582
|
Friday, May 05, 2017, 14:28 |
Aaron Schmidt | UC#20 | LP-IG-LIS | | | | | | Conditioning Heat shield for UC#20 (2) | New O-rings installed on FS#3.
Friday, May 05, 2017, 14:24: Roughing.
Friday, May 05, 2017, 14:34: Waterlines |
|
583
|
Wednesday, May 10, 2017, 15:07 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. (FS#3 out) | FS#3 lines blanked off.
Wednesday, May 10, 2017, 14:40: Roughing
Wednesday, May 10, 2017, 15:05: Turbos |
|
584
|
Tuesday, May 16, 2017, 14:25 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | | | | Tri-Coil CTL-FEBIAD test III | Coil loose (Remove lid, Tighten and place
lid again)
Tuesday, May 16, 2017, 14:24: Roughing. |
8x |
585
|
Wednesday, May 17, 2017, 10:17 |
Anders Mjos | | HP-FEBIAD-CTL | | | | | Problems/Solutions | Sparking between new coil line and ground electrode | Wednesday, May 17, 2017, 10:17: Sparking
around 20 kV. Will need to vent to increase
gap between water lines. |
|
586
|
Monday, May 22, 2017, 09:43 |
Aaron Schmidt | | HP-FEBIAD-CTL | | | | | | Tri-Coil CTL-FEBIAD test IV | Monday, May 22, 2017, 09:41: Roughing.
Monday, May 22, 2017, 10:00: Turbo
pumps started. |
|
587
|
Wednesday, May 24, 2017, 11:12 |
Anders Mjos | | | | | | | Problems/Solutions | FEBIAD Anode bias configuration | The Test Stand has been configured
for Anode bias. John Chow changed the power
supply and the electrical connections have |
|
589
|
Saturday, June 03, 2017, 09:34 |
Anders Mjos | | | | | | | Problems/Solutions | FEBIAD Cathode bias configuration |
|
|
590
|
Tuesday, June 06, 2017, 09:22 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Tuesday, June 06, 2017, 09:21: roughing.
Friday, June 09, 2017, 08:50:
Ion gauge off. Turbo pumps off. |
|
591
|
Wednesday, June 07, 2017, 12:49 |
Aaron Schmidt | | | | | | | | Gas bottles | Gas bottles for FEBIAD testing were
exchanged yesterday around 1:30. One Neon
& one Argon bottle were removed. |
|
593
|
Friday, June 16, 2017, 11:23 |
Aaron Schmidt | | | | | | | | Pump down empty chamber. | Friday, June 16, 2017, 11:22: roughing.
Friday, June 16, 2017, 14:28: Turbo
pumps on |
|
595
|
Thursday, July 06, 2017, 13:16 |
Aaron Schmidt | Ta#55 | LP-SIS | | | 42218-11 | 42738-2 | In progress | Conditioning Ta spare for Ta#52 | Thursday, July 06, 2017, 13:56: Roughing.
Thursday, July 06, 2017, 14:25: Turbo
pumps started. |
10x |
597
|
Monday, July 17, 2017, 09:55 |
Aaron Schmidt | | | | | 41882-4 | 42738-1 | In progress | Out Gas HS for Target Cleaning Test | -No EE. Insulators, gripper arms,
and blank EE plate included |
|
598
|
Monday, July 17, 2017, 09:58 |
Aaron Schmidt | | HP-SIS | | | 42218-8 | 42738-1 | | Target cleaning test (Long) HP-SIS CC Clean | |
|
599
|
Monday, July 17, 2017, 10:04 |
Aaron Schmidt | | HP-SIS | | | 42218-10 | 42738-1 | | Target cleaning test HP-SIS Full Clean | |
|
600
|
Wednesday, July 19, 2017, 09:13 |
Aaron Schmidt | Ta Targets | | | | | | Done | Ion Peaks | Attached is a recent list of Ta targets
with their extracted ions peaks. |
|
601
|
Thursday, August 03, 2017, 17:00 |
Anders Mjos | | | | | | | Problems/Solutions | Vacuum system tripped on power interruption | Thursday, August 03, 2017, 17:00:
Restarted TPs |
|
602
|
Tuesday, August 15, 2017, 08:41 |
Aaron Schmidt | Ta#55 | LP-SIS | | | 42218-11 | 42738-2 | In progress | TBHT sight in test | Heat TGHT to 580 A & TGHT to
200 A for view port test.
Tuesday, August 15, 2017, 08:40: |
|
603
|
Thursday, August 17, 2017, 12:45 |
Anders Mjos | | | | | | | Problems/Solutions | TBHT power supply removed | The Xantrex 10V 600 A power supply
for the TBHT has been moved to ITE to replace
the failed TGHT power supply |
|
604
|
Monday, August 21, 2017, 16:20 |
Anders Mjos | | | | | | | Problems/Solutions | TBHT power supply removed |
|
|
606
|
Monday, September 25, 2017, 14:10 |
Aaron Schmidt | | | | | | | | Pump down empty chamber | Monday, September 25, 2017, 14:10: Roughing.
Wednesday, September 27,
2017, 08:23: Turbo pumps on |
|
|