Started March 31, 2014:
- did the HV conditioning up to 30kV.
April 1, 2014:
- started the Heaters Conditioning.
Heaters Conditioning finished.
The Power Supplies front panel:
TGHT: 5.56V and 580A
TBHT: 2.23V and 227A
April 2, 2014:
- did a mass scan. NOTE: data is shifted by 10-15%.
plotdump-local-clean.txt_Apr2_14_16-33-19.txt
After the scan finished I found the Test Stand EPICS screens whited-out. Decided with Friedhelm to leave it as it was for the night and to contact Controls next day to reboot it without tripping the heaters and the HV.
April 3, 2014:
Found everything recovered. Except: “SOURCES ARCH IS RUNNING” was red. So, I restarted it. Jane Richards and Friedhelm didn’t do any IOC reboot. Also found that the data from yesterday’s scan was saved (see the previous scan).
Did another mass scan: plotdump-local-clean.txt_Apr3_14_10-18-13.txt
NOTE: data is shifted by 10-15%.
Cooling down .
|