  IDdown Date Author Category Type Module Target/Number Subject
  878   Monday, March 30, 2015, 09:03 Anders MjosConditioning StationStandard OperationTM4Ta#45Ta#45 Conditionoing

Monday, March 30, 2015, 08:59: Reset chiller by switching on off power (fault 2)

Monday, March 30, 2015, 09:02: Switched on CHILL:CP2, TS5 at 34 C

Monday, March 30, 2015, 10:24 : Cage locked. EE to GND. BIAS and EL ON.

Troubleshooting BIAS current limiting. Turned out to be a EPICS initialization issue. Resolved by setting/changing the current limit again in EPICS.

Monday, March 30, 2015, 14:00: BIAS/EL 18 / 9 kV

Monday, March 30, 2015, 14:16: BIAS/EL 24 / 12 kV

Monday, March 30, 2015, 16:03: BIAS/EL 30 / 15 kV. Occasional sparking while stepping up since 26 kV

Monday, March 30, 2015, 16:13: BIAS/EL 30.8 / 15 kV. 110% of scheduled 28 kV. BIAS/EL 0.04 / 0.09 mA

Monday, March 30, 2015, 17:26 : Maintained BIAS over 1 hour. One spark after.

Monday, March 30, 2015, 17:27 : BIAS / EL off.


Tuesday, March 31, 2015, 08:12: Cage access. EE to EE PS. Cage locked.

Tuesday, March 31, 2015, 08:24: BIAS/EL/EE at 30.8 / 15 / 1 kV

Tuesday, March 31, 2015, 08:26 : EE to 2 kV, 1.96 mA

Tuesday, March 31, 2015, 08:46: No sparks for 20 min.

Tuesday, March 31, 2015, 08:48 : BIAS/EL/EE at 20 / 9.3 / 1.5 kV

Tuesday, March 31, 2015, 08:57: Started auto ramping of heaters to 580 / 230 A at 2 A/min.

Tuesday, March 31, 2015, 10:54: TBHT at 230 A

Tuesday, March 31, 2015, 14:05: TGHT at 580 A

Tuesday, March 31, 2015, 14:21: BIAS/EL/EE to 30.8 / 15 / 2 kV

Tuesday, March 31, 2015, 17:48: Source stable for 4h

Tuesday, March 31, 2015, 18:20: Lowered IAS/EL/EE to 20 / 9.3 / 1.5 kV. IG2 at 6.2E-6 T

Tuesday, March 31, 2015, 21:27: Starting ramp down at 15/12 A/min. IG2 at 6.8E-6 T

Tuesday, March 31, 2015, 21:51: BIAS/EL/EE to zero and off. IG2 at 6.6E-6 T

Tuesday, March 31, 2015, 22:17: TGHT and TBHT off

Tuesday, March 31, 2015, 22:41: Turbos off.

Tuesday, March 31, 2015, 22:42: Water off.

Attachment 1: Ta#45_Conditioning.docx
  877   Monday, March 30, 2015, 07:38 David WangITEStandard OperationTM4 TH Shut Down Activities Schedule Feb 23th- Apr 15th update

Updated schedule this morning after last Fridays ISAC facility support group meeting.

Updated schedule on 2015-April -02. See attachments 3,4. The scheduled all shut down jobs are done on time.The TM2 move to SHC will be delayed to May.There will be a new beam running time TH activities schedule (start from April 15) replacing this shut down schedule on next time  weekly update.

Attachment 1: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 2: Target_Hall_shut_down_activities.mpp
Attachment 3: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 4: Target_Hall_shut_down_activities.mpp
  876   Friday, March 27, 2015, 11:29 David WangConditioning StationStandard OperationTM4Ta#45TM4 is connected at CS

TM4 has been connected at CS which includes high current cables, water lines, EE cable, and Enizel lens cable. The HV cover has been  installed onto the TM4 service cap.The CS water system is started. All water signals are good so far.   Anders will start  HV and heaters conditioning on next Monday.

Attachment 1: 010.JPG
010.JPG
Attachment 2: 013.JPG
013.JPG
Attachment 3: 012.JPG
012.JPG
  875   Friday, March 27, 2015, 10:03 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CS

The helium pressure test on TM4 HS line at conditioning station is done. No leak. I also leak checked all vacuum seals on TM4 service cap. They are all good.

Attachment 1: 001.JPG
001.JPG
Attachment 2: 005.JPG
005.JPG
Attachment 3: 006.JPG
006.JPG
  874   Thursday, March 26, 2015, 09:20 Travis CaveConditioning StationStandard OperationTM4Ta#45Electrical check

Electrical check of TM#4 with Ta#45 at the conditioning station, see attached pdf for details.

Attachment 1: TM4_Ta#45_tgt_elec_chk_CS.PDF
TM4_Ta#45_tgt_elec_chk_CS.PDF
  873   Wednesday, March 25, 2015, 14:34 David WangConditioning StationStandard OperationTM4Ta#45 TM4 and CS turbo- pumps are started .

I connected TM4 and CS vacuum system after TM4 move. CS roughing pump was started first this morning. Later, Anders, Bill and I started 3 turbo pumps on TM4 and CS. The pumping down is good so far. The CS vacuum system ion gauges are turned on also.

  872   Wednesday, March 25, 2015, 14:25 David WangSouth Hot-CellStandard OperationTM4Ta#45Leak check on TM4 HS water line with new Ta#45 target. at SHC

Chad and I leak checked TM4 HS water line with new Ta#45 target installed at SHC. Leak detector base leak rate 0.0Xe-9 atm.cc/sec, base pressure 0.0Xe-4 torr. Chad sprayed helium twice on each of HS 2 VCR joints.No leak has been found. The joints are leak tight. The helium pressure test  will be done at CS later.

  871   Wednesday, March 25, 2015, 10:37 chad fisherSouth Hot-CellDevelopment  TM2 optics tray build

TM2 optics tray build is continuing. Going well. Hope to have assembly and alignment finished by Friday.

 

 

Attachment 1: 20150325_101718.jpg
20150325_101718.jpg
Attachment 2: 20150325_101735.jpg
20150325_101735.jpg
Attachment 3: 20150325_102024.jpg
20150325_102024.jpg
  870   Tuesday, March 24, 2015, 13:57 Travis CaveSouth Hot-CellStandard OperationTM4Ta#45Electrical check

TM#4 electrical checks with and without the target installed, installed target is Ta#45.

Attachment 1: TM4_no_tgt_elec_chk_CS.PDF
TM4_no_tgt_elec_chk_CS.PDF
Attachment 2: TM4_Ta45_elec_chk_SHC.PDF
TM4_Ta45_elec_chk_SHC.PDF
  869   Tuesday, March 24, 2015, 09:47 chad fisherSouth Hot-CellStandard OperationTM4Ta#45Ta#45 installed

Ta#45 has been installed onto TM4 and is ready for leak and electrical check. High current fasteners torqued to 130 in.lbs.

 

 

  868   Tuesday, March 24, 2015, 08:46 Travis CaveConditioning StationStandard OperationTM4No targetModule move

TM#4  with no target has been moved from conditioning station to the south hot cell.

  867   Monday, March 23, 2015, 14:03 chad fisherSouth Hot-CellStandard Operation Ta#45Ta#45 inserted into hot cell

Ta#45 has been inserted into the hot cell. Swipe taken of inner tool port area: 100000 counts/min.

  866   Monday, March 23, 2015, 07:56 David WangITEStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th update

This schedule is following Dons schedule on module moves. See attachments for updating.

2015-03-27: Weekly update the schedule. The shut down job is close to the end. See attachment 3, 4.

Attachment 1: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 2: Target_Hall_shut_down_activities.mpp
Attachment 3: Target_Hall_shut_down_activities.pdf
Target_Hall_shut_down_activities.pdf Target_Hall_shut_down_activities.pdf
Attachment 4: Target_Hall_shut_down_activities.mpp
  865   Friday, March 20, 2015, 13:37 chad fisherSouth Hot-CellDevelopment  TM2 Optics Tray

Final assembly and alignment of TM2 optics tray continued today. Front section is "aligned".

Attachment 1: 20150320_113132[2].jpg
20150320_113132[2].jpg
Attachment 2: 20150320_113018_1[1].jpg
20150320_113018_1[1].jpg
  864   Tuesday, March 17, 2015, 10:33 Travis CaveSpent Target VaultStandard Operation UC#11Spent Target Move

The spent UC#11 has benn moved from the south hot cell to the spent target vault. See attached PDF for details.

Attachment 1: Vault_Storage_March_17_2015.pdf
Vault_Storage_March_17_2015.pdf Vault_Storage_March_17_2015.pdf Vault_Storage_March_17_2015.pdf Vault_Storage_March_17_2015.pdf
  863   Monday, March 16, 2015, 14:16 Travis CaveConditioning StationStandard OperationTM4No targetModule move

TM#4 from south hot cell to the conditioning station no target is attached to the module.

  862   Monday, March 16, 2015, 09:41 Travis CaveITEStandard OperationTM4UC#11Module move

TM#4 with UC#11 moved from the east target station to the south hot cell.

  861   Friday, March 13, 2015, 13:36 Travis CaveSpent Target VaultStandard Operation ThO#1Spent Target Move

The ThO#1 has been placed in the storage vault placed in pail #122 in spot 2B of the vault. It was 6.2mSv/hr upon removal from the south hot cell. see attached PDF for details.

Attachment 1: Storage_Vault_March_13_2015.pdf
Storage_Vault_March_13_2015.pdf Storage_Vault_March_13_2015.pdf Storage_Vault_March_13_2015.pdf Storage_Vault_March_13_2015.pdf
  860   Thursday, March 12, 2015, 13:33 Anders MjosSouth Hot-CellStandard OperationTM1ThO#1Target inspection

Chad, Anders and Alex inspected the target this morning. The target had no significant visible damage to the container. Some material was deposited on the Extraction Electrode.

Phots on DocuShare

  859   Thursday, March 12, 2015, 13:04 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITE to ITW.

5 shielding blocks have been transferred from ITE to ITW for next week TM4 move.