  RH-ISAC, Page 89 of 140  Not logged in ELOG logo
Entry  Tuesday, February 17, 2015, 13:06, Anders Mjos, ITE, Development, , , Resistance measured of TGHT and TBHT lines to ITE 002.JPGResistance_from_Electrical_Room_to_Target_Station.xlsx
Entry  Tuesday, February 17, 2015, 13:07, Anders Mjos, ITW, Development, , , Resistance measured of TGHT and TBHT lines to ITW 
Entry  Monday, February 23, 2015, 12:28, David Wang, ITE, Maintenance, , , 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. 2015_shut_down_ITE_water_sensors__replacements.pdf
Entry  Wednesday, February 25, 2015, 10:44, David Wang, ITW, Maintenance, , , 2015 shut dwon ITW water sensor coils and pedal wheels replacement 2015_shut_down_ITW_water_sensors__replacements.pdf
Entry  Thursday, February 26, 2015, 09:22, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Mar 25th Target_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdf
Entry  Friday, February 27, 2015, 09:34, chad fisher, South Hot-Cell, Maintenance, , , Hot cell Entry February 25 2015 ISAC_South_Hot_Cell_Entry.pdf
Entry  Thursday, March 05, 2015, 06:44, David Wang, ITE, Maintenance, TM4, , 5 Shielding blocks have been moved to ITE. 
Entry  Thursday, March 05, 2015, 07:17, David Wang, ITW, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update 6x
Entry  Thursday, March 05, 2015, 14:30, chad fisher, South Hot-Cell, Development, , , Dissection Box 20150305_142144.jpg
Entry  Monday, March 09, 2015, 09:42, chad fisher, South Hot-Cell, Development, , , Hot Cell Table Swiping 
Entry  Thursday, March 12, 2015, 13:04, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITE to ITW. 
Entry  Friday, March 20, 2015, 13:37, chad fisher, South Hot-Cell, Development, , , TM2 Optics Tray 20150320_113132[2].jpg20150320_113018_1[1].jpg
Entry  Monday, March 23, 2015, 07:56, David Wang, ITE, Standard Operation, , , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp
Entry  Wednesday, March 25, 2015, 10:37, chad fisher, South Hot-Cell, Development, , , TM2 optics tray build 20150325_101718.jpg20150325_101735.jpg20150325_102024.jpg
Entry  Monday, March 30, 2015, 07:38, David Wang, ITE, Standard Operation, TM4, , TH Shut Down Activities Schedule Feb 23th- Apr 15th update Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp
Entry  Tuesday, March 31, 2015, 11:36, chad fisher, South Hot-Cell, Development, TM2, , TM2 Optics Tray Complete 20150331_OPTICS_FRONT.jpg20150331_OPTICS_MIDDLE.jpg20150331_OPTICS_BACK.jpg
Entry  Wednesday, April 01, 2015, 13:08, David Wang, ITE, Standard Operation, TM4, , Replaced ITE tank to module 42X0.275 o-ring 001.JPG002.JPG004.JPG005.JPG006.JPG
Entry  Friday, April 10, 2015, 15:40, David Wang, ITE, Standard Operation, TM4, , 5 Shielding blocks have been transferred from ITW to ITE. 
Entry  Monday, April 13, 2015, 08:59, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - June 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Entry  Wednesday, April 15, 2015, 09:01, Anders Mjos, Conditioning Station, Development, , , Archiver variables added by Controls 