1179
|
Wednesday, March 23, 2016, 11:32 |
David Wang | South Hot-Cell | Repair | TM2 | | TM2 Helium spray leak check on GE and MSP lines at SHC | Chad and I did the helium spray
leak check on TM2 GE and MSP water lines
at SHC this morning. We confirmed the GE |
|
1180
|
Thursday, March 24, 2016, 13:15 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 and TCS vacuum system has been connected | TM1 and TCS vacuum system have been connected.
All turbo-pumps are started. The pumping
down is fine. |
|
1182
|
Tuesday, March 29, 2016, 08:38 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 water lines helium pressure check at TCS | TM1 water lines helium pressure check at
TCS is done. 70 psi helium was applied to
water circuits. Leak detector base leak rate |
    |
1183
|
Wednesday, March 30, 2016, 08:40 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | update the schedule according to changes.See
attachment1, 2. |
 |
1185
|
Wednesday, March 30, 2016, 15:49 |
David Wang | Assembly/Bench Test | Repair | TM2 | | TM2 Helium spray leak check on solder stems inside service cap on the top of SW silo. | On each water circuit in side the service
cap, there are 4 soldering stems which two
of them are inside blue nylon insulator and |
7x |
1188
|
Friday, April 01, 2016, 14:41 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 and TCS vacuum system has been connected. TCS control page white out. | I can not start the TCS pumps due to control
page white out. Control group is working
on this issue. |
|
1189
|
Monday, April 04, 2016, 11:14 |
David Wang | Conditioning Station | Standard Operation | TM1 | | Helium pressure test on TM1 HS line at CS | New UCx target is installed on the module.
70psi helium,3 minutes. NO response on LD.
LD is pumped to bottom LR and LP during test. |
|
1190
|
Tuesday, April 05, 2016, 07:12 |
David Wang | Conditioning Station | Standard Operation | TM1 | UC#15 | stop CS vacuum pumps. | Stop TCS vacuum pumps . Preparing argon
venting on TM1 and TCS.
7:34 AM, Disconnected TM1 at TCS, |
|
1192
|
Tuesday, April 05, 2016, 12:36 |
David Wang | ITW | Standard Operation | TM1 | | TM1 vacuum system has been connected in ITW. | All turbo -pumps are started. |
|
1193
|
Tuesday, April 05, 2016, 12:40 |
David Wang | ITE | Standard Operation | TM4 | | I stopped ITE turbo pumps this morning | The ITE and TM4 have been vented with Argon
. TM4 vacuum system is disconnected in ITE. |
|
1198
|
Friday, April 08, 2016, 07:10 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 vacuum has been connected in ITE. | All turbo pumps are started yesterday.
The pumping down is good over night. |
|
1199
|
Friday, April 08, 2016, 07:13 |
David Wang | ITW | Standard Operation | TM1 | UCx15 | TM1 has been connected in ITW. | After ITW HV test is done, TM1 has been
connected to ITW. Water signals are checked
in electrical room. They are good. |
|
1201
|
Friday, April 08, 2016, 08:48 |
David Wang | ITW | Standard Operation | | | ITW water signal interlock check. | I did a ITW water signals interlock check
with ISAC opp. They are checked once a year
before first beam on. |
|
1202
|
Friday, April 08, 2016, 13:16 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | Update schedule weekly .see attachment
1,2 |
 |
1203
|
Monday, April 11, 2016, 09:42 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Helium pressure test on TM4 HS line at CS with new Lp Ta target | 70 psi helium , 2 minutes. Base leak rate
0.0x E-9 atm.cc/sec. base pressure 0.0XE-4
torr. no response on LD.The line is good. |
|
1205
|
Monday, April 11, 2016, 13:44 |
David Wang | Conditioning Station | Standard Operation | TM4 | | I stopped TCS and TM4 vacuum pumps. | The TM4 is still under vacuum at TCS. It
will be vented tomorrow morning.
I disconnected TM4 vacuum system |
|
1207
|
Tuesday, April 12, 2016, 11:41 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been connected in ITE. | Tm4 has been connected in ITE. The ITE
and TM4 is under roughing now. ITE
Turbo-pumps have been started. Everything |
|
1209
|
Wednesday, April 13, 2016, 10:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TCS is under roughing now. |
|
1210
|
Wednesday, April 13, 2016, 10:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TCS is under roughing now.
2016-04-14, Started TCS and TM2 turbo-pumps
yesterday afternoon. Overnight pumping down |
|
1212
|
Thursday, April 14, 2016, 12:56 |
David Wang | ITW | Standard Operation | TM1 | | 5 shielding blocks have been moved to ITW. | The ITW is configured to take proton beam. |
|