789
|
Monday, November 17, 2014, 13:45 |
chad fisher | South Hot-Cell | Repair | | | Jig for roof install of target |
Jig for installation of target through hot cell roof has been assembled and placed in the target hall. |
Attachment 1: Target_roof_install_20141117_01.jpg
|
|
Attachment 2: Target_Roof_install_Jig_20141117_02.jpg
|
|
Attachment 3: Target_roof_install_20141117_03.jpg
|
|
Attachment 4: Target_roof_install_20141117_04.jpg
|
|
788
|
Monday, November 17, 2014, 11:38 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move |
TM#3 with no target has been moved from the conditioning station to the north west silo. |
787
|
Thursday, November 13, 2014, 14:05 |
David Wang | ITE | Repair | TM4 | | Dan and I replaced flow wheel on ITE HVC2 water flow sensor. |
Dan and I replaced flow wheel on ITE HVC2 water flow sensor. The old wheel did rotate smoothly inside its SST case. The new wheel works fine. |
786
|
Thursday, November 13, 2014, 14:01 |
David Wang | ITW | Repair | TM1 | | I replaced flow wheel and coil on ITW MSP water flow sensor. |
I replaced flow wheel and coil on ITW MSP water flow sensor which is located in ITW pit. Before replacement, I checked the signal strength and frequency form e-board on this circuit. The signal was good in 10minutes watching. Still, I replaced them. The flow sensor works fine after replacement. I made a comment on Isac e-fault system about this issue. |
785
|
Thursday, November 13, 2014, 13:52 |
David Wang | ITW | Standard Operation | TM1 | ThO#1 | 5 Shielding blocks have been transferred from ITE to ITW. |
Dan and I transferred 5 shielding blocks from ITE to ITW. The ITW is configured to take proton beam. |
784
|
Thursday, November 06, 2014, 13:43 |
David Wang | Conditioning Station | Development | TM3 | | CS vacuum system has been connected to TM3. |
CS vacuum system has been connected to TM3 for control system test(Dave.Morris). |
783
|
Thursday, November 06, 2014, 08:55 |
David Wang | ITW | Repair | TM1 | ThO#1 | primary vacuum back up pressureITH CG1 ,CG2,CG4A were high. |
I found primary vacuum back up pressure ITH CG1, CG2, and CG4A were unusually high this morning. They should be about 10 -20 mtorr after one night pumping, but all of thier reading were 340-350-mtorr. Thease cause the current draw on primary turbo pumps were all over 2.0A(should be about 1.0A). I let Paul closed all BVs on primary side . The pressure dropped quickly to normal range after all BVs were closed. This shows the back up line are good. The problem are from one of the connections on primary BVs. I let Paul opened the BVs one by one,but the problem did not show again. Now ,the current draw on the turbo pumps are back to normal also.
I will keep monitoring the system and take a look on all KF25 clamps on BVs once I have a chance to access to ITW. |
782
|
Thursday, November 06, 2014, 08:07 |
David Wang | ITW | Standard Operation | TM1 | ThO#1 | TM1 has been connected in ITW. |
TM1 has been connected in ITW. All turbo pumps are started. The pumping down on ITW is good so far. The water is supplied to TM1 for HV conditioning. |
781
|
Wednesday, November 05, 2014, 14:21 |
Anders Mjos | Conditioning Station | Development | | | Jumper installed on TGHT, TBHT and COIL |
A copper bar jumper (ITD0488) was installed on the TGHT, TBHT and COIL conductors on the taregt hall side for TCS testing. |
Attachment 1: Jumper1.jpg
|
|
Attachment 2: Jumper2.jpg
|
|
780
|
Wednesday, November 05, 2014, 10:20 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ThO#1 | module move |
TM#1 with ThO#1 has been moved from the south hot cell to the west target station. |
779
|
Tuesday, November 04, 2014, 13:17 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | ThO#1 | TM1 w/ ThO#1 ready |
Tm1 with ThO#1 is buttoned up and ready for transport. |
778
|
Tuesday, November 04, 2014, 11:05 |
David Wang | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Leak check on TM1 HS water line withThO#1 installed. |
Chad and I leak checked HS line on TM1 with ThO#1 target installed. The LD pumped down to base leak rate 0.0xE-9 atm.cc/sec, base leak rate 0.0xE-4 torr. The pumping down process is normal. Chad sprayed helium on both VCR joints (each for 2 seconds) , and he did a flush spray around the target for 5 seconds. No any response had been found on LD during and after the spray( 40seconds waiting time). The target is leak tight. |
777
|
Monday, November 03, 2014, 13:47 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Electrical check |
TM#1 with ThO#1 electrical check see attatched PDF for details. |
Attachment 1: TM1_elec_check_ThO1_SHC.PDF
|
|
776
|
Monday, November 03, 2014, 11:16 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | ThO#1 | ThO#1 Installed |
ThO#1 has been installed onto TM1 and is ready for leak and electrical checking. High current fasteners torqued to 130 in lbs. |
775
|
Monday, November 03, 2014, 10:27 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | no target | module move |
TM#1 has been moved from the south west silo to the south hot cell. |
774
|
Wednesday, October 22, 2014, 13:05 |
Anders Mjos | Conditioning Station | Maintenance | | | Controls upgrade on TCS |
See work permit for details |
773
|
Wednesday, October 22, 2014, 09:41 |
David Wang | Conditioning Station | Development | TM3 | | TM3 has been disconnected at CS. |
TM3 has been disconnected at CS. It is vented and ready to move. |
772
|
Tuesday, October 21, 2014, 14:53 |
Travis Cave | Spent Target Vault | Standard Operation | | ZrC#6 | Spent target move |
ZrC#6 has been moved from the south hot cell and into storage. It was placed in pail 120 in slot 5C of the vault. For more details see PDF. |
Attachment 1: Vault_Storage_October_21_2014.pdf
|
|
771
|
Tuesday, October 21, 2014, 08:55 |
chad fisher | South Hot-Cell | Repair | | | Manipulator repair |
The east manipulator handle has been adjusted and is ready for use. |
770
|
Monday, October 20, 2014, 14:18 |
chad fisher | South Hot-Cell | Repair | | | Manipulator Repair |
The broken cable on the east manipulator has been replaced.
The handle will need some adjustments which will take place first thing tomorrow. |