Tuesday, February 11, 2020, 14:27, Aaron Schmidt, , , , , , , , Pump down empty Chamber
|
Tuesday, February 11, 2020, 14:27: UC#32 HS removed.
Tuesday, February 11, 2020, 14:27: Roughing.
Wednesday, February 12, 2020, 09:05: Venting. |
Thursday, February 27, 2020, 07:20, Aaron Schmidt, , , , , , , , FS#3 - Fitting change out
|
Thursday, February 27, 2020, 07:10: Swapped out an old brass fitting on the supply line going into FS#3 - Line K.
Replaced w/ SS fitting for interchangeability w/ other lines in case a bypass is needed. |
Wednesday, March 04, 2020, 17:15, Fernando Maldonado, , , , , , , Problems/Solutions, Emittance rig communication
|
Wednesday, March 04, 2020, 17:13: EPICS page indicated a sucesful scan but data was empty.
Wednesday, March 04, 2020, 17:13: Power suppply didn't respond to the voltage sweep
Wednesday, March 04, 2020, 17:14: Problem most likely similar to elog entry 531. |
Friday, March 27, 2020, 11:30, Aaron Schmidt, , , , , , , , Vacuum loss / spike / Shutdown
|
The ISAC was left with the turbo pumps and water supplies running. Just the power supplies off. Monday, March, 23, 2020.
Check daily
Thursday, March 26, 2020, 13:25: Vacuum ok at 3.2e-07T. All status ok. |
Tuesday, April 07, 2020, 10:53, Anders Mjos, , , , , , , , Vacuum loss / spike / Shutdown
|
Aaron Schmidt wrote:
The ISAC was left with the turbo pumps and water supplies running. Just the power supplies off. Monday, |
Wednesday, July 22, 2020, 08:56, Luca Egoriti, P2N test, HP-SIS, ITE, TM4, , , In progress, p2n heating test - electrical feedthrough configuration
|
The electrical feedthroughs at the top of the test stand module were reconfigured to deliver up to 1200A to the p2n target.
1) The two COIL lines (one + and one -) were disconnected from their terminals E and F
2) The TBHT terminals (two + and two -) were disconnected from A and B |
Tuesday, July 28, 2020, 13:27, Aaron Schmidt, , , , , , , Problems/Solutions, Water leak on magnet PS
|
Fault: 13334
Tuesday, July 28, 2020, 12:00: Leak discovered in ISAC Test Stand MB1 PS. Appears
to be coming from hose barb soldered connection to heat sink of pass bank. Pass bank will need to be disassembled and heat sink soldered on a workbench. |
Wednesday, August 05, 2020, 10:01, Aaron Schmidt, , , , , , , Problems/Solutions, Roughing pump swap out.
|
Wednesday, August 05, 2020, 10:00: TP6 & TP2 off. IG6 off.
Wednesday, August 05, 2020, 12:20: RP2 swapped with a smaller roughing pump from the hot lab.
Wednesday, August 05, 2020, 12:25: Roughing. |
Tuesday, August 18, 2020, 10:00, Aaron Schmidt, , , , , , , , IDP15 Scroll pump installed - RP1 replaced
|
PN: X3815-64000
SN: MY2005SA02
Description: IDP15 Scroll pump, Std. |
Wednesday, August 19, 2020, 08:52, Aaron Schmidt, , , , , , , , Leak check / Troubleshoot
|
Wednesday, August 19, 2020, 08:52: Purging all lines, except FS#5, It was already purged / closed.
Wednesday, August 19, 2020, 11:24: Vacuum @ 1.76e-06T.
Wednesday, August 19, 2020, 11:29: FS#2 opened. Observable vacuum spike noted. vacuum @ 2.2e-06T. Purge & Close. |
Tuesday, August 25, 2020, 07:23, Aaron Schmidt, , , , , , , Problems/Solutions, Beam line side vacuum trip
|
Tuesday, August 25, 2020, 07:07: Beam line side of the TS appears to have tripped? Open BV6 & BV2.
Tuesday, August 25, 2020, 07:15: Beam line side TP6 & TP2 on.
Tuesday, August 25, 2020, 07:16: Venting Chamber side |
Tuesday, September 01, 2020, 14:01, Aaron Schmidt, , , , , , , Done, New tubing installed on loops
|
Tuesday, September 01, 2020, 14:00:
New tubing installed.
Blue on FS#4 loop (A)(B) |
Tuesday, September 29, 2020, 11:56, Aaron Schmidt, , LP-SIS, , , , , Problems/Solutions, Leak check 3.0
|
Installed Indium gasket on FS#2 - (C) water block / R- TGHT.
Tuesday, September 29, 2020, 11:23: Pressurize to 120 PSI at atmosphere.
LD: 0.0E-07 atm-CC/sec |
Monday, November 02, 2020, 08:52, Aaron Schmidt, , , , , , , Problems/Solutions, Leak check / Troubleshoot
|
Monday, November 02, 2020, 08:46:
Large Vacuum spike noted 5:30 approx. Tripped TS. On tail end of the Nb#9 conditioning run. HV & heating were completed last week
Monday, November 02, 2020, 08:47: Vacuum @ 2.66e-06T. |
Monday, November 23, 2020, 10:03, Aaron Schmidt, , , , , , , Problems/Solutions, RP2 Check / pump down issue
|
TMSRP2 has been struggling since the power bump occurred Nov 18, 2020
Monday, November 23, 2020, 09:48: Open TMS:PV2.
Monday, November 23, 2020, 09:51: Close TMS:PV2. CG2B @ 0.515T. |
Tuesday, December 01, 2020, 11:56, Carla Babcock, , , , , , , In progress, Modifications to test stand for TM3 tests
|
Tuesday, December 01, 2020, 11:56 :
TSG:BIAS unplugged and controls pigtail (made by Ray) added in order to connect controls cable to TCS:BIAS, which is now installed in the same
rack. |
Tuesday, December 01, 2020, 17:04, Carla Babcock, , , , , , , Problems/Solutions, Found another burned jumper cable
|
Between feedthroughs F (magnet coil) and B (tube heater negative), I found a jumper with two resistors that has been burned up. I am not sure when this
happened, but it would be good to review the overall setup of the service cap wiring in the new year.
The cable connected to feedthrough Q where the multipin sits also looks burned. |
Wednesday, December 02, 2020, 08:32, Carla Babcock, , , , , , , , Modifications to test stand for TM3 tests
|
Wednesday, December 02, 2020, 08:31 :
Added copper wire connection to multipin screw terminals in HV cage to make sure they are grounded.
Attached grounding rod to back of HV cage. Not ideal, but couldn't find a better place without making a extension to the cable. Will see what John |
Wednesday, December 02, 2020, 16:18, Fernando Maldonado, , , , , , , Done, Gas delivery system upgrade
|
Yesterday, December 1st, I successfully installed and tested the gas system inside the faraday cage.
The changes performed were as follows:
Remove He gas tank (to make room for new tank)
Remove calibrated leak to connect new gas line
Remove convectron |
Thursday, December 03, 2020, 15:55, Carla Babcock, Alexander Shkuratoff, , , , , , , , Modifications to ISAC test stand for TM3 tests
|
Thursday, December 03, 2020, 15:54 :
Got sign off from John Chow to run the system, though the nylon insulator was not ready when he came by. But we went over everything together.
Installed blue nylon insulator with all vacuum surfaces cleaned at least with methanol. No NPT fitting or tube installed, just testing service |
|