Friday, December 05, 2014, 15:41, Anders Mjos, Conditioning Station, Development, TM2, , RGA results 
|
Measurement taken at 14:25. IG2 at ~7.7E-6 T |
Thursday, September 26, 2013, 15:00, Bevan Moss, Conditioning Station, Standard Operation, TM3, NiO#2, RGA not connecting
|
Following the helium pressure test Don attempted to connect to the RGA via the network. He was unable to do so. This scan was desired so a pre
and post water scan could be compared to indicate if there was any leaking. It has been decided to carry on as the HV and HP tests are of greater importance.
Don will continue to investigate the RGA. Travis inspected from the conditioning station roof and determined that the RGA is getting power. |
Monday, May 11, 2015, 10:45, Anders Mjos, Conditioning Station, Maintenance, , , RGA electronics box installed
|
The communications chip has been replaced. The electronics box has been grounded (see attached pdf). |
Tuesday, August 09, 2016, 11:36, Anders Mjos, Conditioning Station, Maintenance, , , RGA and CG1S moved 
|
The locations (ports) for the RGA and CG1S was swapped today by Anders and Isaac to provide clearance for the North Hot Cell ventilation. Attached
photos show old and new locations. |
Wednesday, May 29, 2013, 12:07, chad fisher, South Hot-Cell, Development, , SiC#28 RFQ, RFQ Autopsy
|
Major portions of the RFQ target have now been sucessfully dismantled. More minor dismantling with conclude this afternoon. |
Tuesday, July 07, 2020, 17:43, Carla Babcock, ITE, Development, TM4, , RF tests on new IG-LIS wiring
|
Tested RF from RF driver into new IGLIS wires at ITE. Used 5V, 1MHz (2MHz setting because of internal halving issue).
As expected there was a very slight mismatch visible (original cable ~ 68 Ohms, new cable ~ 53 Ohms).
The matching resistor will be changed and it will be retested. |
Wednesday, July 08, 2015, 12:18, chad fisher, South Hot-Cell, Repair, TM2, , R U Coil line Removal
|
R U coil line removal started at 11:30. Water block jig installed and coil line disconnected from module. |
Monday, May 27, 2013, 10:35, Bevan Moss, Conditioning Station, Standard Operation, TM4, Ta #40, Pumps Started HV testing to follow
|
The pumps have been turned on at ~9:30 this morning. Current values are 6.61 Mohm TCS:DIC1 @19.4 C. HV testing will start momentarily. |
Tuesday, January 02, 2018, 14:47, Anders Mjos, Conditioning Station, Standard Operation, , , Pumping on secondary vacuum
|
Tuesday, January 02, 2018, 14:45: TP1S started |
Thursday, August 18, 2011, 16:07, Bevan Moss, Conditioning Station, Standard Operation, TM1, UCx#2, Pump Down
|
Pump down in the conditioning station started at ~2:40 for rough down. The turbo pumps were turned on at ~3:30 and at 3:52 the pressures were reading
as follows:
IMG in the containment box 9.2 x 10^-5 T |
Thursday, May 23, 2013, 14:12, Bevan Moss, Conditioning Station, Maintenance, , , Primary Circuit Drained and Flushed
|
Rob Walker has drained the primary side of the conditioning station. It will be flushed, filled and chemically treated. It was desired to
chemically treat the primary side before before but it took so long that sediment was found (things started to grow). |
Friday, August 05, 2016, 14:13, Isaac Earle, North Hot-Cell, Development, , , Preparations for NHC Ventilation Test
|
A hole was drilled in the NHC exhaust duct in the east end of the target hall above the hatch to the Ante Room. This will be used for measuring
NHC exhaust flow rate with a thermal anemometer. The hole was tapped and plugged with an NPT tap.
Flow was measured in the existing hole in the SHC exhaust duct in approximately the same location. Flow velocity was measured to be 1415 |
Thursday, March 30, 2023, 14:29, Frank Song, ITE/ITW, Development, , , Preparation of target stations for FEBIAD runs 
|
Helium cylinder and Argon cylinder are installed in both ITE/ITW faraday cages , regulator for outlet pressure are not set yet.
TO ITE : Argon bottle size 14"L x 4"D with SV2 connected at pressure 900 Psi ( 70 bar ) |
Wednesday, May 15, 2013, 10:17, Bevan Moss, Conditioning Station, Standard Operation, TM3, No Source Tray, Preliminary Results from HV testing  
|
Testing on TM3 without a source tray was completed on 13/05.2013. All items were tied to common and the water blocks were left open at the bottom
of the module. They were left with the quick connections at the top. The vacuum was in the low 10^-6T range so this was deemed acceptable. The cooling
lines withing the cage in the target hall were shorted so flow could continue. As you will see from the results a maximum of 44kV was achieved before a |
Thursday, March 07, 2019, 12:20, chad fisher, South Hot-Cell, Repair, TM2, , Pre-polishing pictures
|
Pictures of the water blocks before polishing can be found on docushare, collection 24400 |
Wednesday, January 29, 2025, 11:10, chad fisher, South Hot-Cell, Standard Operation, , , Pre-entry field Check
|
Fields in the hot cell were checked using a pole monitor. Field approximately in the area someone would stand to repair manip. is 3.8 mSv/h
Hot item found! Bag with extraction electrode and high current fasteners from an online target. |
Thursday, October 17, 2013, 17:16, Grant Minor, ITE, Repair, , , Pre-Separator-area (ITE Harp 9) Blocks Replaced 8x
|
The pre-separator-area blocks were replaced today by Bevan and Travis, with Grant present for photos and observation.
Photos are attached of each block replacement.
Some difficulty was encountered in replacing the "Layer #3" blocks (photo 9 attached). An interference occurred between the outside |
Thursday, December 21, 2017, 15:11, Anders Mjos, Conditioning Station, Maintenance, , , Powered down devices
|
Powered down mechanical pumps in ISAC-I Experimental hall, vacuum gauge and turbo pump controllers in ISAC-I B2 North Hot Cell service area |
Thursday, August 03, 2017, 17:08, Anders Mjos, Conditioning Station, Repair, TM2, , Power bump
|
Thursday, August 03, 2017, 17:08: Restarting vacuum and water system |
Thursday, November 03, 2022, 16:41, Carla Babcock, North Hot-Cell, Standard Operation, , UCx#39, Post irradiation inspection UCx#39
|
Did the PIE on UCx#39-IGLIS on Thursday Nov. 2 2022, couple pictures uploaded to docushare. Did not remove the target, just the heat shield cover.
Final electrical check on the module showed a dead short from TGHT/TBHT to HV common, which we did not see online. Seems like it must have occurred
after ramp down? It persisted on the target after we removed it from the module. We couldn't find any obvious contact points, because it seems it did not |
|