Thursday, November 08, 2018, 14:13, Aaron Schmidt, , , , , , , , Ar & Ne gas bottle replacement.
|
Thursday, November 08, 2018, 14:05: Fresh / recently calibrated Neon & Argon bottles installed.
Leak rates: Argon=2.02E-7 atm*cc/sec
Neon=1.75E-7 atm*cc/sec |
Monday, December 17, 2018, 12:03, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, , Anode leak current check.
|
Monday, December 17, 2018, 12:01: Connected Multimeter through feedthroughs J & L. Blue wire removed.
To run TGHT, TBHT, Anode ONLY. HV will remain locked with yellow tape over the keyhole. Currently locked out.
Tuesday, December 18, 2018, 08:37: Power / sources on |
Thursday, December 20, 2018, 13:55, Aaron Schmidt, , LP-FEBIAD, , , 395530-3, 42752-5, , Holiday shut down.
|
High winds caused a brief power outage that completely shutoff the ISAC test stand.
Locked out the power.
RGA checked & shutoff complete |
Wednesday, January 09, 2019, 09:10, Aaron Schmidt, , , , , , , , Cathode to Anode. PS to Positive
|
Wednesday, January 09, 2019, 09:09: Upper HV cage set to Anode / Positive as per dwg ISK4523D Rev 6.
Thursday, January 10, 2019, 10:00: Switch Anode PS to positive
Thursday, January 10, 2019, 11:29: Anode switched on. Short discovered. 10 V = 0 V & 100 mA. |
Thursday, January 10, 2019, 11:38, Aaron Schmidt, , , , , , , , Power outtage prep
|
Thursday, January 10, 2019, 11:32: Power down TS. Lock out.
Thursday, January 10, 2019, 11:36: RGA switched off full.
Thursday, January 10, 2019, 11:38: All ion gauge and turbos off. BV's closed. |
Monday, January 14, 2019, 09:47, Aaron Schmidt, , , , , , , , TS restart after power outage
|
Monday, January 14, 2019, 09:00: Epics white out
Ref: Fault report 11993 (11981 & 11817)
Monday, January 14, 2019, 09:35: Vacuum page came back. Restarted Roughing pumps. All other pages still in whiteout state. |
Monday, January 21, 2019, 10:55, Aaron Schmidt, , , , , , , , 2019 Anode tests FM-1
|
Monday, January 21, 2019, 10:50: RGA on.
Monday, January 21, 2019, 10:54: Waterlines opened. No response on RGA. Vacuum ok @ 8.4e-07. IG6 not responding. Ok for this test.
Monday, January 21, 2019, 11:00: Power / Sources on. |
Thursday, January 24, 2019, 08:42, Aaron Schmidt, , , , , , , , IG6 fix (w/ instruction)
|
TMS:IG6 had continued communication errors post power outage & would not switch on. After a power loss, IG6 switches automatically to Filament 1.
Filament 1 is burnt out.
Thursday, January 24, 2019, 08:14: TMS:IG6 fixed. Switched from Filament 1 to Filament 2. FIL2 runs ok. |
Friday, February 22, 2019, 11:11, Aaron Schmidt, , LP-FEBIAD, , , , , , Gas line backing pump tests
|
Backing "mini pump" testing.
-Open gas lines & auto ramp (If using HV, close up the back)
-HV on |
Friday, March 01, 2019, 14:51, Aaron Schmidt, , LP-FEBIAD, , , , , , Gas lines test & Emissions measurement prep   
|
Friday, March 01, 2019, 14:50:
SV5 replaced with a new valve.
SV1 disconnected from the He line and linked to the mini pump line. |
Thursday, March 21, 2019, 08:33, Aaron Schmidt, , , , , , , , Pump down TS
|
Thursday, March 21, 2019, 08:32: Roughing. |
Wednesday, May 22, 2019, 13:47, Aaron Schmidt, , , , , , , , Calibrated Masscorr
|
Wednesday, May 22, 2019, 13:44: Calibration Confirmed.
New Masscorr setup:
|
Friday, June 07, 2019, 16:56, Carla Babcock, , , , , , , , TM4 source tray state
|
TM4 source tray left in test stand over weekend, just the rouging pumps on. Ready to be removed Monday morning.
Monday, June 10, 2019, 06:35: Venting - Aaron S. |
Friday, June 21, 2019, 15:12, Aaron Schmidt, P2N - 1, , , , , , , P2N - 1 - 2019
|
Friday, June 21, 2019, 14:48: Roughing.
Friday, June 21, 2019, 15:18: Turbo pumps on.
Friday, June 21, 2019, 15:31: IG1 on. |
Thursday, July 04, 2019, 15:15, Aaron Schmidt, P2N - 1, , , , , , , P2N - 1 - 2 - 2019
|
Screws instead of rivets on target leg. Insulator changed.
Thursday, July 04, 2019, 15:14: Roughing
Thursday, July 04, 2019, 16:00: Turbos on. |
Tuesday, July 16, 2019, 10:28, Fernando Maldonado, P2N, , , , , , , P2N 1200 A test
|
Tuesday, July 16, 2019, 10:27: The idea of this run is to have the full 600 A from TGHT and the full 600 A from TBHT.
This will done based on the rewiring done previously (see entry 745)
Tuesday, July 16, 2019, 12:16: Jumper cable F-H burning while target was at 600 A total. Ramp up aborted and auto-cooling started to remove the |
Friday, September 27, 2019, 11:54, Aaron Schmidt, , LP-SIS, , , 41790-9, 43515-6, , Conditioning UC#(29) HS
|
Using broken LP-FEBIAD oven. TBHT off.
Friday, September 27, 2019, 11:53: Roughing.
Friday, September 27, 2019, 13:14: Turbo pumps on. |
Friday, November 15, 2019, 10:35, Aaron Schmidt, , , , , , , , Pump down empty Chamber
|
Friday, November 15, 2019, 09:35: Roughing.
Friday, November 15, 2019, 10:34: Turbo pumps on.
Wednesday, November 20, 2019, 09:19: Turbo pumps off. Ion gauge off. |
Friday, November 22, 2019, 19:06, Fernando Maldonado, Ferran Boix Pamies, , , , , , , , PEEK seal tests
|
Friday, November 22, 2019, 19:02: The new design for the PEEK irradiation will be tested.
Blinds were removed and a new LP-SIS assembly with a modify heatshield was installed. Three termocuples installed.
Friday, November 22, 2019, 19:04: Roughing |
Friday, December 20, 2019, 07:59, Aaron Schmidt, , , , , , , , Holiday TS shut down
|
Friday, December 20, 2019, 07:58: Turn off ion gauges. Shut off turbo pumps TP6, TP2, TP1A, & TP1B. Close backing valves.
Friday, December 20, 2019, 08:06: PV1 & PV2 off. RP1 & RP2 off.
Monday, January 06, 2020, 09:35: Restarting TS. RP1 & RP2 on. (BIAS PS upgraded / Note: https://elog.triumf.ca/TIS/Test-Stand/776 ). |
|