Entry  Sunday, October 06, 2013, 17:08, Friedhelm Ames, Conditioning Station, Development, TM3, NiO#2, trip of all power supplies 

All power supplies tripped on high conductivity of the cooling water < 5 MOhm, It is not clear if this was caused by a spark or vice versa. According to the strip tool for this signal the resistance of the water went up. There might be a fault in this signal. I do not have permission to force this signal so I keep the heaters off. We should revisit the interlock conditions, this signal should not be included in the interlocks for the heaters. Both target and tube seem to be still o.k. As I do not want to destroy the target I keep the heaters off and restart the high voltage only.

Entry  Sunday, October 06, 2013, 20:28, Friedhelm Ames, Conditioning Station, Standard Operation, TM3, NiO#2, turbo pumps stopped 

vacuum readings before stopping

IG1: 7.4e-7 T

IG2 3.8 e-6 T

IG1S 1.95 e-6 T

Entry  Monday, October 07, 2013, 12:06, Travis Cave, ITE, Standard Operation, TM3, NiO#2, module move 

TM#3 has been moved from the conditioning station to the east target station, move went well.

Entry  Tuesday, October 22, 2013, 14:23, Anders Mjos, ITE, Standard Operation, TM3, NiO#2, Padlle wheel frequency measurements ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow.pdf

as measured today in the electrical room by David and Anders

Entry  Friday, October 25, 2013, 13:39, Anders Mjos, ITE, Standard Operation, TM3, NiO#2, Padlle wheel frequency measurements ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_wITW-TM4.pdf

with TM4 in ITW as measured today in the electrical room by David and Anders.

 

Entry  Thursday, October 31, 2013, 11:38, Anders Mjos, ITE, Standard Operation, TM3, NiO#2, Padlle wheel frequency measurements ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_EOB.pdf

with TM4 in ITW as measured today in the electrical room by David and Anders.

Entry  Tuesday, November 19, 2013, 10:52, Travis Cave, South Hot-Cell, Standard Operation, TM3, NiO#2, module move 

TM#3 with NiO#2 moved from ITE to the south hot cell.

Entry  Wednesday, November 20, 2013, 08:50, chad fisher, South Hot-Cell, Standard Operation, TM3, NiO#2, NiO#2 removed TM3_20131120.jpgTM3_20131120_2.jpg

NiO#2 has been removed from TM3

Entry  Thursday, November 21, 2013, 12:12, Anders Mjos, South Hot-Cell, Standard Operation, TM3, NiO#2, End of beam target inspection - ANODE does not hold 250V 

The target was inspected by Chad and Anders in the Hot Cell. Electrical megger tests were done during the assembly. It was found that Insulators No 3 (ITD0311) and No 2 (ITD0310) failed to hold voltage after the run.

  [V] [kOhm]
ANODE - HS 40 21
ANODE - TGT 100 55
HS - TGT 100 55
Lid removed    
ANODE - HS 40 21
ANODE - TGT 90 41
HS - TGT 100 55
Target removed    
ANODE - HS 245 139
No 3 Ins - TBHT 0 0
No 2 Ins 110 64
No 2 Ins removed    
ANODE - HS 540 OL

EE to HS was measured OL at 1000  V.

Photos can be found on DocuShare

 

 

Entry  Friday, November 22, 2013, 10:29, Travis Cave, Spent Target Vault, Standard Operation, , NiO#2, Spent target move Vault_Storage_November_22_2013.pdf

NiO#2 has been moved from the south hot cell into spent target storage. It was placed in pail 111 in slot 3C of the storage vault. It was 76.4mSv/hr upon removal from the south hot cell.

Entry  Wednesday, September 05, 2012, 11:55, Travis Cave, Conditioning Station, Standard Operation, TM4, NiO#1, module move 

TM#4 with NiO#1 has been moved from the south hot cell to the conditioning station. Move went well.

Entry  Wednesday, September 05, 2012, 14:40, Travis Cave, Conditioning Station, Standard Operation, TM4, NiO#1, Electrical check TM#4_NiO#1.PDF

See attached PDF for details. 60kV Common to the target is low at 343k but I've been told will work. Test will be done again on Friday after it has sat a few days under vacuum.

Entry  Friday, September 07, 2012, 10:37, Travis Cave, Conditioning Station, Standard Operation, TM4, NiO#1, Electrical check TM#4_NiO#1a.PDF

Electrical check of the TM#4 with NiO#1 was done again today. see attached file for results.

Entry  Tuesday, October 09, 2012, 11:17, Bevan Moss, ITE, Standard Operation, TM4, NiO#1, Module Move 

 TM4 with NiO#1 was moved from ITE to the SHC today. The move went well with no issues.

Entry  Wednesday, October 24, 2012, 11:53, Travis Cave, Spent Target Vault, Standard Operation, , NiO#1, Spent target move Vault_Storage_October_24_2012.pdf

The NiO #1 spent target was placed into storage today. It is in pail number 01 (101 on Vault Status page) and located in slot 4A of the vault. It was 35.5 mSv/hr upon removal from the south hot cell. See attached PDF for vault details.

Entry  Tuesday, September 04, 2012, 14:34, David Wang, South Hot-Cell, Standard Operation, TM4, NiO #1, TM4 heat shield circuit leak check with NiO#1 target 

Chad and i did a leak check on TM4 heat shield circuit with new NiO#1 target installed. It took about 40 mins(much longer than usual) to pump down the circuit to leak rate 0.6x E-9atm.cc/sec and 0.0x E-4 torr o leak detector.

All vacuum lines and joints which connected to the leak detector had been helium sprayed and they are leak  tight.Chad sprayed helium on each VCR joints for 2 seconds every time. During 1min waiting time, there is no any response on leak detector. Chad repeated same test again for double checking and we got same result. Chad finally flushed the helium around the target heat shield for 10 seconds.we waited for 1minute and found no response on the leak detector. The heat shield circuit is leak tight at this stage. I will do a helium pressure test on this circuit when TM4 is in CS and under vacuum.

Entry  Wednesday, September 05, 2012, 14:36, chad fisher, South Hot-Cell, Standard Operation, TM4, NiO #1, UOx removal NiO installation 

UOx was removed from TM4 yesterday and NiO#1 installed.

Video was taken.

Main stand-off insulators continue to deteriorate.

Entry  Friday, September 07, 2012, 08:54, David Wang, Conditioning Station, Standard Operation, TM4, NiO #1, TM4 NiO #1 target heat shield helium pressure check is done. 

leak detector pumped down to 0.0xE-9 atm.cc/sec, and 0.0xE-4 torr. All high vacuum gauge readings at CS and TM4 are at low -6 range from 2.2xE-6torr to 4.2x E-6 torr. Applied 80 psi helium  to heat shield circuit for 5minutes and there is no any response on leak detector. The heat shield circuit is leak tight.

Entry  Wednesday, September 12, 2012, 07:00, David Wang, ITE, Standard Operation, TM4, NiO #1, ITM4 in ITE connected and pumping down 

TM4 had been connected in ITE. Six turbo pump had been started . thepumpming diwn is very good so far. The water interlock check on ITE and TM4 had been finished and everything is good.All water signals are strong and constant by visually checking.

Entry  Tuesday, October 09, 2012, 10:35, David Wang, ITE, Standard Operation, TM4, NiO #1, Disconnected TM4 in ITE. 

I disconnected TM4 in ITE this morning. The heat shield circuit has been purged with air.