Entry  Monday, November 27, 2023, 16:09, Ferran Boix Pamies, , LP-SIS, , , 45220-2, 45235-13, In progress, HV power surge test plus mass scans 
Monday, November 27, 2023, 16:09  Roughing
Monday, November 27, 2023, 17:22 Both turbos are on, leaving vacuum over night.
Tuesday, November 28, 2023, 09:28  after pumping over night IG1 is at .15e-6 T. Water cooling on.
Entry  Friday, December 12, 2014, 13:11, Anders Mjos, , , , , , , Problems/Solutions, HV inspection and cleaning 
by Ray D and Anders in preparation for 60kV test. Rack insulators and f/t insulators cleaned with windex
Entry  Friday, December 12, 2014, 13:11, Anders Mjos, , , , , , , Problems/Solutions, HV inspection and cleaning 
by Ray D and Anders in preparation for 60kV test. Rack insulators and f/t insulators cleaned with windex
Entry  Wednesday, March 07, 2012, 10:36, Paul Mocock, , , , , , , , HV conditioning begins. 
HV conditioning has begins. Vacuum chamber pressure is currently 3.2e-07 Torr on TSG:IG1.
Entry  Monday, August 27, 2012, 13:21, Aurelia Laxdal, NiO#1, HP-FEBIAD, ITE, TM4, , , In progress, HV conditioning at Test Stand  
Did HV conditioning up to TSG:BIAS=30kV, TSH=EE=-600V
Turned off the HV for Kazuya to check the connection/output of the TSG:TGHT Xantrex power supply.
Entry  Friday, September 16, 2011, 12:39, Aurelia Laxdal, TaC#1, LP-SIS, ITE, TM1, 38634-6, 36833-6, In progress, HV conditioning 
Started the HV conditioning: TSG:BIAS=30kV and TSH:EE=-700V.
Entry  Wednesday, September 28, 2011, 16:33, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, HV conditioning 
Started the HV conditioning: TSG:BIAS=30kV
Entry  Tuesday, April 01, 2014, 11:09, Aurelia Laxdal, TiC#4, HP-SIS, ITE, TM3, , , In progress, HV and Heaters Conditioning  ITE-TM3-TiC#4-HP-SIS_Test_Stand_Conditioning.docx
Started March 31, 2014: 
- did the HV conditioning up to 30kV.
April 1, 2014: 
Entry  Thursday, April 03, 2014, 16:46, Aurelia Laxdal, TiC#4, HP-SIS, ITE, TM3, , , Done, HV and Heaters Conditioning ITE-TM3-TiC#4-HP-SIS_Test_Stand_Conditioning.docx
HV and Heaters Conditioning had finished. The target was cooled down and it's ready for the on-line installation.
Entry  Monday, March 12, 2018, 10:07, Aaron Schmidt, , , , , , , , HV Test w-gas 
Monday, March 12, 2018, 09:45: Gas lines opened. Leak rate set. Vacuum @ 1.16e-06T
Monday, March 12, 2018, 10:00: RGA on
Monday, March 12, 2018, 10:07: RGA off. Manually shut off power as well
Entry  Wednesday, February 28, 2018, 11:50, Aaron Schmidt, , , , , , , , HV Test Np 2018_HV_test_Np.docx
New parts installed. Corona Shield, brackets, and board/spark gap orientation.
Wednesday, February 28, 2018, 11:48: Power on. Ready to test
Wednesday, February 28, 2018, 14:00: BIAS / EZL / EE @ 30 / 13 / 1.5 kV
Entry  Friday, December 12, 2014, 14:09, Anders Mjos, , LP-FEBIAD, , , Tube only, , In progress, HV BIAS Test 2014-12-17_60_kV_3h.png60_kV_Test.docx
BIAS current limit pot changed from 2.40 to 0.25
EZL current limit pot changed from 0.50 to 0.20
Testing max HV bias with Ray
Entry  Wednesday, January 21, 2015, 13:40, Anders Mjos, , , , , , , In progress, HV BIAS Test 
Wednesday, January 21, 2015, 13:34: Opened water flow.
Wednesday, January 21, 2015, 13:42: 30 / 15 kV (BIAS / EZL)
Wednesday, January 21, 2015, 13:4: 40 / 20 kV
Entry  Friday, June 01, 2012, 12:23, Aurelia Laxdal, Ta#38, LP-SIS, ITW, TM1, , , In progress, HV & Heaters conditioning. 
Did the HV conditioning.
Heaters conditioning in progress.
The Hall probe is not working: couldn't pass 35.5 units (readback) or 50.16 units (setpoint) at field -3710G.
Entry  Monday, August 15, 2016, 08:09, Aaron Schmidt, , , , , 41882-4, 41751-4, , HS Test OR Clean HS_41751-4_TEST.docxTS-2016-08-15-11-45.rga20160824_143550.jpg
Heat Shield Test (OR Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
Entry  Wednesday, August 17, 2016, 08:19, Aaron Schmidt, , , , , 41882-4, 41751-5, , HS Test OR Clean HS_41751-5_TEST.docxTS-2016-08-17-11-45.rga20160824_143555.jpg20160824_143558.jpg
Heat Shield Test (OR Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
Entry  Wednesday, August 24, 2016, 09:16, Aaron Schmidt, , , , , 41882-4, 41751-6, , HS Test OR Clean 7x
Heat Shield Test (OR only).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
Entry  Monday, August 08, 2016, 09:48, Aaron Schmidt, , , , , 41882-4, 41751-1, , HS Test Full Clean HS_41751-1_TEST.docxTS-2016-08-08-11-45.rga20160824_144103.jpg20160824_144106.jpg
Heat Shield Test (Fully Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
Entry  Wednesday, August 10, 2016, 08:09, Aaron Schmidt, , , , , 41882-4, 41751-2, , HS Test Full Clean HS_41751-2_TEST.docxTS-2016-08-10-11-45.rga20160824_143539.jpg
Heat Shield Test (Fully Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.
Entry  Monday, August 22, 2016, 08:20, Aaron Schmidt, , , , , 41882-4, 41751-3, , HS Test Full Clean HS_41751-3_TEST.docxTS-2016-08-22-11-50.rga20160824_143544.jpg
Heat Shield Test (Fully Cleaned).
For all 6 tests:
-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.