ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O#down Status Subject Text Attachments
  783   Tuesday, February 11, 2020, 14:27 Aaron Schmidt       Pump down empty ChamberTuesday, February 11, 2020, 14:27: UC#32
HS removed.
Tuesday, February 11, 2020, 14:27:
  
  786   Thursday, February 27, 2020, 07:20 Aaron Schmidt       FS#3 - Fitting change outThursday, February 27, 2020, 07:10: Swapped
out an old brass fitting on the supply line
going into FS#3 - Line K. 
  
  788   Wednesday, March 04, 2020, 17:15 Fernando Maldonado      Problems/SolutionsEmittance rig communicationWednesday, March 04, 2020, 17:13: EPICS
page indicated a sucesful scan but data was
empty.
  
  791   Friday, March 27, 2020, 11:30 Aaron Schmidt       Vacuum loss / spike / ShutdownThe ISAC was left with the turbo pumps
and water supplies running. Just the power
supplies off. Monday, March, 23, 2020.
 Mar_27_-_2020_-_Vacuum_Trip.docx 
  792   Tuesday, April 07, 2020, 10:53 Anders Mjos       Vacuum loss / spike / Shutdown


   
        
            
  
  802   Wednesday, July 22, 2020, 08:56 Luca Egoriti P2N testHP-SISITETM4  In progressp2n heating test - electrical feedthrough configuration The electrical feedthroughs at the
top of the test stand module were reconfigured
to deliver up to 1200A to the p2n target.
 ISACteststand_TMwiring.pptxP2N-TestStand_20200722.pngP2N-TestStand_1200A.png 
  803   Tuesday, July 28, 2020, 13:27 Aaron Schmidt      Problems/SolutionsWater leak on magnet PS Fault: 13334
  
  805   Wednesday, August 05, 2020, 10:01 Aaron Schmidt      Problems/SolutionsRoughing pump swap out.Wednesday, August 05, 2020, 10:00: TP6
& TP2 off. IG6 off.
Wednesday, August 05, 2020, 12:20:
  
  807   Tuesday, August 18, 2020, 10:00 Aaron Schmidt       IDP15 Scroll pump installed - RP1 replacedPN: X3815-64000
SN: MY2005SA02
Description: IDP15 Scroll pump, Std.
  
  809   Wednesday, August 19, 2020, 08:52 Aaron Schmidt       Leak check / TroubleshootWednesday, August 19, 2020, 08:52: Purging
all lines, except FS#5, It was already purged
/ closed.
 Aug_19_-_2020_Leak_Check..docx 
  810   Tuesday, August 25, 2020, 07:23 Aaron Schmidt      Problems/SolutionsBeam line side vacuum tripTuesday, August 25, 2020, 07:07: Beam line
side of the TS appears to have tripped? Open
BV6 & BV2.
  
  811   Tuesday, September 01, 2020, 14:01 Aaron Schmidt      DoneNew tubing installed on loopsTuesday, September 01, 2020, 14:00: 
New tubing installed.
Blue on FS#4 loop (A)(B)
  
  813   Tuesday, September 29, 2020, 11:56 Aaron Schmidt LP-SIS    Problems/SolutionsLeak check 3.0Installed Indium gasket on FS#2 - (C) water
block / R- TGHT.
Tuesday, September 29, 2020, 11:23:
  
  818   Monday, November 02, 2020, 08:52 Aaron Schmidt      Problems/SolutionsLeak check / TroubleshootMonday, November 02, 2020, 08:46:
Large Vacuum spike noted 5:30 approx.
Tripped TS. On tail end of the Nb#9 conditioning
 Nov-2-2020_Leak.docx 
  821   Monday, November 23, 2020, 10:03 Aaron Schmidt      Problems/SolutionsRP2 Check / pump down issueTMSRP2 has been struggling since the power
bump occurred Nov 18, 2020
Monday, November 23, 2020, 09:48:
 20201123_114110.jpg20201123_120204.jpg20201123_120208.jpg20201123_131124.jpg20201123_131127.jpg 
  822   Tuesday, December 01, 2020, 11:56 Carla Babcock      In progressModifications to test stand for TM3 testsTuesday, December 01, 2020, 11:56 :
TSG:BIAS unplugged and controls pigtail
(made by Ray) added in order to connect controls
  
  823   Tuesday, December 01, 2020, 17:04 Carla Babcock      Problems/SolutionsFound another burned jumper cableBetween feedthroughs F (magnet coil) and
B (tube heater negative), I found a jumper
with two resistors that has been burned up.
 20201201_115557.jpg 
  824   Wednesday, December 02, 2020, 08:32 Carla Babcock       Modifications to test stand for TM3 testsWednesday, December 02, 2020, 08:31 :
Added copper wire connection to multipin
screw terminals in HV cage to make sure they
  
  825   Wednesday, December 02, 2020, 16:18 Fernando Maldonado      DoneGas delivery system upgradeYesterday, December 1st, I successfully
installed and tested the gas system inside
the faraday cage.
  
  826   Thursday, December 03, 2020, 15:55 Carla Babcock, Alexander Shkuratoff       Modifications to ISAC test stand for TM3 testsThursday, December 03, 2020, 15:54 :
Got sign off from John Chow to run
the system, though the nylon insulator was
 20201203_150458.jpg20201203_173725.jpg 