Message ID: 471     Entry time: Thursday, September 26, 2013, 14:47
Author: Bevan Moss 
Category: Conditioning Station 
Type: Maintenance 
Module: TM3 
Target/Number: NiO#2 
Subject: Water pumps turned on 

 The water pumps for the conditioning station were turned on at ~11:45. It took longer to start the conditioning station as the air from the leak test had to be bled off and the make up water tank refilled. The valves on the water supply line were closed slightly to make up for the fact the water cooled power supply has been removed. DIF2 was installed by Maico so we can measure the flow in the primary side.