  502   Tuesday, October 15, 2013, 15:34 Bevan MossITEStandard OperationTM3 Blocks moved from ITW to ITE Blocks 1-4 have been moved from ITW
to ITE. Block 5 was moved to a storage area
as it will be in the way of the harp repair.
  
  503   Tuesday, October 15, 2013, 16:44 Grant MinorCraneRepair  Target Hall Crane - operational with temporary thermal sensor bypassE-mail correspondence on the Target Hall
crane fault diagnosis between October 11th
and 15th:
 ISAC_THall_Crane_elec_E5_1slash1_15Oct2013.pdf 
  505   Wednesday, October 16, 2013, 18:53 Grant MinorITERepair  ITE Harp 9 Removed & Blanked-Off - blocks NOT YET replacedThe blocks above the pre-separator section
of the ISAC beam lines     were removed today
in the Target Hall by Bevan Moss and Chad
 11x 
  506   Thursday, October 17, 2013, 10:24 chad fisherSouth Hot-CellRepairTM4 Coil Line RemovalThe containment box was removed from TM4
earlier this morning in preparation for removal
of the C2 circuit water lines, their
 TM4_C2_circuit.pdf 
  507   Thursday, October 17, 2013, 17:16 Grant MinorITERepair  Pre-Separator-area (ITE Harp 9) Blocks ReplacedThe pre-separator-area blocks were replaced
today by Bevan and Travis, with Grant present
for photos and observation.
 8x 
  508   Friday, October 18, 2013, 10:17 Bevan MossITWRepair  Paddle Wheel Yesterday I visually inspected the
paddle wheel and noticed that it was spinning
freely and constant. As the signal was intermittent
  
  509   Friday, October 18, 2013, 13:43 chad fisherSouth Hot-CellRepairTM4 C2 Circuit RemovalThe C2 circuit (coil 2) water lines and
blocks have been revoed from TM4.
Water block jig could not be used
 IMG_1224[1].JPGIMG_1227[1].JPGIMG_1230[1].JPG 
  510   Friday, October 18, 2013, 14:33 Bevan MossSouth Hot-CellStandard OperationTM4 Module move TM4 without a source tray was moved
from the SHC to the TCS.  All went well.
  
  511   Friday, October 18, 2013, 14:37 Bevan MossConditioning StationStandard OperationTM4 Roughing Started The roughing pump has been started.   
  513   Friday, October 18, 2013, 15:55 Bevan MossConditioning StationStandard OperationTM4 Turbo Pumps are on The Turbo pumps are now running on
TCS
  
  514   Monday, October 21, 2013, 10:52 Bevan MossConditioning StationStandard OperationTM4 Cooling On and Electrical Connections Made The electrical connection have been
made and cooling package was started at ~10:50am
today
  
  515   Monday, October 21, 2013, 12:29 Bevan MossConditioning StationRepairTM4 BIAS Canbus There is something wrong with the
BIAS canbus controller. It says that it is
not alive and has timed out. I have tried
  
  518   Tuesday, October 22, 2013, 16:52 Bevan MossConditioning StationRepair  Canbus base card for BIAS  The base card in the canbus BIAS
module was determined to be faulty. Dave
Morris removed a card VECC to repair the
  
  519   Tuesday, October 22, 2013, 17:04 Bevan MossConditioning StationStandard OperationTM4 HV testing This afternoon TM4 with the coil
removed was tested with HV. The EINZEL LENS
was first tested independently while the
 22102013_TM4_Coil_removed_EL_testing_(1).txt 
  520   Tuesday, October 22, 2013, 17:07 Bevan MossConditioning StationStandard Operation  services shut down The turbo pump, roughing pump, have
been turned off and the valves for venting
opened. The cooling package has also been
  
  527   Friday, October 25, 2013, 06:58 David WangSouth Hot-CellStandard OperationTM4 Leak check on TM4 target heat shieldMaico and I leak checked HS circuit after
Chad installed the target. The circuit was
a little bit difficult o pump down because
  
  531   Thursday, October 31, 2013, 10:36 David WangITWStandard OperationTM4 I moved 5 shielding blocks from ITE to ITW.I moved 5 shielding blocks from ITW to
ITE. The ITW  is configured to take
proton beam.
  
  534   Monday, November 04, 2013, 10:46 chad fisherSouth Hot-CellRepairTM2 TM2 ExplorationTM2 is now in the hot cell with the containment
box off for inspection and eventual blank
off off the water blocks.
 TM2_20131104.jpg 
  535   Tuesday, November 05, 2013, 10:37 chad fisherSouth Hot-CellRepairTM2 Thermocouple wire removalThe old thermocouple wire has been sucessfully
removed from the module.
Thanks Bevan, Travis and David.
  
  536   Wednesday, November 06, 2013, 10:41 David WangSouth Hot-CellRepairTM2 Installed 2 turbopumps on TM2Bevan and I installed 2 turbo pumps on
TM2. The o- ring flanges on TM2 had been
cleaned before the installation.
  