Wednesday, September 20, 2017, 13:38, chad fisher, South Hot-Cell, Repair, TM2, , TM2 Insulator replacement  
|
Broken insulators ITD0053 and ITD0054 have been uninstalled from TM2. |
Thursday, September 21, 2017, 10:48, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#53, Electrical Check  
|
Electrical checks of TM#2 with Ta#53 and also with out a target. |
Thursday, September 21, 2017, 12:07, chad fisher, South Hot-Cell, Repair, TM2, , Insulator Replacement
|
Insulators ITD0053 and 54 have been replaced. All fasteners torqued to 56 in lbs.
|
Thursday, September 21, 2017, 16:26, Anders Mjos, South Hot-Cell, Standard Operation, TM2, , Inspection of Source Tray
|
Chad and Anders inspected the Source Tray today using the camera in the hot cell. A dark spot was observed on one of the four insulators separating the Extraction Electrode from the Ground Electrode. This could potentially influence the high leakage current. Some discolored areas were also observed in the Service Tray, but these was present when the module was built. See attachment for details. |
Friday, September 22, 2017, 11:00, Travis Cave, South Hot-Cell, Standard Operation, TM2, no target, Electrical Check
|
Electrical check of TM#2 after the insulator change on thursday september 21. |
Friday, September 22, 2017, 12:13, David Wang, South Hot-Cell, Maintenance, TM2, , TM2 service cap inside inspection.    
|
Two side panels on TM2 service cap were removed for TM2 service cap inside inspection. A piece of cable tie was found inside cap closing to service tray entrance area. All blue nylon insulators are inspected. They look good. The broken cable tie is moved out of service cap.
Panels are installed back after the inspection.
See attachments |
Friday, September 22, 2017, 14:15, chad fisher, South Hot-Cell, Repair, TM2, , TM2 containment box off 
|
TM2 containment box has been removed. Found a piece of capton tape or tubing under table (see picture). |
Tuesday, September 26, 2017, 14:27, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#54, Electrical Check
|
Electrical check of TM#2 with Ta#54 at the south hot cell. See attached PDF for details. |
Wednesday, September 27, 2017, 08:00, chad fisher, South Hot-Cell, Standard Operation, TM2, Ta#54, Ta#54 installed
|
Containment box has been replaced onto TM2, interior of containment box vacuumed, and Ta#54 installed with new fasteners (high current torqued to 130 in lbs). |
Wednesday, September 27, 2017, 09:02, Travis Cave, Conditioning Station, Standard Operation, TM2, Ta#54, Module move
|
TM#2 with Ta#54 has been moved from the south hot cell to the conditioning station. |
Thursday, September 28, 2017, 10:50, David Wang, Conditioning Station, Standard Operation, TM2, , Helium pressure test on TM2 window and HS water lines at TCS.
|
I did helium pressure test on TM2 containment box window and HS line at TCS. @ 70psi helium for 3 minutes, HS:2.2XE-7 atm.cc/sec., Window:1.2XE-7 atm.cc/sec. There is no change on HS. But LR on window is bigger than before that was in E -9atm.cc/sec range. |
Thursday, September 28, 2017, 15:34, Anders Mjos, Conditioning Station, Development, TM2, , Changes to MP3 startup
|
Due to problems with the regulating valve WPV1, the VFD (Variable Frequency Drive) for the pump has been programmed to do a slow (2 min) ramp up. WPV1 has been bypassed and left fully opened. Work was done by Dave Morris |
Thursday, September 28, 2017, 17:44, Anders Mjos, Conditioning Station, Standard Operation, TM2, Ta#54, Conditioning Ta#54 
|
Thursday, September 28, 2017
Cooling water not yet connected to TM.
High leakage current still observed. 200 uA at 22 kV. Did not go past 25 kV.
Friday, September 29, 2017, 14:05: Started heater ramping to 580 / 200 A at 1 A/min
Friday, September 29, 2017, 14:09: BIAS / EZL / EE at 20 / 10 / 1.5 kV. BIAS current at 90 uA
Monday, October 02, 2017, 10:29: Accidentally set BIAS current limit to 0 A (step size too large) at 28 kV. This also caused the TGHT to got to 0 A. Recovered to 580 A in 10 - 15 s.
Monday, October 02, 2017, 12:07: Ramping down heaters at 2 A / min |
Tuesday, October 03, 2017, 09:29, Travis Cave, ITW, Standard Operation, TM2, Ta#54, Module move
|
TM#2 with Ta#54 has been moved from the conditioning station to the west target station. |
Tuesday, November 07, 2017, 10:11, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#54, Module move
|
TM#2 with Ta#54 has been moved from the west target station to the south hot cell. |
Thursday, November 09, 2017, 09:34, David Wang, Conditioning Station, Standard Operation, TM2, Ta#55, Leak check on TM2 HS line at SHC and TCS.
|
The TM2 HS line was leak checked at SHC yesterday . 0.9xE-9 atm.cc/sec.Helium sprayed by Chad, NO leak. It was helium pressurized at TCS this morning. Leak rat:2.5 XE-7 atm.c/sec. The result is same as last time check. No concern. |
Thursday, November 09, 2017, 09:35, David Wang, Conditioning Station, Standard Operation, TM2, Ta#55, TM2 has been connected at TCS
|
TCS vacuum system and water system have been started as well. Everything looks fine. |
Thursday, November 09, 2017, 10:39, Anders Mjos, Conditioning Station, Standard Operation, TM2, Ta#55, Conditioning Ta#55
|
Thursday, November 09, 2017, 10:40: BIAS / EL to 30 / 15 kV. 400 uA on BIAS
Bias was stable for 1 hour. Handed over to RIB ops for heater conditioning. |
Monday, November 13, 2017, 13:39, Travis Cave, South Hot-Cell, Standard Operation, TM2, Ta#54 and #55, Electrical Check  
|
The results of the various electrical check done on the target module on November 7th and 8th of 2017. Checks were done with the old Ta#54 target without a target and finally with the new Ta#55 target. See the attached PDF for results. |
Tuesday, November 14, 2017, 10:01, Travis Cave, ITW, Standard Operation, TM2, Ta#55, Module move
|
TM#2 with Ta#55 has been moved from the conditioning station to the west target station. The field was measured on the access panel to the service chase and the field was found to be 430uSv/hr at one meter from the module. |
|