  RH-ISAC, Page 98 of 138  Not logged in ELOG logo
ID Date Authordown Category Type Module Target/Number Subject
  2042   Tuesday, January 07, 2020, 09:37 David WangITWStandard Operation  5 shielding blocks are moved out of ITW top.

5 shielding blocks are moved out of itw top.

  2043   Wednesday, January 08, 2020, 10:34 David WangAssembly/Bench TestDevelopment  Module lifting assembly ITA0490

The second module lifting assembly ITA0490 is moved into TH and installed onto TM3 . It will stay with TM3. I adjusted the  CofG on the assembly. It is same to the first lifting assembly we are using now. After adjustment, The installation of assembly on TM3 are smooth. 

  2045   Thursday, January 09, 2020, 14:14 David WangConditioning StationStandard OperationTM3 Start of TCS roughing pump for TM3.

I started TCS roughing pump. TM3 TP1 and TP2 will be started tomorrow morning.

  2046   Friday, January 10, 2020, 10:26 David WangITEStandard Operation  ITE water signal inerlock check.

ITE water  signal interlock   check is done.  Everything is good. It is a annual check we do in winter shut down time.

  2048   Tuesday, January 14, 2020, 10:12 David WangConditioning StationStandard OperationTM3 Helium spray leak check on TCS.

Using a long pole with a probe to spray helium on TCS vacuum seals and joints which are installed in  TCS service pit. No response has been found on leak detector during leak check. TCS is leak free.

  2049   Tuesday, January 14, 2020, 10:19 David WangConditioning StationStandard OperationTM3 TCS vacuum system is switched off.

TM3 TP1 and TP2 work  fine in past 4 days. During operation, The current draw on pumps were 0.7A to 0.8 A. TM3 will be moved back to silo tomorrow.

  2051   Friday, January 24, 2020, 08:19 David WangITWStandard OperationTM4 ITW water signal interlock check.

ITW water signal interlock check is done. Everything works fine. ITW 2A2 tank water signal is broken and is not ok on XT2A2  page. I will fix it next week.

  2052   Monday, January 27, 2020, 10:40 David WangCoolingMaintenance  ITE/ITW supply water presuure on dump circuits.

With both stations in operation,ITE dump supply gauge reading is 27 psi. ITW is 20 Psi.  I adjusted ITW dump pressure to 25 psi by changing the return line side pressure relieve valve.

ITE full operation+ ITW no TM: ITE dump pressure 27psi, ITW dump pressure 27psi.

2019-01-30: Water only supply to 2A beam lines only on both side, No TM2 and TM4 in water loop.  ITE dump pressure 27psi, ITW dump pressure 27psi.

  2053   Wednesday, January 29, 2020, 12:37 David WangITEStandard OperationTM2 ITE primary/secondary vacuum vessel leak check.

Leak check on ITE vacuum vessel is done. LD base leak rate 0.0XE-9atm.cc/sec. base pressure 0.0Xe-4torr. Sprayed helium on all ITE primary and secondary vacuum vessel seals(including TM2). No leak . Also,70psi helium  pressurized TM2 waterlines inside the module for each circuit 3 minutes. No leak on all operating TM2 waterlines.  

  2054   Thursday, January 30, 2020, 10:22 David WangITWStandard OperationTM4  TM4 water lines helium pressure leak check.

  TM4 internal water lines helium pressure leak check at ITW : 70psi helium 5 minutes on  each circuits. Base leak rate 0.0X E-9 atm.cc/sec. Base pressure 0.0X E-4torr. Only B line(Oven -) has a tiny 1.5Xe-9 atm.cc/sec response on LD during the check . All others all perfect good. 

  2055   Thursday, January 30, 2020, 12:06 David WangITWStandard OperationTM4 ITW primary and secondary vacuum seals leak check.

Connected LD to ITW(TM4) TP1. Base LR 0.0Xe-9 atm.cc/sec. Base pressure 0.0Xe-4 torr. All ITW primary and secondary air to vacuum seals are helium spray checked. There is a 5XE-9 atm.cc/sec leak on  exit2 module top cover plate o-ring seal. The location is on west  side, south corner of the plate. Hi- vacuum resin are sprayed to leak area, and leak checked  again. The leak is gone.   The other seals on ITW vacuum vessel are good.

 

  2056   Monday, February 03, 2020, 09:10 David WangITWStandard OperationTM4 ITW TPs are switched off. started of ITW argon venting.

ITW is argon venting now.

Argon venting of ITW is done. It took about 4.0 to 4.5 hours to vent the ITW with 2-3 psi argon. The CG4 and CG4S showed 35 to 36 torr on epic page when mechanical gauge is 760torr in electrical. Argon gas bottle is closed in electrical room.

  2057   Monday, February 03, 2020, 09:14 David WangITWStandard OperationTM4UCx 29TM4 UCx 29 disconnection checklist

TM4 has been disconnected in ITW. See attachment checklist.

Attachment 1: UCx29__disconnection_checklist.pdf
UCx29__disconnection_checklist.pdf UCx29__disconnection_checklist.pdf UCx29__disconnection_checklist.pdf
  2060   Wednesday, February 05, 2020, 10:49 David WangConditioning StationStandard OperationTM4 Remove of TM4 from SHC to TCS.

TM4 has been moved from SHC to TCS. No target on module. The move is successful.

  2061   Wednesday, February 05, 2020, 10:54 David WangConditioning StationStandard OperationTM4 Roughing out TM4 at TCS.

TCS MP1 is started to rough out TM4 and TCS. TCS and TM4 will be under roughing only today and tomorrow. No plan to start TCS and TM4 turbo pumps this time.

  2062   Wednesday, February 05, 2020, 11:03 David WangSouth Hot-CellStandard OperationTM4UCx 29UCx 29 post run electrical check

UCx 29 TM4 post run electrical check is done before target is removed. Everything is normal on measurements.

Attachment 1: UCx29_post_run_electrical_check..pdf
UCx29_post_run_electrical_check..pdf
  2067   Friday, February 14, 2020, 14:06 David WangConditioning StationStandard OperationTM4 TCS vacuum system and water sytem are switched on.

All turbo pumps are started. 

  2068   Friday, February 14, 2020, 14:13 David WangSouth Hot-CellStandard OperationTM4 SIS dummy target for IGLIS TM4 electrical check

Electrical check and HS, window leak check result at SHC. See attachment.

Attachment 1: Dumm_SIS_target_for_IGLIS_test_on_TM4.pdf
Dumm_SIS_target_for_IGLIS_test_on_TM4.pdf
  2069   Thursday, February 20, 2020, 09:27 David WangSpent Target VaultStandard Operation  Inventory of mini storage and vault.

Repacked nSiC#1 in SHC and moved it to mini storage vault. Transferred UCx26 and UCx28# from vault to mini-storage. See attachment for vault and mini-storage inventory.

Attachment 1: Mini_Vault_2020-02-20.pdf
Mini_Vault_2020-02-20.pdf
Attachment 2: Vault__2020-02-20.pdf
Vault__2020-02-20.pdf
  2070   Wednesday, February 26, 2020, 08:45 David WangConditioning StationStandard OperationTM4 Remove of TM4 from TCS to SW silo

TM4 has been moved from TCS to SW silo. The move is fine.