  124   Monday, June 11, 2012, 10:52 Travis CaveSpent Target VaultStandard Operation Nb#6Spent target moveThe Nb#6 target has been moved from the
south hot cell into storage. It was place
in pail #95 and is in slot 5C of the vault.
 Vault_Storage_June_11_2012.pdf 
  125   Monday, June 11, 2012, 14:14 Travis CaveConditioning StationStandard OperationTM1Ta#38Electrical checkElectrical check of TM#1 with Ta#38 at
the conditioning station under vacuum. See
attached file for details.
 TM#1_Ta38_at_constat_elec_check.PDF 
  126   Monday, June 11, 2012, 14:41 David WangConditioning StationStandard OperationTM1Ta38Heat shield helium pressure testConnected leak detector to TM1 and CS vacuum
system. The vacuum readings on TM1 and CS:PNG1
1.3 xE-6 Torr, IG1 4.7xE-7torr, IG4(diagnostic
  
  127   Tuesday, June 19, 2012, 10:35 Travis CaveITWStandard OperationTM1Ta#38module moveTM#1 with Ta#38 moved from the conditioning
station to the west target station. Move
went well.
  
  128   Tuesday, June 19, 2012, 16:18 David WangITWStandard OperationTM1Ta38TM1connected in ITW
 

 Normal
  0

 
   
  
  134   Monday, June 25, 2012, 14:39 David WangITWStandard Operation  I moved 5 shielding blocks from ITE to ITW,and set up ventilation for ITW. ITW is
ready for taking proton beam now. All water
interlock checks for ITW are done. The ITW
  
  136   Tuesday, July 03, 2012, 10:50 David WangITEStandard OperationTM4 Disconnected TM4 in ITE.I disconnected TM4 in ITE this morning.
The window circuit and heat shield circuit
had been purged. The general field inside
  
  137   Tuesday, July 03, 2012, 12:26 Travis CaveSouth Hot-CellStandard OperationTM4SiC#27module moveTM#4 with SiC#27 moved from the east station
to the south hot cell. Fields at East MAA
were 127mSv/hr and the fields at the south
  
  138   Wednesday, July 04, 2012, 11:33 Travis CaveSouth Hot-CellStandard OperationTM4UO#3Electrical checkElectrical check of TM#4 with  UO#3
attached at the south hot cell see attached
PDF for full results. It has been noted that
 TM#4_UO#3_elec_check.PDF 
  139   Wednesday, July 04, 2012, 13:18 David WangConditioning StationStandard OperationTM4uo#3leak check on heat shield circuit

    
        

           
  
  
  140   Wednesday, July 04, 2012, 14:16 Travis CaveConditioning StationStandard OperationTM4UO#3module moveTM#4 with UO#3 moved from the south hot
cell to the conditioning station. The fields
of the module at the hot cell was 74.4 mSv/hr.
  
  141   Friday, July 06, 2012, 09:24 Travis CaveConditioning StationStandard OperationTM4UO#3Electrical checkElectrical check of the target was done
at the conditioning station under vacuum,
see attached file for details.
 TM#4_UO#3_elec_check_under_vac.PDF 
  142   Friday, July 06, 2012, 11:34 Travis CaveSpent Target VaultStandard Operation SiC#27Spent target moveSiC#27 has been moved from the south hot
cell to the spent target vault. Target was
placed in pail #96, placed in slot 3A, the
 Vault_Storage_July_6_2012.pdf 
  143   Friday, July 06, 2012, 14:38 David WangConditioning StationStandard OperationTM4UO#3TM4 UO#3 target heat shield helium pressure check is done.Connected leak detector to TM4 and CS vacuum
system. The vacuum readings  on TM4 and CS:PNG4
3.6 xE-6 Torr, IG1 2.3xE-6torr, IG4(diagnostic
  
  144   Monday, July 09, 2012, 10:51 Travis CaveITEStandard OperationTM4UO#3module moveTM#4 with UO#3 from the conditioning station
to the east target station. Move went well.
  
  145   Monday, July 09, 2012, 16:08 David WangITEStandard OperationTM4UO#3ITM4 in ITE connected and pumping down
 

 Normal
  0

 
   
  
  150   Thursday, July 26, 2012, 08:33 David WangITEStandard OperationTM4 I moved 5 shielding blocks from ITW to ITE thisTuesday morning .  All water interlock checks for ITE
had been done. The ITE water signals  strength
and frequency(Espcially on MSP circuit) had
  
  151   Tuesday, July 31, 2012, 09:52 David WangITWStandard OperationTM1Ta38TM1 disconnected in ITWI disconnected TM1 in ITW.  Heat shield
line has been purged .
  
  152   Tuesday, July 31, 2012, 10:50 Travis CaveSouth Hot-CellStandard OperationTM1Ta#38module moveTM#1 with Ta#38 has been moved from the
west target station to the south hot cell,
no problems with the move.
  
  153   Tuesday, July 31, 2012, 12:24 chad fisherSouth Hot-CellStandard OperationTM1UCx#4UCx#4 InstalledStarting at 11:00 am and finishing at 12:10
Ucx#4 previous target was removed and UCx#4
installed and leak checked on TM1.
  