Entry  Thursday, December 07, 2017, 13:54, Isaac Earle, Development, Other, Other, Waste pails transferred from warm cell storage bunker to rad waste pit IMG_0102.JPGIMG_6285.JPGIMG_0102.JPGIMG_6285.JPG
Six 5 gallon pails were transferred this morning from a temporary storage bunker in the Warm Cell to the Rad Waste Pit for long term storage.  The
pails contain various BL1A active waste from the East Hot Cell including dozens of irradiated beryllium and graphite targets.  The field from the
pails ranged from 0.1 to 9mSv/hr at 0.5m.  The work was performed according to the clean-out procedure (Document-142965). 
Entry  Wednesday, January 10, 2018, 17:45, Isaac Earle, Standard Operation, Target 2, Target, T2-MK2 beam spot photos, M20BB moved to storage pit T2-MK2_Position_4_beam_spot_photo_-_12mm_Be_-_Jan_10_2018.jpgT2-MK2_Position_4_beam_spot_photo_-_12mm_Be_-_Jan_10_2018_s.jpg
 The T2-MK2 target was moved from the beamline to the hot cell on January 8th.  The field at 0.5m was 130mSv/hr.  Photographs of the beam
spot of the Position 4 target are attached below.  This is a 12mm beryllium target (ID: "JUL.06#4).  This is the only target on the T2 ladder
that has seen beam since it was installed on October 10, 2017.  A shielding plug was installed on the T2 flange.  A new 5cm target will be installed
Entry  Thursday, March 22, 2018, 17:24, Isaac Earle, Standard Operation, Other, Active Sump, RH Lab active sump released 
 The RH Lab active sump level reached the high limit yesterday due to an overflow of the ultrasonic cleaner in the Rad Waste Area.  The sump
was sampled by RPG, and after analysis the water was approved for release.  The water was pumped out today.  Local and MCR alarms functioned
as expected.
Entry  Wednesday, March 28, 2018, 10:12, Isaac Earle, Standard Operation, Other, Other, Five waste pails moved to East Vault Tunnel for storage 
 Five 5 gallon metal pails with active waste were moved from the Warm Cell to the Cyclotron East Vault Tunnel today for long term storage. 
The pails were labeled with radioactive item tags and storage item numbers (1442 through 1446).  The pails contain used resin from T1, T2, and STF,
as well as one pail with active metal parts.
Entry  Friday, April 06, 2018, 15:05, Isaac Earle, Standard Operation, Target 2, Target, T2-MK2 target MRO 
The following is a summary of MRO work done on the T2-MK2 target during the 2018 shutdown:

 
Jan 8:
Entry  Tuesday, April 10, 2018, 11:20, Isaac Earle, Maintenance, Other, Cooling, T1 and T2 cooling package shutdown MRO work 
 The following work was performed on the T1 and T2 cooling packages during the 2018 shutdown:
- T1 and T2 cooling packages both sampled and drained to South TNF holding tank
- Water released after testing and approval from RPG
Entry  Friday, April 13, 2018, 14:21, Isaac Earle, Maintenance, Other, Other, M20 beam blocker MRO and T1/T2 final checks 
The M20 beam blocker main shaft seals were replaced as per the T1/T2 target device maintenance schedule.  Both air cylinders were found to be leaking
past the seals, and the blocker would not actuate in the hot cell even with 100psi (max site air) so they were also replaced.  With the new cylinders
the blocker actuated smoothly at about 45psi.  It is recommended that the air cylinders be replaced every second service (once per 10 years). 
Entry  Thursday, May 10, 2018, 15:23, Isaac Earle, Repair, Target 1, Target, T1-MK2 protect monitor and profile monitor replaced 
During first injection of beam down 1A problems were encountered with the T1 protect monitor.  Testing was done by Probes Group from the mezzanine
leading to the following investigation and repair work.
 
Entry  Friday, June 01, 2018, 17:50, Isaac Earle, Repair, Target 1, Cooling, T1 collimator solenoid valve coil replaced 
Flow stopped through the T1 collimator cooling loop around the same time as a power bump this afternoon.  The problem was narrowed down to failed
solenoid valve B1A:T1:SVCOL by comparing coil resistance to other units without issue (~1.0ohm vs 3.6ohm for working units), measured at the T1/T2 PLC
cabinet.  Shielding above the T1 package was removed and the solenoid coil was replaced with a new unit.  After replacement the valve works as
Entry  Tuesday, July 03, 2018, 11:09, Isaac Earle, Repair, Target 1, Cooling, T1 cooling package outlet water pressure sensor replaced 
 The T1 cooling package outlet water pressure sensor (B1A:T1CS:PGOUT) was replaced this morning with a new unit.  Over the last few months
the sensor readout had been steadily decreasing (from around 20psi to 4psi) with no corresponding decrease in inlet pressure, and no change in the circuit
flowrate (this is how these pressure sensors typically fail).
Entry  Monday, July 23, 2018, 09:39, Isaac Earle, Repair, Target 1, Cooling, T1 collimator solenoid valve failed - Solenoid replaced 
On Saturday July 21st the T1 Collimator solenoid valve would not re-open after tripping closed due to a (planned) loss of vacuum.  Shielding was
removed and the valve solenoid was replaced which fixed the problem.  The original valve body was left in place.
This is the second time the solenoid at this location failed (See E-Log #239), and the latest of several failures of these new 24VDC solenoids
Entry  Thursday, August 23, 2018, 11:52, Isaac Earle, Repair, Target 1, Cooling, T1 cooling package pump failure and replacement TUS1801057_Triumf.pdf
On Wednesday August 15th the T1 cooling package tripped off, and could not be restarted.  On the EPICS screen the pump device went into an immediate
time-out each time we attempted to turn it on.  An electrician was involved in the debugging, and issues were found with the 480V supply.  The
breaker switch in the 480V supply panel was found to be damaged, and was replaced.  The relay in the contactor box for the pump motor thermal protection
Entry  Tuesday, August 28, 2018, 11:16, Isaac Earle, Standard Operation, Other, Other, South TNF Holding Tank water released 
 The water in the South TNF Holding Tank was released today under work permit #C2018-08-28-3.  The tank contained approximately 100L from the
T1 cooling package (drained Aug 16, 2018) and 350L from the 500MeV system (drained April 23, 2018 by Steve Sapriken).
Entry  Thursday, September 06, 2018, 13:49, Isaac Earle, Repair, Target 1, Cooling, T1 cooling package secondary side solenoid failed 
 On Friday Aug 31 at approximately 3am T1CS:FGSEC dropped to 0gpm flow.  This was confirmed to be a real reading when T1CS temperatures continued
to rise steadily.  Beam was turned off, and T1CS later turned off by operators (temps continued to rise due to heat from pump).  The cooling
package was uncovered in the morning, and the T1CS:SVSEC solenoid was replaced by Doug Preddy and Keith Ng.  This solved the problem and the package
Entry  Thursday, January 10, 2019, 13:51, Isaac Earle, Maintenance, Target 1, Cooling, T1 and T2 cooling packages inspected 
The T1 and T2 cooling packages were inspected today while running.  No water leaks were observed at either package including the high-active loops
and copper active. 
The T1 pump was fairly noisy (video was taken to record the sound).  This is the new pump installed in August 2018 (see E-Log #242). 
Entry  Tuesday, February 26, 2019, 10:55, Isaac Earle, Maintenance, Target 1, Cooling, T1 and T2 MRO work and solenoid valve change summary 
The following work was completed between Jan 16 - Feb 19, 2019:

    T1 and T2 cooling packages drained to South TNF holding tank, water sampled and tested, released after approval from RPG
    T1
resin can swapped
    All Cuno filters changed at T1 (3 total)
    T1 inlet (T1CSPGIN) and outlet (T1CSPGOUT) pressure gauges replaced
Entry  Wednesday, May 22, 2019, 14:25, Isaac Earle, Repair, Target 1, Target, T1-MK2 target moved to HC; T1-MK1 target moved to BL T1-MK1_target_info_sheet_-_Installed_May_21_2019.pdf
After extensive testing over the last 2 weeks it was determined that the protect monitor
on the T1-MK2 target had an issue with intermittent shorting between the high voltage line and ground (movement of the target ladder was causing the short
to come and go).
Entry  Monday, June 24, 2019, 14:29, Isaac Earle, Development, Target 1, Target, T1 and T2 target alignment frames overhauled 8x
The following work was completed on both the T1 and T2 target alignment frames

    One of the short taper pins on the top of the frame was swapped for a longer version to simplify flask alignment to the frame (now one
pin can be aligned at a time instead of both concurrently)
    Three permanently mounted cameras installed to view east/west alignment, north/south
Entry  Tuesday, December 17, 2019, 12:39, Isaac Earle, Standard Operation, Other, Other, 55 gallon drum and old M9 service stand moved to Rad Waste Pit RWC-55-01-2019.pdfpit_-_before_move.jpgdrum_being_lifted.jpgpit_-_after_move_-_showing_drum.jpgpit_-_after_move_-_showing_service_stand_(bottom_right_with_green_sling).jpg
The following items were moved today from the Warm Cell to the Rad Waste Pit for long term storage:
1. A 55 gallon drum containing various active components from the East Hot Cell.  The drum was labelled on the body and lid with the identification
number RWC-55-01-2019.
Entry  Monday, January 20, 2020, 16:07, Isaac Earle, Other, Other, Other, Second 55-gal drum moved to cyclotron east vault tunnel RWC-55-02-2019_(after_move_to_cyc_vault_tunnel).pdf
 The second (and final) 55 gallon drum containing active items from the Meson Hall East Hot Cell was transported today from the Warm Cell to the
Cyclotron East Vault Tunnel.   The updated form is attached.