258
|
Friday, February 28, 2020, 09:06 |
Isaac Earle | Development | Other | M9 | M9 Q1Q2 service stand floor plate installed | The M9 service stand floor plate
(TB23351) was installed in the M9 pit yesterday.
Prior to installation all 5 threaded inserts |
|
257
|
Monday, February 10, 2020, 14:51 |
Isaac Earle | Maintenance | Other | Other | T1-MK2 target and M9BB moved | The T1-MK2 target was moved from
the hot cell to Hole #5 in the storage pit.
The M9 beam blocker was then moved from the |
|
256
|
Wednesday, February 05, 2020, 14:53 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 & T2 cooling package MRO work completed | Annual MRO work on the T1 and T2
cooling packages is now complete. The
following tasks were performed: |
|
255
|
Thursday, January 30, 2020, 17:55 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target assembly repair completed in hot cell | The following work was done to the T1-MK2
target in the hotcell between the dates of
May 24, 2019 - Jan 30, 2020 (See E-Log #251 |
|
254
|
Monday, January 20, 2020, 16:07 |
Isaac Earle | Other | Other | Other | Second 55-gal drum moved to cyclotron east vault tunnel | The second (and final) 55 gallon
drum containing active items from the Meson
Hall East Hot Cell was transported today |
|
253
|
Tuesday, December 17, 2019, 12:39 |
Isaac Earle | Standard Operation | Other | Other | 55 gallon drum and old M9 service stand moved to Rad Waste Pit | The following items were moved today from
the Warm Cell to the Rad Waste Pit for long
term storage: |
|
252
|
Monday, June 24, 2019, 14:29 |
Isaac Earle | Development | Target 1 | Target | T1 and T2 target alignment frames overhauled | The following work was completed on both
the T1 and T2 target alignment frames
One of the short taper |
8x |
251
|
Wednesday, May 22, 2019, 14:25 |
Isaac Earle | Repair | Target 1 | Target | T1-MK2 target moved to HC; T1-MK1 target moved to BL | After extensive
testing over the last 2 weeks it was determined |
|
250
|
Tuesday, April 16, 2019, 15:35 |
Keith C Ng | Repair | Other | M9 | M9 project post shutdown summary | Completed work at m9 beam line:
- Removed existing service stand
and associated cable and water services. |
|
249
|
Tuesday, February 26, 2019, 10:55 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 MRO work and solenoid valve change summary | The following work was completed between
Jan 16 - Feb 19, 2019:
T1 and T2 cooling packages |
|
248
|
Friday, January 25, 2019, 10:53 |
maicodallavalle | Repair | Other | Cyclotron electrical | Cyclotron Elevating system Motor electrical wire repairs | 2018 Cyclotron lid up problem. Station
#9 was found to have the motor
wires along the beam plain had damaged wire |
|
247
|
Thursday, January 10, 2019, 13:51 |
Isaac Earle | Maintenance | Target 1 | Cooling | T1 and T2 cooling packages inspected | The T1 and T2 cooling packages were inspected
today while running. No water leaks
were observed at either package including |
|
246
|
Thursday, November 01, 2018, 13:57 |
Keith C Ng | Other | Other | Other | nuclear venillation in hot cells not working | Randomly checked on the nuclear ventilation
for the Meson Hall Hotcells and discovered
they were not running again (both magnahelic |
|
245
|
Thursday, October 25, 2018, 08:58 |
Keith C Ng | Repair | Other | Other | T1 collimator valve solenoid coil replaced again | On
23rd October we restarted the T1 and T2 water
packages after the mini shutdown and after |
|
244
|
Thursday, September 06, 2018, 13:49 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package secondary side solenoid failed | On Friday Aug 31 at approximately
3am T1CS:FGSEC dropped to 0gpm flow.
This was confirmed to be a real reading when |
|
243
|
Tuesday, August 28, 2018, 11:16 |
Isaac Earle | Standard Operation | Other | Other | South TNF Holding Tank water released | The water in the South TNF Holding
Tank was released today under work permit
#C2018-08-28-3. The tank contained |
|
242
|
Thursday, August 23, 2018, 11:52 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package pump failure and replacement | On Wednesday August 15th the T1 cooling
package tripped off, and could not be restarted.
On the EPICS screen the pump device went |
|
241
|
Monday, July 23, 2018, 09:39 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve failed - Solenoid replaced | On Saturday July 21st the T1 Collimator
solenoid valve would not re-open after tripping
closed due to a (planned) loss of vacuum. |
|
240
|
Tuesday, July 03, 2018, 11:09 |
Isaac Earle | Repair | Target 1 | Cooling | T1 cooling package outlet water pressure sensor replaced | The T1 cooling package outlet water
pressure sensor (B1A:T1CS:PGOUT) was replaced
this morning with a new unit. Over |
|
239
|
Friday, June 01, 2018, 17:50 |
Isaac Earle | Repair | Target 1 | Cooling | T1 collimator solenoid valve coil replaced | Flow stopped through the T1 collimator
cooling loop around the same time as a power
bump this afternoon. The problem was |
|