Tuesday, February 26, 2019, 10:55, Isaac Earle, Maintenance, Target 1, Cooling, T1 and T2 MRO work and solenoid valve change summary
|
The following work was completed between Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages drained to South TNF holding tank, water sampled and tested, released after approval from RPG
T1
resin can swapped
All Cuno filters changed at T1 (3 total)
T1 inlet (T1CSPGIN) and outlet (T1CSPGOUT) pressure gauges replaced |
Wednesday, February 05, 2020, 14:53, Isaac Earle, Maintenance, Target 1, Cooling, T1 & T2 cooling package MRO work completed
|
Annual MRO work on the T1 and T2 cooling packages is now complete. The following tasks were performed:
Water from both packages drained to the South TNF holding tank (samples taken)
All Proteus paddle wheels, shafts, and
o-rings replaced (5 each at T1 and T2)
All Cuno filters changed
Archived data for all sensor readbacks inspected. Only |
Wednesday, August 19, 2020, 12:57, Isaac Earle, Maintenance, Target 1, Cooling, T1/T2 MRO summary for 2020 shutdown
|
The following work was completed during the 2020 shutdown period for BL1A (Jan-Aug 2020):
T1 and T2 EPICS data checked for anomalies. None found, all sensors behaving as expected
T1 and T2 cooling package
water drained to storage tank, sampled, and released
All cuno filters changed (3 for T1, 2 for T2)
All T1 and T2 proteus paddle |
Tuesday, October 27, 2020, 14:01, Isaac Earle, Repair, Target 2, Cooling, T2 Collimator flow meter paddle wheel replaced
|
The T2 Collimator A flow meter signal (B1A:T2:FGCOLA) began fluctuating and occasionally reading 0gpm on Sunday Oct 25 causing BL1A trips and machine
down time.
On the maintenance day today (Tues Oct 27), the T2 package was uncovered and the T2 Col. A flow meter was opened. No unusual deposits were |
Friday, April 09, 2021, 12:42, Matthew Gareau, Maintenance, Target 2, Cooling, Changed the paddle wheel, o ring, and shaft in the Collimator A flow meter at the T2 package
|
With the assistance of Maico we changed the paddle wheel, o ring, and shaft in the Collimator A flow meter (Q4) at the T2 package.
Flow meter was wiped clean to ensure o ring surface was clean.
Everything was changed without incident, and ops confirmed that the flow rate is now normal. |
Thursday, March 10, 2022, 11:18, Adam Newsome, Maintenance, Target 2, Cooling, Changed paddle wheel, o-ring, and shaft in flow sensors at T2 cooling package
|
The paddle wheels, o-rings, and shafts were changed at the T2 cooling package for the following sensors:
B1A:T2:FGCOLA
T2CS:FGTGT
T2CS:FGDEM
T2CS:FGSEC
T2:FGCOLB
No
major issues were noted. Some residue was observed upon cleaning the sensors. No leaks observed when turning water isolation valves back on. |
Thursday, March 10, 2022, 13:57, Adam Newsome, Maintenance, Target 1, Cooling, Changed paddle wheel, o-ring, and shaft in flow sensors at T1 cooling package
|
The paddle wheels, o-rings, and shafts were changed at the T1 cooling package for the following sensors:
B1A:T1:FGCOLA
T1CS:FGTGT
T1CS:FGDEM
T1CS:FGSEC
T1:FGCOLB
No
major issues were noted. Some residue was observed upon cleaning the sensors. No leaks observed when turning water isolation valves back on. |
Friday, March 11, 2022, 15:05, Adam Newsome, Maintenance, Target 1, Cooling, O-rings on T1 cooling package water reservoir changed
|
The four o-rings on top of the T1 cooling package water reservoir were changed as per the recommended 5 year replacement schedule. |
Friday, March 11, 2022, 15:06, Adam Newsome, Maintenance, Target 2, Cooling, O-rings on T2 cooling package water reservoir changed
|
The four o-rings on top of the T2 cooling package water reservoir were changed as per the recommended 5 year replacement schedule. |
Friday, March 11, 2022, 15:08, Adam Newsome, Maintenance, Target 1, Cooling, Filters replaced: T1 cooling system
|
All filters were replaced for the T1 cooling system: demineralizing resin circuit, target water system, and M15. |
Friday, March 11, 2022, 15:09, Adam Newsome, Maintenance, Target 2, Cooling, Filters replaced: T2 cooling system
|
All filters were replaced for the T2 cooling system: demineralizing resin circuit and target water system. |
Monday, March 14, 2022, 14:08, Adam Newsome, Maintenance, Target 1, Cooling, T1 cooling system: filled, tuned, leak-checked
|
The T1 cooling system was refilled with water via the expansion tank until the tank level read approximately 38 cm.
The system pump was restarted. All sensors displayed acceptable nominal values. Demin flow was tuned to 1.0 gpm.
No leaks or abnormalities observed - system running normally. |
Monday, March 14, 2022, 14:09, Adam Newsome, Maintenance, Target 2, Cooling, T2 cooling system: filled, tuned, leak-checked
|
The T2 cooling system was refilled with water via the expansion tank until the tank level read approximately 38 cm.
The system pump was restarted. All sensors displayed acceptable nominal values. Demin flow was tuned to 1.0 gpm.
No leaks or abnormalities observed - system running normally. |
Wednesday, March 16, 2022, 14:16, Matthew Gareau, Standard Operation, Other, Cooling, T1/T2 water packages drained to B1A AWHT, tested, and released. Also solenoid valve SV1 broken
|
The T1/T2 water packages were drained into the B1AAWHT (280L), the water was sampled and tested by RPG, results included in elog.
Once given the all clear myself and Maico released the water from the B1AAWHT (300L).
It was discovered that the solenoid valve SV1 which is located in the RH lab beside the sump, is broken and will need replacing, picture included |
Wednesday, June 08, 2022, 08:59, Adam Newsome, Other, Target 2, Cooling, T2 flow rate sensor (BL1A:T2CS:FGTGT ) - warning and trip limits adjusted
|
See fault 14966:
Normal
0
false
false
false
|
Tuesday, October 04, 2022, 09:59, Adam Newsome, Maintenance, Target 2, Cooling, T2 cooling package maintenance - mini-shutdown 2022
|
The following maintenance tasks were performed during mini-shutdown of 2022 with the goal of resolving the Fault 14966 (target water flow rate low).
Replace the o-ring, paddle wheel, and shaft on the following flow rate sensors:
Q1 (FGTGT)
Q2
Q4
Replace the demineralizing flow metering valve with a new needle valve (the old one was flaky and appeared |
Tuesday, October 11, 2022, 11:27, Adam Newsome, Maintenance, Target 1, Cooling, T1 inlet pressure transducer replacement
|
A fault was reported June 21, 2022 (Fault
15033) regarding T1 inlet pressure warnings... the pressure reading slowly dropped over time as seen in the attached strip tool screenshot (B1A:T1CS:PGIN).
The pressure reading issue is attributed to a fault pressure transducer. The transducer was replaced on Oct. 11, 2022 my M. Dalla Valle. It is currently |
Monday, January 16, 2023, 09:54, Adam Newsome, Standard Operation, Other, Cooling, T1 and T2 - Cooling Package Drained
|
On Jan. 13, the T1 and T2 cooling package water reservoirs were drained to the BL1A holding tank. Water samples were obtained for each system and provided
to RPG for analysis.
Prior to starting draining, the BL1A holding tank water level was approximately 330L. After draining, the water level was approximately 550L (checked |
Monday, January 16, 2023, 15:01, Adam Newsome, Maintenance, Target 1, Cooling, T1 Cooling Package MRO - 2023 Shutdown
|
T1 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have been completed for T1 (this list will be updated as work progresses): |
Monday, January 16, 2023, 15:04, Adam Newsome, Maintenance, Target 2, Cooling, T2 Cooling Package MRO - 2023 Shutdown
|
T2 Cooling Package MRO began Jan. 16, 2023.
The following maintenance tasks have been completed for T2 (this list will be updated as work progresses): |
|