ID Date Author Category Type Module Target/Number Subject
  1108   Tuesday, October 20, 2015, 12:49 Dan McDonaldITWStandard Operation SiC#32Tm2 hook up In ITW

Lower and disconnect TM2 from crane in ITW, proceed with hooking up TM2 as per checklist with Anders. Double check flow meters and coils, reset TP1 and TP2

  1107   Tuesday, October 20, 2015, 10:18 Travis CaveITWStandard OperationTM2SiC#32Module moved

TM#2 with SiC#32 has been moved from the south hot cell to the west target station.

  1106   Monday, October 19, 2015, 15:52 Anders MjosSouth Hot-CellStandard OperationTM2SiC#32Electrical and leak check

 An electrical check was completed by Travis C and Anders M. Note ~250 kOhm between Target and 60 kV common. Leak check was done by Dan M and Chad F on HS and Window circuits. No leaks found

  1105   Monday, October 19, 2015, 11:53 chad fisherSouth Hot-CellStandard OperationTM2SiC#32SiC#32 installed on TM2

SiC#32 has been installed on TM2. High current fasteners torqued to 130 in lbs.

  1104   Thursday, October 15, 2015, 14:17 chad fisherSouth Hot-CellRepairTM2 Anode Connector Install and adjustment

The TM2 containment box was removed this morning for installation of the 9 pin connector...connection.

The 9 pin connector copper tube connection was made and Anders advised on routing of the cable to the banana plug water block connection.

Short was diagnosed (short disappeared when water block was pushed slightly towards center of module) and thicker Ultem spacer installed and tested again. All good.

  1103   Thursday, October 15, 2015, 08:07 David WangSouth Hot-CellStandard OperationTM2no targetTM2 no target electrical check at SHC.

I did a TM2 no target electrical check at SHC this morning. A to RU at 500v  is 250K which is low.   anode- x pin is dead short to 60kv bias. RU is dead short to 60kv bias( as before).   see attachment

  1102   Wednesday, October 14, 2015, 14:49 David WangSouth Hot-CellStandard OperationTM2 Install new high current cables to TM2

I installed a set of new high current cables for TM2 Febiad run. The top of TM2  is configured to Febiad mode. See attachments

  1101   Wednesday, October 14, 2015, 14:03 chad fisherSouth Hot-CellStandard OperationTM2ZrC#7ZrC#7 removed

ZrC#7 has been removed from TM2. Everything looks good.

  1100   Wednesday, October 14, 2015, 12:48 David WangSouth Hot-CellStandard OperationTM2ZrC#7TM2 ZrC#7 after run electrical check at SHC.

I did an electrical check on TM2 with ZrC #7 on it. The EE is short to 60KV bias. See attachment

  1099   Wednesday, October 14, 2015, 12:44 David WangITWStandard OperationTM2ZrC#7TM2 has been moved from ITW to SHC

Bill and I remotely removed TM2 from ITW to SHC. The move is smooth.

  1098   Wednesday, October 14, 2015, 12:42 David WangITWStandard OperationTM2ZrC#7TM2 has been disconnected in ITW

Dan and I disconnected TM2 in ITW this morning.

  1097   Tuesday, October 13, 2015, 10:53 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update schedule. TM3 evaluation schedule in Nov is added.  

update the schedule after  the cancellation of TM2 from SHC to CS trip.see attachments 3,4

  1096   Thursday, October 08, 2015, 14:08 David WangSouth Hot-CellStandard OperationTM3Dummy target febiad.TM3 has been moved from SHC to NW silo

Bill and I moved TM3 from SHC to NW silo with a dummy febiad target installed on it. The move is smooth.

  1095   Tuesday, October 06, 2015, 21:12 Aurelia LaxdalSouth Hot-CellRepairTM3 TM3 service cap inspection in target hall

David Wang and I did the service cap inspection in target hall: see WP I2015-10-06-10.<br>

Signs of sparking were seen underneath 3 insulators: E ("Cavity"), A ("Oven+") and B ("Oven -") at the pair water lines coming out of the  feed-through and going to the HV chase. Specifically one water line of E is very close to the feed-through insulator (2-3mm gap) and here the sparking sings are more prominent: see picture.

  1094   Tuesday, October 06, 2015, 13:25 David WangITEStandard OperationTM4 Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update target hall schedule. See attachment 1,2.

  1093   Tuesday, October 06, 2015, 13:00 David WangITERepairTM4  spark on top of TM4 in ITE

During the weekend condition The TM4 spark at 30KV without vacuum response. It is confirmed the spark is from the top TM4 this morning.The flexible cables in a  black wire sleeve which is used for febiad X pin connection drooped too close to the TM4 surface plate, and caused the sparking. The problem is fixed by Anders and David. The cables is put back where it should stay.  After test, no sparking on the top.

  1092   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1091   Tuesday, October 06, 2015, 12:50 David WangITEStandard OperationTM4Ta#465 Shielding blocks have been transferred from ITW to ITE.

The ITE is configured to take proton beam.

  1090   Monday, October 05, 2015, 10:19 Anders MjosConditioning StationMaintenance  Chiller maintenance

 will be performed Tuesday October 6th

Tuesday, October 06, 2015: Maintenance re-schedlued for Wednesday October 7th

  1089   Thursday, October 01, 2015, 09:18 Travis CaveSpent Target VaultStandard Operation  Targets transfered to mini storage.

In preparation for shipping of the spent targets five have been moved to the mini storage. The following target were moved to the mini storage, SiC#26, Ta#36, UC#9,10,11.