  257   Monday, February 10, 2020, 14:51 Isaac EarleMaintenanceOtherOtherT1-MK2 target and M9BB moved The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit. 
The M9 beam blocker was then moved from the
  
  238   Thursday, May 10, 2018, 15:23 Isaac EarleRepairTarget 1TargetT1-MK2 protect monitor and profile monitor replacedDuring first injection of beam down 1A
problems were encountered with the T1 protect
monitor.  Testing was done by Probes
  
  292   Wednesday, May 25, 2022, 10:15 Adam NewsomeStandard OperationTarget 1TargetT1-MK2 moved from hot cell to storage areaThe T1-MK2 target was moved from the hot
cell to the storage area, in position 5.
Note: manual nudging of the flask was required
  
  48   Friday, July 06, 2012, 16:03 Isaac EarleRepairTarget 1TargetT1-MK2 Target Repair Complete Target elevation measurements and
beam spot plots were completed on the T1-MK2
target and the target is now fully repaired
 T1MK2_-_July_2012.pdf 
  60   Wednesday, October 24, 2012, 17:34 Isaac EarleRepairTarget 1TargetT1-MK2 Target Repair CompleteThe target ladder was detached, old delta
seals removed, sealing surfaces cleaned using
scotchbrite pad and a dremel tool, and delta
  
  64   Monday, December 10, 2012, 15:42 Isaac EarleMaintenanceTarget 1TargetT1-MK2 Target Maintenance- T1-MK2 target moved from storage pit
to hot cell
- Removed unused proximity sensor
  
  181   Friday, October 09, 2015, 15:52 Isaac EarleRepairTarget 1TargetT1-MK2 Protect Monitor Replacement and InspectionWhen the damage to the T2 Protect Monitor
was found to be caused by flying debris from
a vacuum spike (see e-log #179), it was decided
 12x 
  41   Monday, June 18, 2012, 16:27 Isaac EarleRepairTarget 1TargetT1-MK2 Profile and Protect Monitor Electronics Check Bill Rawnsley and Mike Russell performed
a 'blip' test on the T1-MK2 profile monitor
and protect monitors today.  A possible
  
  135   Wednesday, January 14, 2015, 13:32 Isaac EarleStandard OperationTarget 1TargetT1-MK2 Moved from B/L to Storage PitThe T1-MK2 target was transferred from
the beam line to the storage pit in hole
#5 using the transfer flask.  A maximum
  
  40   Friday, June 08, 2012, 17:01 Isaac EarleRepairTarget 1TargetT1-MK2 Leak Repair Update A leak check was performed on the
T1-MK2 target in the hot cell today and confirmed
successful leak-free installation of the
  
  59   Friday, September 28, 2012, 15:19 Isaac EarleRepairTarget 1TargetT1-MK2 Delta Seal Leak  After removal of the leaky
target cassette at position 3, plugs were
installed on the target ladder and a leak
  
  208   Friday, September 30, 2016, 16:54 Isaac EarleRepairTarget 1TargetT1-MK2 - New Beryllium Targets Installed The following work was performed
on the T1-MK2 target assembly during the
September 2016 Mini-shutdown:
 T1-MK2_Posn_4_Entrance_Window_Beam_Spot_-_Sept_27_2016.JPGT1-MK2_Posn_4_Exit_Window_Beam_Spot_-_Sept_27_2016.JPGTarget_Info_Sheet_&_Elevations.pdf 
  273   Wednesday, March 31, 2021, 16:15 Matthew GareauStandard OperationTarget 1TargetT1-MK1 target exchange March 29 Monday
- moved T1-MK1 target from beamline
to hotcell  (field from target 15mSv/hr
 IMG_20210330_140744.jpgIMG_20210330_141059.jpgIMG_20210330_141455.jpgT1-MK1_-_2021.pdf 
  291   Thursday, May 05, 2022, 14:39 Adam NewsomeStandard OperationTarget 1TargetT1-MK1 and T2-MK1 profile monitor actuation testThe profile monitor actuation tests were
completed for T1 and T2. No abnormalities
were noticed in vacuum during either test.
  
  228   Tuesday, August 29, 2017, 12:17 Isaac EarleMaintenanceTarget 1TargetT1-MK1 and T2-MK1 Hansen water fittings replaced The #6 male Hansen fittings for the
T1-MK1 and T2-MK1 targets (both currently
stored in the target storage pit) were replaced
  
  5   Thursday, December 22, 2011, 15:27 Isaac EarleMaintenanceTarget 1TargetT1-MK1 Transferred to Storage Pit T1-MK1 target transferred from hot
cell to storage pit position #3 to free up
the hot cell in preparation for shut-down
  
  53   Friday, July 27, 2012, 14:48 Isaac EarleRepairTarget 1TargetT1-MK1 Target Repair Update- T1MK1 target transferred from storage
pit to hot cell (max field: 4700 
  
  54   Wednesday, August 08, 2012, 14:40 Isaac EarleRepairTarget 1TargetT1-MK1 Target Repair Complete- Re-wired profile monitor was received
from Probes Group and installed on the target
  
  80   Wednesday, April 17, 2013, 16:45 Isaac EarleStandard OperationTarget 1TargetT1-MK1 Target Leak Checked The T1-MK1 target was leak checked
on April 15th at the T1 monolith by Ron Kuramoto
and Edi Dalla Valle.  No leaks were
  
  125   Friday, November 14, 2014, 17:30 Isaac EarleRepairTarget 1TargetT1-MK1 Target Failure / T1 Target Swap -
On Nov 13 at ~1am the BL1A vacuum went bad.
 The T1 and T2 volumes were isolated
 T1MK2_Nov_14_2014.pdf 