Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 29 of 53  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subjectdown Text Attachments
  448   Wednesday, June 03, 2015, 09:35 Anders Mjos      Problems/SolutionsPLC upgradeWednesday, June 03, 2015, 09:35: TP6 and
TP2 off
Wednesday, June 03, 2015, 10:15:
  
  427   Friday, February 13, 2015, 13:59 Anders Mjos      Problems/SolutionsPLC failureThe PLC CPU came out of the socket around
11:50am today (Dave Morris). The CPU had
not been properly attached. This resulted
  
  772   Friday, November 22, 2019, 19:06 Fernando Maldonado, Ferran Boix Pamies       PEEK seal tests Friday, November 22, 2019, 19:02:
The new design for the PEEK irradiation will
be tested.
  
  872   Wednesday, April 28, 2021, 22:34 Luca EgoritiP2N test - Apr 2021P2N-SISITETM4  In progressP2N heating test Wednesday, April 28, 2021, 22:30
First P2N heating test ongoing.
At P2NHT ~ 570 A and TBHT ~ 100 A
 Target_580A_100A_glowing.jpgInitial_rampup.PNG 
  924   Monday, May 09, 2022, 10:08 Luca Egoriti P2N-SISITETM4  In progressP2N heating testBeginning of May:
The cabling on the top of the test
stand was changed to adapt for P2N testing.
 2022-05-09_-_Voltage_event_during_rampup.PNG2022-05-09_-_Rampup_and_down.PNGIMG_20220509_111314.jpgITS_short_plasma_electrode_schematics.png 
  923   Thursday, May 05, 2022, 14:43 Aaron Schmidt P2N-SIS  45241-145240-1In progressP2N assembly conditioning.Thursday, May 05, 2022, 14:43: Roughing.
Open BV1B
Thursday, May 05, 2022, 14:46: Upper
  
  927   Thursday, May 12, 2022, 10:50 Aaron Schmidt P2N-SISITETM444812-245240-1In progressP2N assembly conditioning - 4PE shimmed & extended 1mm due to likely
ion source contact.
Thursday, May 12, 2022, 10:41: Roughing.
  
  926   Wednesday, May 11, 2022, 10:05 Aaron Schmidt P2N-SISITETM444812-245240-1 P2N assembly conditioning - 3Target oven #45241-1 swapped out. SS bolts
were in use on the legs.
Molybdenum screws in the legs on
  
  925   Tuesday, May 10, 2022, 10:09 Aaron Schmidt P2N-SISITETM445241-145240-1In progressP2N assembly conditioning - 2 Ref: https://elog.triumf.ca/TIS/Test-Stand/924.
During testing, it was noted one leg was
glowing vs the other. P2N assembly was removed
  
  988   Tuesday, December 12, 2023, 16:11 Dave NeilsonShunt #0   -- P2N Thermal TestTuesday, December 12, 2023, 16:07 
- Pumping down test stand overnight for testing
tomorrow. vacuum good, turbos starting now.
  
  753   Thursday, August 08, 2019, 09:12 Aaron Schmidt LP-FEBIAD   42752-7In progressP2N Setup - LP-FEBIAD targetInserted a used (heating) LP-FEBIAD target
with a basic heat shield assembly with no
end plate foil on the window side to observe
 8x 
  873   Wednesday, May 19, 2021, 16:02 Aaron Schmidt       P2N HS conditioning Parasitic assemblies on the lid & end
plate included. Online HS.
Wednesday, May 19, 2021, 16:00: Roughing.
 HV_test_-_Online_HS_&_parasitic_mods.docx 
  746   Tuesday, July 16, 2019, 10:28 Fernando MaldonadoP2N      P2N 1200 A testTuesday, July 16, 2019, 10:27: The idea
of this run is to have the full 600 A from
TGHT and the full 600 A from TBHT.
  
  734   Friday, June 21, 2019, 15:12 Aaron SchmidtP2N - 1      P2N - 1 - 2019Friday, June 21, 2019, 14:48: Roughing.
Friday, June 21, 2019, 15:18: Turbo
pumps on.
  
  742   Thursday, July 04, 2019, 15:15 Aaron SchmidtP2N - 1      P2N - 1 - 2 - 2019Screws instead of rivets on target leg.
Insulator changed.
Thursday, July 04, 2019, 15:14: Roughing
  
  564   Wednesday, January 25, 2017, 09:48 Aaron Schmidt    41882-441751-6DoneOut gas Heat Shield for Target cleaning testNo EE. Insulators, gripper arms, and blank
EE plate included
-New grounded 9 pins included in
 7x 
  597   Monday, July 17, 2017, 09:55 Aaron Schmidt    41882-442738-1In progressOut Gas HS for Target Cleaning Test-No EE. Insulators, gripper arms,
and blank EE plate included
 OMEGA_OM-DAQPRO-5300_24-Jul-17_10.23.02.dlpTarget_Cleaning_Test_HS_Outgassing.docxTS-2017-07-17-11-17.rga 
  852   Thursday, February 18, 2021, 10:47 Aaron Schmidt       Optics loss / CANBUS failure.Thursday, February 18, 2021, 10:45: TPS:Q3
& the TSB CBC CANBUS controllers had
failed yesterday, as well as a cable was
  
  650   Tuesday, March 20, 2018, 09:14 Aaron Schmidt      Problems/SolutionsOptics issueTuesday, March 20, 2018, 09:11: TMS:Q5
& TMS:Q2 controllers require repair.
Unable to hold a negative voltage.
  
  730   Monday, June 10, 2019, 14:35 Aaron Schmidt      DoneOptics Tray / EZL inspection.Monday, June 10, 2019, 13:00: Optics Tray
removed.
Megger'd @ 1000V on EZL and Collimator.
 20190610_135100.jpg20190610_135926.jpg20190610_135045.jpg20190610_135517.jpg 
ELOG V2.9.2-2455