1201
|
Friday, April 08, 2016, 08:48 |
David Wang | ITW | Standard Operation | | | ITW water signal interlock check. | I did a ITW water signals interlock check
with ISAC opp. They are checked once a year
before first beam on. |
|
1202
|
Friday, April 08, 2016, 13:16 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule | Update schedule weekly .see attachment
1,2 |
|
1203
|
Monday, April 11, 2016, 09:42 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Helium pressure test on TM4 HS line at CS with new Lp Ta target | 70 psi helium , 2 minutes. Base leak rate
0.0x E-9 atm.cc/sec. base pressure 0.0XE-4
torr. no response on LD.The line is good. |
|
1205
|
Monday, April 11, 2016, 13:44 |
David Wang | Conditioning Station | Standard Operation | TM4 | | I stopped TCS and TM4 vacuum pumps. | The TM4 is still under vacuum at TCS. It
will be vented tomorrow morning.
I disconnected TM4 vacuum system |
|
1207
|
Tuesday, April 12, 2016, 11:41 |
David Wang | ITE | Standard Operation | TM4 | | TM4 has been connected in ITE. | Tm4 has been connected in ITE. The ITE
and TM4 is under roughing now. ITE
Turbo-pumps have been started. Everything |
|
1209
|
Wednesday, April 13, 2016, 10:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TCS is under roughing now. |
|
1210
|
Wednesday, April 13, 2016, 10:46 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TCS is under roughing now.
2016-04-14, Started TCS and TM2 turbo-pumps
yesterday afternoon. Overnight pumping down |
|
1212
|
Thursday, April 14, 2016, 12:56 |
David Wang | ITW | Standard Operation | TM1 | | 5 shielding blocks have been moved to ITW. | The ITW is configured to take proton beam. |
|
1213
|
Monday, April 18, 2016, 09:07 |
David Wang | Conditioning Station | Repair | TM2 | | venting TCS with argon. | Anders reported a possible air leak on
TM2 and TCS by watching RGA this morning.
I found the quick connector on F terminal |
|
1214
|
Friday, April 22, 2016, 14:07 |
David Wang | Conditioning Station | Standard Operation | TM2 | | 2016 Winter Shut Down Target Hall Schedule | Weekly update.This is the last update on
2016 winter shut down schedule. The new TH
schedule for beam130 will be posted |
|
1215
|
Monday, April 25, 2016, 12:18 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) | Post MS project and Excel
target hall schedule for beam schedule 130
see attachments 1,2 |
7x |
1216
|
Tuesday, April 26, 2016, 10:47 |
David Wang | Conditioning Station | Repair | TM2 | | TM2 leak check at TCS, water test. | The following water circuits in TM2 are
connected at TCS and running with water
now : target oven+ - ( one circuit), tube |
|
1217
|
Thursday, April 28, 2016, 06:28 |
David Wang | Conditioning Station | Maintenance | TM2 | | TCS water system are turned off. | TCS water system worked fine overnight.
I turned off TCS water system at 6:16 AM
this morning. Start of purging TM2 water |
|
1218
|
Friday, April 29, 2016, 08:01 |
David Wang | Conditioning Station | Maintenance | TM2 | | TM2 leak check at TCS, helium pressure test | Anders and I finished the most part of
TM2 water lines helium pressure test yesterday.I
list the system parameters and test result |
|
1219
|
Friday, April 29, 2016, 10:06 |
David Wang | Conditioning Station | Standard Operation | TM2 | | I switched off TCS and TM2 vacuum pumps. | I switched off TCS and TM2 vacuum
pumps. The TM2 will be disconnected at TCS
today and moved to silo on next Monday. |
|
1222
|
Wednesday, May 04, 2016, 12:01 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall schedule for beam schedule 130 (Apr- Sep) | Update schedule weekly. See attachment
1,2,3. |
|
1223
|
Monday, May 09, 2016, 08:43 |
David Wang | Conditioning Station | Repair | TM3 | | I reinstalled all the side panel on TM3 service cap. | They were moved for TM3 inspection job
last week. All the bolts on the panel are
hand tight only now since they will be removed |
|
1226
|
Tuesday, May 10, 2016, 13:54 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on window line and HS line. | Chad and I leak checked the TM2 HS and
window lines after new target installation.
The window line was very easy pumped down |
|
1229
|
Wednesday, May 11, 2016, 13:15 |
David Wang | Conditioning Station | Maintenance | TM2 | | TCS tank top flange seal is changed this morning | I changed TCS tank top flange seal(o-ring
42.00"ID X 0.275" DIA) this morning
before TM2 was moved to TCS. |
|
1230
|
Wednesday, May 11, 2016, 13:16 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | TM2 and TCS vacuum system has been connected.
I started all turbo pumps. Everything is
good so far. |
|