Message ID: 837     Entry time: Thursday, January 29, 2015, 11:31
Author: chad fisher 
Category: South Hot-Cell 
Type: Repair 
Module: TM2 
Target/Number:  
Subject: TM2 Tray Build 

On Tuesday morning I attempted to complete assembly of the source tray for TM2 however discovered that 3 1/4-20 x 0.25 titanium helicoils had not been installed into the mounting plate as they should have been. Checked and asked around for them but to no avail. I have ordered some, they should have been here yesterday.

Also, I have noticed that the threaded portion of the target pins ITA0328A appear to be too long and as such may be (are indeed) touching the supports. I am going to remove 1/32" or appropriate to remedy this problem (drawing shows 0.035 clearance).

Attachment 1: TM2_Tray_20150126_112232.jpg  1.007 MB  | Show | Hide all