ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
Text |
|
963
|
Wednesday, April 26, 2023, 08:46 |
Aaron Schmidt | TiC#5 | LP-FEBIAD | ITE | TM4 | 44692-6 | 45235-20 | | Testing TiC#5 assembly w/ an empty target | Anode remade with a ceramic "elbow-cube".
Empty target oven in use for testing.
Wednesday, April 26, 2023, 08:44: |
|
964
|
Monday, May 01, 2023, 14:31 |
Aaron Schmidt | TiC#5 | LP-FEBIAD | ITE | TM4 | 44692-5 | 45235-20 | In progress | Conditioning TiC#5 | New TiC LP-FEBIAD Target installed.
Monday, May 01, 2023, 14:23: Roughing.
Monday, May 01, 2023, 21:42: TP1B |
|
367
|
Friday, March 28, 2014, 10:39 |
Anders Mjos | TiC#4 | HP-SIS | ITE | TM3 | | | In progress | Conditioning TiC#4 | NOTE:
TBHT Power Supply is 600A. EPICS thinks |
|
368
|
Tuesday, April 01, 2014, 11:09 |
Aurelia Laxdal | TiC#4 | HP-SIS | ITE | TM3 | | | In progress | HV and Heaters Conditioning | Started March 31, 2014:
- did the HV conditioning up to 30kV.
April 1, 2014: |
|
369
|
Thursday, April 03, 2014, 16:46 |
Aurelia Laxdal | TiC#4 | HP-SIS | ITE | TM3 | | | Done | HV and Heaters Conditioning | HV and Heaters Conditioning had finished.
The target was cooled down and it's ready
for the on-line installation. |
|
370
|
Friday, April 04, 2014, 08:24 |
Anders Mjos | TiC#4 | HP-SIS | ITE | TM3 | | | In progress | Venting |
|
|
223
|
Thursday, October 25, 2012, 13:02 |
Anders Mjos | TiC#3 | LP-SIS | ITW | TM1 | | | In progress | Pumping down | Thursday, October 25, 2012, 13:00: Roughing
Thursday, October 25, 2012, 13:19
: Turbos on |
|
224
|
Friday, October 26, 2012, 08:29 |
Anders Mjos | TiC#3 | LP-SIS | ITW | TM1 | | | Done | Target ready for conditioning |
|
|
225
|
Thursday, November 01, 2012, 11:16 |
Aurelia Laxdal | TiC#3 | LP-SIS | ITW | TM1 | | | | TiC#3-LP-SIS Startup | Did the HV conditioning for the TiC#3 up
to 30kV.
Heaters ramp up in progress. |
|
226
|
Thursday, November 01, 2012, 14:57 |
Aurelia Laxdal | TiC#3 | LP-SIS | ITW | TM1 | | | | TSH:TGHT readback stopped at 264.5A (for a higher setpoint) | The TSH:TGHT stopped at 263.7A, but the
setpoint is still ramping (now at 421A).
The voltage is set correctly: have 6.238V |
|
231
|
Monday, November 05, 2012, 14:41 |
Anders Mjos | TiC#3 | LP-SIS | ITW | TM1 | | | Done | Target Removed | Target looks OK. The right leg was a bit
much out of center and will be adjusted in
the lab. |
|
1016
|
Wednesday, July 31, 2024, 18:50 |
Aaron Schmidt | TiC Spare | HP-FEBIAD | ITW | TM4 | 45447-2 | 42752-7 | In progress | Conditioning Spare for TiC#7 | Wednesday, July 31, 2024, 18:47: Roughing.
Wednesday, July 31, 2024, 19:24:
TP1B on. |
|
1021
|
Tuesday, September 10, 2024, 16:24 |
Dave Neilson | TiC #24D | HP-SIS | ITW | TM3 | 45447-27 | 45235-25 | | Back up target testing and conditioning | Tuesday, September 10, 2024, 16:21:
Target installed in test stand by Brady
Tuesday, September 10, 2024, 16:21: |
|
404
|
Thursday, September 25, 2014, 15:44 |
Anders Mjos | ThO#1 | | ITW | TM1 | 40282-5 | | Done | ThO#1 Heat Shield Conditioning | Thursday, September 25, 2014, 15:44: Roughing
Thursday, September 25, 2014, 16:06:
Starting turbos |
|
233
|
Monday, November 19, 2012, 10:20 |
Aurelia Laxdal | Test-SiC | HP-FEBIAD | | | | | | Preparations for E-Fault#6389 investigations | Prepared the Test Stand for Controls to
investigate E-Fault#6389.
|
|
234
|
Thursday, November 22, 2012, 12:52 |
Aurelia Laxdal | Test-SiC | HP-FEBIAD | | | | | | E-Fault#6389 re-directed to PS | Evgeniy and Kazuya investigated the problem
with TSH:TGHT readbacks and they came to
the conclusion that the PS is faulty, and |
|
2
|
Wednesday, September 14, 2011, 15:33 |
John Wong | Test#1 | HP-SIS | ITW | TM1 | test | test | In progress | testing elog for test stand | Wednesday, September 14, 2011, 15:33
blah blah blah... |
|
466
|
Wednesday, September 30, 2015, 16:28 |
Anders Mjos | Test Target wrapped with heat shields | LP-SIS | | | | | In progress | New centre block test |
|
|
464
|
Thursday, September 17, 2015, 14:05 |
Anders Mjos | Test Target | LP-SIS | | | | | In progress | New centre block test |
|
|
738
|
Wednesday, June 26, 2019, 11:34 |
Aaron Schmidt | Test Ta | HP-SIS | | TM4 | No Target oven # | 42972-4 | In progress | Test target for TM4 checks | The HP-SIS uses the older center block.
No serial number found.
Loaded with Tantalum. Rough Target |
|