835
|
Monday, January 26, 2015, 09:36 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Alignment | TM2 tray alignment was confirmed with the
alignment tray this morning:
Front target 0.000 vertically, 0.000 |
|
836
|
Wednesday, January 28, 2015, 10:42 |
Anders Mjos | Conditioning Station | Maintenance | TM2 | | TCS shut down for site wide power outage | |
|
837
|
Thursday, January 29, 2015, 11:31 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Build | On Tuesday morning I attempted to complete
assembly of the source tray for TM2 however
discovered that 3 1/4-20 x 0.25 titanium |
|
838
|
Monday, February 02, 2015, 09:59 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray Build | Missing heli coils installed this morning.
Threads had to be chased with tap
for 1/4-20 heli coil and missing countersinks |
|
839
|
Monday, February 02, 2015, 14:06 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Tray build | Master target jig installed to locate attachment
bracket ITA3389 as well as conductor insulator
block b (aluminum / for soldering version) |
 |
858
|
Thursday, March 12, 2015, 09:48 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | No target | Module move | TM#2 with no target and no source tray
has been moved from the conditioning station
to the north east silo. |
|
879
|
Tuesday, March 31, 2015, 11:36 |
chad fisher | South Hot-Cell | Development | TM2 | | TM2 Optics Tray Complete | TM2 optics tray is complete.
Master alignment tray: 0 up/down,
0 left/right |
  |
893
|
Tuesday, April 21, 2015, 13:01 |
Grant Minor | ITW | Development | TM2 | | TM2 MK4 Optics Tray - banana plug bore modification (on bench) | The MK4 optics tray prepared for TM2 (as
per ITA6082) had an undersized bore for the
banana plug, making insertion of the plug |
   |
899
|
Monday, April 27, 2015, 16:12 |
Keith C Ng | South Hot-Cell | Development | TM2 | | Ceramic Standoffs in TM2 source tray steerer assembly | On drawing ITA6008 for the Encole 0.5"
ceramic standoffs there is a note to match
pairs of ceramics to within +/-0.001". |
|
900
|
Monday, April 27, 2015, 17:09 |
Grant Minor | ITE | Development | TM2 | | TM2 - New Source Tray - Water Block Seal Groove Inspection Report | The water blocks soldered to the TM2 cooling
lines (see Ref. Assy. ITA6144) were inspected.
See attached inspection reports and |
   |
906
|
Thursday, April 30, 2015, 08:50 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | No target | Module move | TM#2 with no source tray has been moved
from the north east silo to the south hot
cell. |
|
907
|
Friday, May 01, 2015, 08:27 |
chad fisher | South Hot-Cell | Repair | TM2 | | Containment Box Removal | Containment box has been removed in preparation
for wire replacement. |
|
908
|
Friday, May 01, 2015, 13:48 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 update | Target Hall Scheduled Activities
April 07 - June 26 2015 update.
2015-05-01. All TH scheduled |
 |
910
|
Tuesday, May 05, 2015, 10:57 |
chad fisher | South Hot-Cell | Repair | TM2 | | TM2 Wiring | Old wiring was removed yesterday, new wiring
run thru the vacuum chase. Old IMG gauge
removed today, new cable trays installed |
 |
911
|
Wednesday, May 06, 2015, 14:30 |
Travis Cave | South Hot-Cell | Repair | TM2 | No target | Wiring of TM#2 | Wires for TM#2 steering elements, and png
gauge have been run down to the containment
box level. Chad has placed them in the little |
 |
912
|
Thursday, May 07, 2015, 11:02 |
Travis Cave | South Hot-Cell | Repair | TM2 | No target | Wiring of TM#2 | Wires in TM#2 have been terminated at the
top of the module. |
|
914
|
Monday, May 11, 2015, 11:20 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Target Hall Scheduled Activities April 07 - June 26 2015 | The schedule has some changes due to
new TM2 source tray coil cooling line leaking
at test stand. Now,It is re-scheduled in |
6x |
915
|
Wednesday, May 13, 2015, 13:55 |
chad fisher | South Hot-Cell | Repair | TM2 | | Shutter removal | TM2 has been successfully de-shuttered.
All went pretty much according to
plan except I had to remove one fastener |
 |
917
|
Tuesday, May 26, 2015, 11:49 |
Grant Minor | Assembly/Bench Test | Repair | TM2 | | TM2 New Source Tray - Braze & Solder Report - 22 May 2015 | Hello,
For reference, I have attached a list |
6x |
918
|
Tuesday, May 26, 2015, 14:34 |
chad fisher | South Hot-Cell | Repair | TM2 | | Shutter replacement | The shutter in TM2 was successfully replaced
today.
New lock washer and nut were installed |
|