2555
|
Wednesday, March 27, 2024, 09:49 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 has been moved to SHC from silo. | Tm3 has been moved to SHC from silo. the
move is smooth. |
|
2557
|
Thursday, March 28, 2024, 09:26 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 has been moved from SHC to silo. | Tm3 has been moved from SHC to silo.
The move is smooth. |
|
2558
|
Wednesday, April 03, 2024, 10:48 |
chad fisher | South Hot-Cell | Maintenance | | | SE Manipulator wrist swap | On April 2, 2024 the wrist on the SE manipulator
of the SHC (Serial # 7986) was swapped with
a rebuild unit originally from SW position |
|
2561
|
Thursday, April 11, 2024, 06:07 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 was moved from silo to SHC yesterday. | Tm3 was moved from silo to SHC yesterday.
the move is smooth. |
|
2562
|
Thursday, April 11, 2024, 06:27 |
David Wang | South Hot-Cell | Development | TM3 | | TM3 new source tray was transferred into SHC on this Tuesday. | TM3 new source tray was transferred into
SHC on this Tuesday. one hook arm of transfer
jig is very close to optic tray tube when |
|
2565
|
Friday, April 19, 2024, 10:44 |
David Wang | South Hot-Cell | Development | TM3 | | TM3 water lines helium spray leak check at SHC. | TM3 water lines helium spray leak check
at SHC is done. No leak has been found on
all lines. seeattachment |
|
2566
|
Tuesday, April 23, 2024, 17:34 |
Carla Babcock | South Hot-Cell | Repair | TM3 | | TM3 wire pulling | Wires were pulled in TM3 and service cap
was closed up again:
Einzel lens wire (30kV kapton), routed |
|
2570
|
Friday, April 26, 2024, 13:22 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | TM4 has been moved from SMP to SHC. | TM4 has been moved from SMP to SHC. Adam
and I did the move. the move is smooth. |
|
2573
|
Tuesday, April 30, 2024, 08:00 |
Frank Song | South Hot-Cell | Standard Operation | TM4 | Lp-Febiad empty | electrical check/leak check | David Wang made E/L checking before
module moving to ITW. read attachment pls. |
|
2576
|
Wednesday, May 01, 2024, 14:51 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 has been moved form TCS to SHC. | Travis and I moved TM3 from TCS to SHC
this afternoon. The move is smooth. |
|
2579
|
Thursday, May 02, 2024, 14:58 |
David Wang | South Hot-Cell | Standard Operation | TM3 | UCx#44 | TM3 with UCx#44 electrical check and leak check. | TM3 with UCx#44 electrical check and leak
check are good. see attachment.
HS line 70 psi helium pressure test |
|
2580
|
Thursday, May 02, 2024, 15:23 |
David Wang | South Hot-Cell | Development | TM3 | | Leak check on TM3 new containment box window line VCR fittings. | After new containment box installation
on TM3, Chad and I did a helium spray leak
check on two VCR fittings on front side water |
|
2595
|
Wednesday, May 22, 2024, 12:32 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UCx#45 | TM4 has been moved from SHC to TCS. | TM4 has been moved from SHC to TCS. the
move is smooth. |
|
2596
|
Wednesday, May 22, 2024, 12:43 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UCx#45 | electrical check and leak check were done on TM4 UCx#45 target at SHC. | electrical check and leak check were done
on TM4 UCx#45 target at SHC. everything
is ok. See attachment |
|
2599
|
Friday, May 24, 2024, 08:10 |
chad fisher | South Hot-Cell | Standard Operation | TM4 | UCx#45 | UCx#45 Installation | On Wednesday, May 22, 2024 UCx#45 was installed
on TM4 in the SHC. Installation was normal
other then minor issue with the multipin |
|
2604
|
Tuesday, June 04, 2024, 11:44 |
Carla Babcock | South Hot-Cell | Development | | empty LP FEBIAD | investigation of cathode short on empty LP FEBIAD | On May 30 Aaron, Chad and I removed the
empty LP FEBIAD target from the SHC into
the anteroom to attempt to find out the source |
|
2611
|
Friday, June 14, 2024, 11:55 |
David Wang | South Hot-Cell | Standard Operation | TM3 | UCx#44 | TM3 UCx#44 after operation electrical check at SHC | TM3 UCx#44 after operation electrical check
at SHC . see attachment.
Carla: Looks like the short on the |
|
2616
|
Tuesday, June 18, 2024, 11:59 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Tm3 electrical check without target. | Tm3 electrical check without target is
done. Everything is good including 2 x 5
pin connectors( all OL at 250 V to 60 KV |
|
2620
|
Wednesday, June 19, 2024, 14:11 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | TM3 has been moved from SHC to TCS. | TM3 has been moved from SHC to TCS.The
move is smooth. |
|
2621
|
Wednesday, June 19, 2024, 14:16 |
David Wang | South Hot-Cell | Standard Operation | TM3 | SiC #46 | Tm3 electrical check with SiC#46 target at SHC | Tm3 electrical check with SiC#46 target
and HS line helium spray check at SHC. were
done. everything is good. see attachment. |
|