231
|
Thursday, December 07, 2017, 13:54 |
Isaac Earle | Development | Other | Other | Waste pails transferred from warm cell storage bunker to rad waste pit | Six 5 gallon pails were transferred this
morning from a temporary storage bunker in
the Warm Cell to the Rad Waste Pit for long |
|
232
|
Wednesday, January 10, 2018, 17:45 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 beam spot photos, M20BB moved to storage pit | The T2-MK2 target was moved from
the beamline to the hot cell on January 8th.
The field at 0.5m was 130mSv/hr. Photographs |
|
233
|
Thursday, March 22, 2018, 17:24 |
Isaac Earle | Standard Operation | Other | Active Sump | RH Lab active sump released | The RH Lab active sump level reached
the high limit yesterday due to an overflow
of the ultrasonic cleaner in the Rad Waste |
|
234
|
Wednesday, March 28, 2018, 10:12 |
Isaac Earle | Standard Operation | Other | Other | Five waste pails moved to East Vault Tunnel for storage | Five 5 gallon metal pails with active
waste were moved from the Warm Cell to the
Cyclotron East Vault Tunnel today for long |
|
235
|
Friday, April 06, 2018, 15:05 |
Isaac Earle | Standard Operation | Target 2 | Target | T2-MK2 target MRO | The following is a summary of MRO work
done on the T2-MK2 target during the 2018
shutdown:
|
|
236
|
Tuesday, April 10, 2018, 11:20 |
Isaac Earle | Maintenance | Other | Cooling | T1 and T2 cooling package shutdown MRO work | The following work was performed
on the T1 and T2 cooling packages during
the 2018 shutdown: |
|
237
|
Friday, April 13, 2018, 14:21 |
Isaac Earle | Maintenance | Other | Other | M20 beam blocker MRO and T1/T2 final checks | The M20 beam blocker main shaft seals were
replaced as per the T1/T2 target device maintenance
schedule. Both air cylinders were found |
|
238
|
Thursday, May 10, 2018, 15:23 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 protect monitor and profile monitor replaced | During first injection of beam down 1A
problems were encountered with the T1 protect
monitor. Testing was done by Probes |
|
239
|
Friday, June 01, 2018, 17:50 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve coil replaced | Flow stopped through the T1 collimator
cooling loop around the same time as a power
bump this afternoon. The problem was |
|
240
|
Tuesday, July 03, 2018, 11:09 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package outlet water pressure sensor replaced | The T1 cooling package outlet water
pressure sensor (B1A:T1CS:PGOUT) was replaced
this morning with a new unit. Over |
|
241
|
Monday, July 23, 2018, 09:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve failed - Solenoid replaced | On Saturday July 21st the T1 Collimator
solenoid valve would not re-open after tripping
closed due to a (planned) loss of vacuum. |
|
242
|
Thursday, August 23, 2018, 11:52 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package pump failure and replacement | On Wednesday August 15th the T1 cooling
package tripped off, and could not be restarted.
On the EPICS screen the pump device went |
|
243
|
Tuesday, August 28, 2018, 11:16 |
Isaac Earle | Standard Operation | Other | Other | South TNF Holding Tank water released | The water in the South TNF Holding
Tank was released today under work permit
#C2018-08-28-3. The tank contained |
|
244
|
Thursday, September 06, 2018, 13:49 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package secondary side solenoid failed | On Friday Aug 31 at approximately
3am T1CS:FGSEC dropped to 0gpm flow.
This was confirmed to be a real reading when |
|
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
251
|
Wednesday, May 22, 2019, 14:25 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target moved to HC; T1-MK1 target moved to BL | After extensive
testing over the last 2 weeks it was determined |
|
252
|
Monday, June 24, 2019, 14:29 |
Isaac Earle | Development | Target 1 | Target | T1 and T2 target alignment frames overhauled | The following work was completed on both
the T1 and T2 target alignment frames
One of the short taper |
8x |
253
|
Tuesday, December 17, 2019, 12:39 |
Isaac Earle | Standard Operation | Other | Other | 55 gallon drum and old M9 service stand moved to Rad Waste Pit | The following items were moved today from
the Warm Cell to the Rad Waste Pit for long
term storage: |
|
254
|
Monday, January 20, 2020, 16:07 |
Isaac Earle | Other | Other | Other | Second 55-gal drum moved to cyclotron east vault tunnel | The second (and final) 55 gallon
drum containing active items from the Meson
Hall East Hot Cell was transported today |
|