Message ID: 746     Entry time: Tuesday, July 16, 2019, 10:28
Author: Fernando Maldonado 
Target/No.#: P2N 
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status:  
Subject: P2N 1200 A test 

Tuesday, July 16, 2019, 10:27: The idea of this run is to have the full 600 A from TGHT and the full 600 A from TBHT.

This will done based on the rewiring done previously (see entry 745)

Tuesday, July 16, 2019, 12:16: Jumper cable F-H burning while target was at 600 A total. Ramp up aborted and auto-cooling started to remove the jumper.

Jumper removed.

TBHT cables on both positive coil FT.

Jumper E-G removed.

High current cable connecting F-H.

Tuesday, July 16, 2019, 16:49

Current ramped up to 300A + 300A on TGHT and TBHT in parallel, for an equivalent of 600A on the target. No burn to anything noticed, PS ramping nicely together. Stopped ramping up and started ramp down for the night.