Entry  Tuesday, October 04, 2022, 09:59, Adam Newsome, Maintenance, Target 2, Cooling, T2 cooling package maintenance - mini-shutdown 2022 
The following maintenance tasks were performed during mini-shutdown of 2022 with the goal of resolving the Fault 14966 (target water flow rate low).

    Replace the o-ring, paddle wheel, and shaft on the following flow rate sensors:
    
        Q1 (FGTGT)
        Q2

       Q4
    
    
    Replace the demineralizing flow metering valve with a new needle valve (the old one was flaky and appeared
Entry  Friday, September 23, 2022, 10:51, Matthew Gareau, Standard Operation, Target 2, Target, Target T2-MK2 moved to storage pit Storage_location_state_as_of_Sept_23_2022_(after_target_moves).jpg
The T2-MK2 target was transported from the east hot cell to the storage pit at position 3.
As was noted in the past, position 3 is difficult to align. The flask alignment pins prevent the flask from positioning in the correct location,
and it is required to have the flask just above the pins to ensure that the pins did not restrict the flask movement.
Entry  Thursday, September 15, 2022, 14:34, Adam Newsome, Standard Operation, Target 2, Target, T2-MK2 target elevations measurement T2-MK2_-_Sept_2022.pdf
The target elevations measurement and beam spot checks were completed on Sept. 15, 2022. This was done after a July 2022 target exchange for target positions
3 and 5. 
 
Entry  Tuesday, August 30, 2022, 14:24, Adam Newsome, Maintenance, Other, Hot Cell, Nuclear Ventilation - Filter Change 
Mechanical Services Group changed the pre-filter in the ventilation system on Aug. 29, 2022 as per work permit C2022-08-29-2.
 
It is recommended that Mechanical Services change the HEPA filter as soon as possible. These filters are on order with approximately 7 month lead
Entry  Tuesday, August 23, 2022, 14:36, Adam Newsome, Standard Operation, Other, Other, BL1A Holding Tank - Level Check 
The water level inside the BL1A active water holding tank was checked today (Aug. 23, 2022). The tank is essentially empty at this time. 
Entry  Monday, August 22, 2022, 09:01, Adam Newsome, Standard Operation, Other, Active Sump, Active Sump Draining 
On Aug. 18, 2022, Operations informed RH group that an alarm activated for the full status of the MHESA B1 RCR1 Lab holding tank. Additionally another
alarm was reported in the RH control room regarding the RH sump full (Southwest Meson Hall Extension - Remote Handling area). However, there is an alarm
signal for the RH sump that was seen as OK at the MHESA Lab HMI.
Entry  Thursday, July 28, 2022, 12:51, Adam Newsome, Repair, Other, Hot Cell, Meson Hall Hot Cell - Nuclear Ventilation Issue 
It was reported today by Peter Bratt that the nuclear ventilation system for the hot cell is not functioning. At this time, the cause of the issue is
unknown. Remote Handling and Electrical Services are investigating. This e-log will be updated when the issue is resolved.
 
Entry  Wednesday, July 06, 2022, 12:52, Adam Newsome, Other, Other, Hot Cell, Potential hot cell window oil leak 
Some oil was noticed around the hot cell window, on the control panel, and on the ground below the control panel. A leak is suspected. 
 
Suggest tightening all bolts to specified torque along the window, and monitoring overflow oil level (position today was marked). If the problem
Entry  Wednesday, July 06, 2022, 12:49, Adam Newsome, Repair, Other, Hot Cell, Hot Cell - Helium wand tubing broken 
The tubing for the helium wand inside the hot cell is broken and needs to be replaced. More tubing has been ordered and the job will be completed in
the coming weeks.
Entry  Wednesday, July 06, 2022, 12:49, Matthew Gareau, Repair, Other, Other, Helium line damage, and hotcell window oil leaking 
Today myself and Adam Newsome started the leak detection steps for a target exchange and notice that the Helium line was not connected/broken from inside
the hotcell.
A new line will need to be installed and the line attached to the helium wand.
Entry  Wednesday, June 08, 2022, 08:59, Adam Newsome, Other, Target 2, Cooling, T2 flow rate sensor (BL1A:T2CS:FGTGT ) - warning and trip limits adjusted After_Adjustment.PNGSensor_data_around_June_6-8.PNG
See fault 14966: 





Normal
0




false
false
false
Entry  Wednesday, May 25, 2022, 10:16, Adam Newsome, Standard Operation, Target 2, Target, T2-MK2 moved: from storage location to hot cell 
Target T2-MK2 was moved from the storage location (formerly position 3) to the hot cell in preparation for replacement of end of life targets. 
Entry  Wednesday, May 25, 2022, 10:15, Adam Newsome, Standard Operation, Target 1, Target, T1-MK2 moved from hot cell to storage area 
The T1-MK2 target was moved from the hot cell to the storage area, in position 5. Note: manual nudging of the flask was required to get it to align with
guide pins properly. 
Entry  Thursday, May 05, 2022, 14:39, Adam Newsome, Standard Operation, Target 1, Target, T1-MK1 and T2-MK1 profile monitor actuation test 
The profile monitor actuation tests were completed for T1 and T2. No abnormalities were noticed in vacuum during either test. 
 
Note: an issue was observed with T2-MK1 - see e-log 290. The issue was resolved. 
Entry  Thursday, May 05, 2022, 14:38, Adam Newsome, Maintenance, Target 2, Controls, T2-MK1: profile monitor actuation check and repair to connector T2-MK1_prof_mon_connector_-_rear_-_after_fix.jpg
An attempt was made to actuation the T2 profile monitor, however it showed up in EPICS as being not present. Furthermore, the "Remote"
indicator light on the physical controller was not lit up despite the switch being in remote mode. The limit switch indicator light was working.
 
Entry  Wednesday, May 04, 2022, 11:27, Adam Newsome, Standard Operation, Target 2, M9, M9 and M20 Beam Blocker Actuation Test 
The beam blockers for M9 and M20 were actuated, and vacuum was monitored to ensure no disruptions. Both actuation tests were successful. Motion was observed
and no abnormalities noted. Cabling and air connections checked: OK.
 
Entry  Thursday, April 14, 2022, 14:38, Adam Newsome, Other, Target 2, Diagnostics, Issue with Protect Monitor SHV Cable PXL_20220414_210238000.jpgPXL_20220414_210053641.jpgPXL_20220414_210037717.jpg
Diagnostics group (Shengli Liu) noted a lack of connectivity between control panel and T2 Protect Monitor via the high voltage cable. Upon inspection
it was noted:

    The cable was very brittle due to radiation exposure and it was cracking in multiple places
    In the SHV connector, the
Entry  Wednesday, April 13, 2022, 12:33, Adam Newsome, Standard Operation, Target 2, Target, T2-MK1 moved: from storage area to target station 
The T2-MK1 target was moved from the storage area (formerly position 4) to the target station. Services were reconnected in order to prepare for normal
operation. 
Entry  Wednesday, April 13, 2022, 12:31, Adam Newsome, Standard Operation, Target 2, Target, T2-MK2 moved: from target station to storage 
The T2-MK2 target was moved from the target station to the storage area (position 3). Upon removal, it was measured with a pole monitor at 0.5 m to be
960 mSv/h. 
Entry  Wednesday, March 16, 2022, 14:16, Matthew Gareau, Standard Operation, Other, Cooling, T1/T2 water packages drained to B1A AWHT, tested, and released. Also solenoid valve SV1 broken 11_Mar_2022_Tritium_Records_T1_T2_from_RPG.pdfsolenoid_valve_SV1.jpg
 The T1/T2 water packages were drained into the B1AAWHT (280L), the water was sampled and tested by RPG, results included in elog.
Once given the all clear myself and Maico released the water from the B1AAWHT (300L). 
It was discovered that the solenoid valve SV1 which is located in the RH lab beside the sump, is broken and will need replacing, picture included