  Test-Stand  Not logged in ELOG logo
Message ID: 530     Entry time: Wednesday, August 10, 2016, 08:09
Author: Aaron Schmidt 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#: 41882-4 
Heat Shield W.O#: 41751-2 
Status:  
Subject: HS Test Full Clean 

Heat Shield Test (Fully Cleaned).

For all 6 tests:

-Start Turbo pumps & Ion gauge as soon as available on ISAC TEST STAND VACUUM Screen.

-Start Roughing by 10:10am +/- 1 minute and ensure previous HS started venting by 9:15am to meet timeline.


HS# 41751-2 . OR, Acetone, Methanol. TGHT only.

No insulators, bracket, or gripper arms. Blank/Plate. No source cup.

Wednesday, August 10, 2016, 09:47: 41751-1 removed from test stand. Exchange target & End plates to 41751-2

Wednesday, August 10, 2016, 10:07: 41751-2 placed into test stand. Door open for 20 minutes.

Wednesday, August 10, 2016, 10:10: Roughing.

Wednesday, August 10, 2016, 10:13: Doors finally sealed for roughing.

Wednesday, August 10, 2016, 10:23: BV1B OPEN. Opened @ 59T.

Wednesday, August 10, 2016, 10:45: Both Turbo pumps started.

Wednesday, August 10, 2016, 10:50: Ion gauge on. TP1B @ speed 42 KRPM.

Wednesday, August 10, 2016, 10:53: TP1A @ speed 38 KRPM

Wednesday, August 10, 2016, 11:45: RGA on. Vacuum @ 3.56E-6T


Thursday, August 11, 2016, 08:16: Water lines opened. No response on RGA. Vacuum stable @ 2.34E-7T

Thursday, August 11, 2016, 08:19: Power/sources on

Thursday, August 11, 2016, 08:30: TGHT auto-ramping to 580A @ 2A/min. Vacuum stable @ 2.36E-7T

Thursday, August 11, 2016, 11:15: Screen shots and check made @ 329-330A.

Thursday, August 11, 2016, 13:25: TGHT @ 580A. Vacuum @4.16E-7T

Thursday, August 11, 2016, 15:54: Screen shots and check made @ 580A. Vacuum @4.43E-7T and increasing. Cool in Am.


Friday, August 12, 2016, 08:30: Auto-cooling started @ 2A/min. Vacuum @ 3.88E-7T

Friday, August 12, 2016, 13:20: Cooling Complete. Vacuum @ 2.16E-7T.

Friday, August 12, 2016, 13:33: Water lines purged. Power/sources off.


Monday, August 15, 2016, 08:07: Turbo pumps, Ion gauge, and RGA off.

Monday, August 15, 2016, 09:14: Venting.

Attachment 1: HS_41751-2_TEST.docx  1.787 MB  Uploaded Tuesday, August 16, 2016, 17:04
Attachment 2: TS-2016-08-10-11-45.rga  3.532 MB  Uploaded Tuesday, August 16, 2016, 17:04
Attachment 3: 20160824_143539.jpg  1.038 MB  Uploaded Wednesday, August 24, 2016, 16:18  | Show | Hide all