @ 4.48e-06T.
LD to TP1B base @ 1.4E-08 to 1.9E-08 atm-cc/sec.
Tuesday, March 30, 2021, 08:58: He @ 55 PSI
Tuesday, March 30, 2021, 09:04: LD to TP1B base @ 2.4E-08 atm-cc/sec.
Tuesday, March 30, 2021, 09:12: Reconnect FS#3 to DI.
Tuesday, March 30, 2021, 09:14: Opened FS#3 w/ DI
Tuesday, March 30, 2021, 09:20: Vacuum @ 4.40e-06T.
Tuesday, March 30, 2021, 09:33: FS#2, 4, & 5 open. Vacuum ok @ 4.40e-06T
Tuesday, March 30, 2021, 09:34: Power/sources on.
Tuesday, March 30, 2021, 09:37: Auto-ramping TGHT / TBHT to 200 / 100 A @ 2 A per min.
Tuesday, March 30, 2021, 12:12: Auto-ramping TGHT / TBHT to 350 / 125 A @ 2 A per min.
Tuesday, March 30, 2021, 13:50: Vacuum @ 4.66e-06T. Auto-ramping TGHT / TBHT to 450 / 150 A @ 2 A per min.
Tuesday, March 30, 2021, 21:59: Vacuum @ 5.01e-06T. TGHT / TBHT @ 393 / 150 A. Reset Auto-ramping TGHT / TBHT to 550 / 200 A @ 2 A per min.
Wednesday, March 31, 2021, 11:46: IV4 opened. Optics & HV power switched on.
Wednesday, March 31, 2021, 11:52: HV check ok. Optics reset. BIAS / EE / EZL @ 1 / 0.1 / 1 kV. Coil @ 4 A. Anode @ 100 V
Wednesday, March 31, 2021, 11:54: Optics remain on. HV & coil back to 0. Ready to run once the Vacuum returns to a reasonable level. Vacuum @ 5.45e-06T.
Wednesday, March 31, 2021, 15:05: Auto-ramping TGHT / TBHT to 580 / 270 A @ 2 A per min. |
Attachment 1: Mar_2021_-_FS#3_leak..docx
|
866
|
Friday, March 26, 2021, 17:04 |
Carla Babcock | | | | | | | | Beam line vented for emittance meter exchange | Vented beamline and removed ARIEL emittance meter. In the process of swapping components, beamline left vented until Monday when we will finish the job. |
867
|
Tuesday, March 30, 2021, 13:19 |
Carla Babcock | | | | | | | | Second emittance meter testing | Emittance meter number 2 ready for beam shortly - installed and pumping down.
No beam found by Thursday evening, but beam seems to be coming out much differently than last time. Will check on emittance meter functionality and try to re-tune later.
Ramping things down for the next couple days.
Saturday, April 03, 2021, 10:41 :
Source heating ramped back up, everything back on. Will try to straighten out steering then see if I can get things back in the previous positions.
Saturday, April 03, 2021, 14:59 :
Nothing seems to be working, will vent the beamline and remove the slit.
Saturday, April 03, 2021, 15:36 :
Apparently closing the valve started a vacuum leak that tripped everything in the source. I noticed within the first minute and ramped everything back up, maybe too quickly....
Have now put everything in a holding state, will resume tomorrow.
Sunday, April 04, 2021, 14:17 :
Found everything off again this morning. Ramping back up in the hopes that I can get something done before the whole system trips again. The trips look like water leaks again.
Uninstalled the slit and left it in the bottom of the vacuum box. Swapped the window to the computer side for convenience. Seal on the other side on the CF flange is a bit weird, not sure if it is in properly...
Sunday, April 04, 2021, 18:43
Still no beam. TISA emittance FC won't come back on, so waiting for Mike Rowe to troubleshoot on Tuesday. Will ramp things down all the way, since I expect the vacuum to trip the source before I need it again.
Tuesday, April 06, 2021, 23:43
Found some beam, but looks really weird, like it is cut off. Good enough. Ramped everything down. |
Attachment 1: Carla_tune_tracking.docx
|
868
|
Sunday, April 04, 2021, 14:16 |
Carla Babcock | | | | | | | | Water leak problem persists | IG1 has been spiking randomly, causing everything to turn off. Looks like the water leak is still there.
AS - Multiple purges done on RP1 & the backing lines. Some water noted. FS#3 is closed.
Tuesday, April 06, 2021, 09:39: TP1B on.
Tuesday, April 06, 2021, 10:01: TP1A on.
Tuesday, April 06, 2021, 10:12: IG1 on. Vacuum @ 1.97e-05T.
Tuesday, April 06, 2021, 11:00: FS#2, #4, & #5 open. Vacuum @ 5.73e-06T.
Tuesday, April 06, 2021, 11:12: Vacuum @ 5.09e-06T. Open FS#3.
Tuesday, April 06, 2021, 11:17: IG1 @ 4.64e-06T. Open IV4. Reset optics & sources.
Tuesday, April 06, 2021, 11:20: Optics on.
Test were run
Thursday, April 08, 2021, 10:30: Power / sources off.
Thursday, April 08, 2021, 10:34: IG1 & turbo pumps off.
|
869
|
Tuesday, April 13, 2021, 13:27 |
Aaron Schmidt | | | | | | | | Indium gaskets installed FS#3 | Changed the gaskets from C-seals on FS#3 water blocks E, F,& H. G was already done.
Tuesday, April 13, 2021, 13:23: FS#3 Waterline opened.
Tuesday, April 13, 2021, 13:25: No immediate water noticed visually or on the gloves.
Tuesday, April 13, 2021, 13:31: Visual leak present on (F). Purge the line.
Change the gasket.
Tuesday, April 13, 2021, 14:42: FS#3 Waterline opened.
Tuesday, April 13, 2021, 14:55: No water leak noticed visually or on the gloves.
Tuesday, April 13, 2021, 14:58: Roughing. Will leak check under vacuum tomorrow morning.
Tuesday, April 13, 2021, 16:01: TP1B on.
Tuesday, April 13, 2021, 20:53: TP1A on.
Tuesday, April 13, 2021, 20:58: IG1 on.
|
873
|
Wednesday, May 19, 2021, 16:02 |
Aaron Schmidt | | | | | | | | P2N HS conditioning | Parasitic assemblies on the lid & end plate included. Online HS.
Wednesday, May 19, 2021, 16:00: Roughing.
Thursday, May 20, 2021, 08:42: Turbo pumps were turned on last night. Vacuum @ 9.99e-07T.
Thursday, May 20, 2021, 08:44: FS#5 open. Vacuum ok.
Thursday, May 20, 2021, 08:45: Power / sources on.
Thursday, May 20, 2021, 09:34: Turbos OFF
Thursday, May 20, 2021, 10:37: Venting.
Thursday, May 20, 2021, 11:28: P2N legs no longer touching. Roughing.
Thursday, May 20, 2021, 12:05: Turbo pump TP1B on.
Thursday, May 20, 2021, 12:10: Turbo pump TP1A on.
LE:
Thursday, May 20, 2021, 15:00: Ramping stared at high warming rate. 10 or 5 A every 15 seconds
Friday, May 21, 2021, 01:31: Around midnight, the P2NHT current was very noisy for few hours, and then it dropped to zero. Turbos are now stopped to open up and investigate.
Friday, May 21, 2021, 05:45 P2N assembly removed, water lines closed and purged - one leg is fully broken
FBP:
HV tests Monday 24/05/2021 and Tuesday 25/05/2021
HS was ramped up to 30KV on monday, only 1 spark seen over night. BIAS/EZL/EE : 30KV/14KV/-1.5
Ramping to max HV on Tuesday.
40KV
AS:
Tuesday, May 25, 2021, 11:5: HV tapped down to 0 kV on BIAS / EE / EZL.
Wednesday, May 26, 2021, 07:23: Power / sources off. IG1 off. Turbo pumps off.
Wednesday, May 26, 2021, 09:04: Venting. Waterlines purged.
LE:
Wednesday, May 26, 2021, 10:37 Target removed from test stand and brought to cold lab
|
Attachment 1: HV_test_-_Online_HS_&_parasitic_mods.docx
|
|